| CITATION: | Piper v Hookham Constructions Pty Ltd [2014] QCAT 215 |
| PARTIES: | Darryl Piper (Applicant) |
| v | |
| Hookham Constructions Pty Ltd (Respondent) |
| APPLICATION NUMBER: | BDL121-13 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | 15 April 2014 |
| HEARD AT: | Brisbane |
| DECISION OF: | Senior Member Oliver |
| DELIVERED ON: | 21 May 2014 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. Darryl Piper pay to Hookham Constructions Pty Ltd the sum of $95,516.63 by 30 June 2014. |
| CATCHWORDS: | BUILDING CONTRACT – TERMS AND EXTENSION OF TIME – TERMINATION – where contract for the construction of three units on a single block of land – where contract stipulated an amount for delay damages – where amount inserted by applicant – whether the parties agreed to the daily rate – where contract provided for specific construction period for the three units to be built together – where agreement to split the project to build one unit first and then two units – where original time for construction exceeded the time in the contract – whether the parties agreed to an extension of time for the build – where payment schedule changed to reflect the change in the construction arrangements – where applicant sought to terminate the contract for substantial breach – whether the respondent in substantial breach - whether respondent entitled to balance monies owed under the contract –whether the respondent entitled to be paid prime cost items for food and accommodation when not included in the “inclusions” to the contract. |
APPEARANCES and REPRESENTATION (if any):
| APPLICANT: | Mr Piper in person |
| RESPONDENT: | Mr Hookham in person |
REASONS FOR DECISION
Mr Piper owned a house at 4 Leichhardt Drive, Moranbah in the State of Queensland. On 13 May 2011, he entered into a contract with Hookham Constructions Pty Ltd for the construction of three units on the land. The existing house was to be demolished to make way for the three new units.
Mr Piper was living in the house when the contract was signed. He would use the house when in Moranbah for work. The total contract price for the three units was $904,813 inclusive of GST. The contract provided that the works must reach practical completion with 210 days. The work commenced on 11 July 2011 and the actual practical completion date was either 6 February 2013 or 20 February 2013. This was well in excess of the original 210 days provided for in the contract.
When the project was completed, Hookham Constructions delivered an invoice for the final payment under the contract for $87,278. Mr Piper does not dispute that this is the final payment. Despite that, Mr Piper did not pay the final payment. Instead, he filed an application in the Tribunal for $87,278.12 on 15 May 2013, which, according to the statement of claim attached to the application, he claimed was owed $85,868.08 for what might be described as late completion damages under item 11 of the contract for $76,000, plus interest of $9,578.08 and the filing fee. The basis of this claim was that the work was…
Continue reading Piper v Hookham Constructions Pty Ltd
Sign in free to access the full text
- AGLC
- Piper v Hookham Constructions Pty Ltd [2014] QCAT 215
- Case
- [2014] QCAT 215
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.