PJD Group Pty Ltd t/as Esk Caravan Park v Both & Ors

Link copied
Case Copied 22 min read

CITATION:

PJD Group Pty Ltd t/as Esk Caravan Park v Both & Ors [2017] QCATA 94

PARTIES:

PJD Group Pty Ltd t/as Esk Caravan Park
(Appellant)

v

Allan Both
Jennifer Both
David Gilmore
Alison Gilmore
Kevin Goldsworthy
Ann Goldsworthy
Douglas Green
Gayle Green
Allan Paxman
Pamela Paxman
Peter Raine
Christine Joy Raine
Jan Rouw
Ineke Rouw

(Respondents)

APPLICATION NUMBER:

APL201-16

MATTER TYPE:

Appeals

HEARING DATE:

On the papers

HEARD AT:

Brisbane

DECISION OF:

Judge Sheridan, Acting President

Member Allen

DELIVERED ON:

27 September 2017

DELIVERED AT:

Brisbane

ORDERS MADE:

1.   The appeal is dismissed.

2.   The appellant file and serve its submissions on costs by 4:00pm on Wednesday, 11 October 2017.

3.   The respondents file and serve their submissions on costs by 4:00pm on Wednesday, 25 October 2017.

CATCHWORDS:

ENVIRONMENT AND PLANNING – ENVIRONMENTAL PLANNING – DEVELOPMENT CONTROL – CONTROL OF PARTICULAR MATTERS – RESIDENTIAL – CARAVAN PARKS AND MOVEABLE DWELLINGS – where the park owner proposed to impose charges on the home owners under s 77 of the Manufactured Homes (Residential Parks) Act 2003 (Qld) (MHRPA) – where the home owners made an application to the Tribunal for an order declaring the proposed rules unreasonable – where the Tribunal determined that the park owner was unable in or through the park rules to impose charges on home owners which were note provided for in the written and signed site agreement – where the Tribunal determined that in any event, the proposed park rules were unreasonable and void – where the park owner appealed the decision of the Tribunal to the Appeal Tribunal – whether the terms of s 77 of the MHRPA permit a park owner to impose charges on the home owners through the park rules

Acts Interpretation Act 1954 (Qld), s 14A
Manufactured Homes (Residential Parks) Act 2003 (Qld), s 4, s 25, s 77, s 86

Fearnley v Finlay [2014] 2 Qd R 392, [2014] QCA 155, cited
Gilmore & Ors v Lawson [2014] QCAT 620, distinguished
IW v The City of Perth (1997) 191 CLR 1, [1997] HCA 30, cited
Mills v Meeking (1990) 169 CLR 214, [1990] HCA 6, cited
Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355, [1998] HCA 28, cited

REPRESENTATIVES:

APPELLANT:

PJD Group Pty Ltd represented by HopgoodGanim Lawyers

RESPONDENTS:

APPEARANCES:

The respondents were self-represented

This appeal was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).

REASONS FOR DECISION

  1. This appeal concerns whether the terms of s 77 of the Manufactured Homes (Residential Parks) Act 2003 (Qld) (MHRPA) permit a park owner to impose charges on home owners through the park rules.

The Facts

  1. PJD Group Pty Ltd own and operate the Esk Caravan Park containing sites utilised for manufactured homes, caravans, campers and tourists. The respondents are the owners of manufactured homes located at the park and have site agreements…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read PJD Group Pty Ltd t/as Esk Caravan Park v Both & Ors and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] QCATA 94
Decision Date

CaseChat Overview and Summary

PJD Group Pty Ltd, trading as Esk Caravan Park, sought to impose certain charges on homeowners in the park under section 77 of the Manufactured Homes (Residential Parks) Act 2003 (Qld). The homeowners contested the charges, applying to the Tribunal for an order declaring the proposed rules unreasonable. The Tribunal ruled that the park owner could not impose charges on homeowners that were not specified in the written and signed site agreement, and in any event, found the proposed park rules unreasonable and void. The park owner appealed the Tribunal's decision to the Appeal Tribunal.

The central legal issue in the appeal was whether section 77 of the Manufactured Homes (Residential Parks) Act 2003 (Qld) allowed the park owner to impose charges on homeowners through the park rules. The appeal hinged on the interpretation of section 77 and whether it permitted the imposition of charges outside the terms of the written and signed site agreement. The court needed to consider the interaction between the statutory provisions and the contractual terms of the site agreement, and whether the proposed charges were consistent with the legislative intent.

The Appeal Tribunal found that section 77 of the Act did not permit the imposition of charges on homeowners that were not provided for in the written and signed site agreement. The court emphasised the importance of the contractual terms agreed upon by the parties, and that any additional charges must be explicitly outlined in the site agreement. The Tribunal's determination that the proposed park rules were unreasonable and void was upheld, as the charges did not align with the statutory framework and the contractual obligations. Consequently, the appeal was dismissed.

The Appeal Tribunal dismissed the appeal, thereby affirming the Tribunal's decision. The appellant was required to file and serve its submissions on costs by 4:00pm on Wednesday, 11 October 2017, and the respondents were required to file and serve their submissions on costs by 4:00pm on Wednesday, 25 October 2017. This ruling reinforced the necessity for park owners to adhere to the terms of the written and signed site agreements and the statutory provisions when imposing charges on homeowners.

Orders

Orders of the court

1. The appeal is dismissed.

2. The appellant file and serve its submissions on costs by 4:00pm on Wednesday, 11 October 2017.

3. The respondents file and serve their submissions on costs by 4:00pm on Wednesday, 25 October 2017.

Background

Background to the litigation

PJD Group Pty Ltd t/as Esk Caravan Park (the appellant) operates a caravan park where residents own and occupy manufactured homes. Under the terms of the Manufactured Homes (Residential Parks) Act 2003 (Qld) (MHRPA), the appellant sought to impose charges on the home owners by amending the park rules. The home owners contested the proposed charges, arguing that the charges were not provided for in their signed site agreement. They made an application to the Tribunal under section 77 of the MHRPA for an order declaring the proposed rules unreasonable. The Tribunal found that the appellant could not impose charges on home owners through the park rules if those charges were not provided for in the written and signed site agreement. Furthermore, the Tribunal determined that the proposed park rules were unreasonable and void. The appellant appealed this decision to the Appeal Tribunal.

The case originated in the Tribunal, where the home owners applied for a declaration that the proposed park rules were unreasonable. The Tribunal ruled in favour of the home owners and declared the proposed park rules unreasonable and void. Dissatisfied with this decision, the appellant appealed to the Appeal Tribunal. The Appeal Tribunal was tasked with reviewing the decision of the Tribunal and determining whether the appellant could impose charges on home owners through the park rules under section 77 of the MHRPA.

Decision

Reasons for decision

Issues
1. Whether the terms of section 77 of the MHRPA permit a park owner to impose charges on home owners through the park rules.
2. Whether the proposed park rules are unreasonable and void.

Held
1. The court held that the terms of section 77 of the MHRPA do not permit a park owner to impose charges on home owners through the park rules unless those charges are provided for in the written and signed site agreement.
2. The court held that the proposed park rules were unreasonable and void.

Ratio Decidendi

Legal Principle Established

The court examined the language and intent of section 77 of the MHRPA and found that it does not allow a park owner to impose charges on home owners that are not stipulated in the written and signed site agreement. The court noted that any charges must be expressly agreed upon by the parties, and therefore, the proposed charges that were not included in the site agreement were impermissible. Furthermore, the court found the proposed rules to be unreasonable and void, as they sought to impose charges outside the scope of the written agreement, which is not authorized by the MHRPA. The court's decision reinforces the principle that charges must be clearly outlined and agreed upon by both parties in the site agreement to be enforceable. The ratio decidendi is that charges not specified in the written and signed site agreement cannot be imposed on home owners under section 77 of the MHRPA, and any such attempt renders the park rules unreasonable and void. The court's interpretation of section 77 and its application to the facts of this case provides clarity on the permissible scope of charges under the MHRPA, establishing a binding principle for future cases involving similar issues.