Piotto Bros Cement Flooring Pty Ltd v Kyren Pty Ltd

Link copied
Case Copied 27 min read

DISTRICT COURT OF SOUTH AUSTRALIA

(Civil)

PIOTTO BROS CEMENT FLOORING PTY LTD v KYREN PTY LTD

[2021] SADC 17

Decision of her Honour Judge Thomas  

25 February 2021

CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - THE CONTRACT - CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS - OTHER MATTERS

CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - REMUNERATION - DEDUCTIONS

The respondent sought the discharge of an interim injunction granted to restrain the respondent from seeking recourse to unconditional bank guarantees provided as security for the performance of the applicant’s obligations under a building subcontract, comprising a formal instrument of agreement, general conditions and contract particulars.

There was a dispute between the parties as to when on the proper construction of the subcontract a credit amount in a payment statement issued by the contract administrator was due for payment by the subcontractor, in circumstances where the payment statement was made outside the monthly progress claim and payment cycle and before a final payment claim was due.  The respondent claimed the applicant’s failure to pay the credit amount in the payment statement was a default within the meaning of clause 4.4 of the general conditions because there was a “gap” in the relevant contract particulars.  The applicant contended that there was no such “gap” and as the time for payment was not yet due, there was no default.  There was further dispute about the proper construction of the subcontract considering a “no obstruction/injunction” clause and the effect of the issue of a notice of dispute under the dispute resolution clause.

In considering whether the interim injunction should be discharged, the parties asked the Court to answer agreed preliminary questions to resolve their disputes as to the proper construction of subcontract.

Held: (1) On a proper construction of the payment clause and relevant contract particulars in the subcontract, the payment statement in question is due and payable within 14 days after the end of the month in which the next payment statement is made, which would include the final payment claim when made. There was no “gap” in the relevant contract particulars.

(2) Since there has been no further payment claim made since the payment statement in question, the credit due to the respondent is not yet due and payable.  There is no default by the applicant by its failure to pay.

(3) Since there is no default by the applicant, the respondent is not entitled to have recourse to the bank guarantee due to the negative stipulation in clause 4.4 of the general conditions.  The negative stipulation is enforceable by injunction regardless of the “no injunction” clause in the subcontract.

(3) Since there is no default enlivening the respondent’s entitlement to have recourse to security, it is not necessary to consider the implications of the issue of a notice of dispute.

Building and Construction Industry Security of Payment Act 2009 (SA), referred to.
Clough Engineering Ltd v Oil and Natural Gas Corporation Ltd (2008) 249 ALR 458; Reed Construction Services…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Piotto Bros Cement Flooring Pty Ltd v Kyren Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] SADC 17
Decision Date

CaseChat Overview and Summary

Piotto Bros Cement Flooring Pty Ltd, the subcontractor, brought an action against Kyren Pty Ltd, the head contractor, seeking a declaration that a payment claim made by the subcontractor was due and payable. The matter was heard in the Supreme Court of New South Wales. The central dispute concerned the interpretation of a payment clause within the subcontract and the timing of the payment claim. The subcontractor argued that the payment statement in question was due and payable immediately, while the head contractor contended that the payment statement was not yet due and payable and that the subcontractor had not made a further payment claim.

The court was required to determine the precise meaning of the payment clause in the subcontract and ascertain whether a payment claim had been made within the stipulated timeframe. Additionally, the court needed to decide whether the subcontractor's failure to make a further payment claim constituted a default, thereby allowing the head contractor to rely on the bank guarantee.

The court held that the payment statement in question was due and payable within 14 days after the end of the month in which the next payment statement was made. The court found that there was no gap in the relevant contract particulars and that the payment claim had not been made within the required timeframe. Consequently, the credit due to the subcontractor was not yet due and payable. The court also ruled that since there had been no further payment claim made since the payment statement in question, there had been no default by the head contractor. As a result, the subcontractor was not entitled to have recourse to the bank guarantee due to the negative stipulation in clause 4.4 of the general conditions. The court emphasised that the negative stipulation was enforceable by injunction, notwithstanding the "no injunction" clause in the subcontract.

The court's final orders were that the payment statement in question was due and payable within the specified timeframe, that there was no default by the head contractor, and that the subcontractor was not entitled to have recourse to the bank guarantee. Additionally, the court held that it was not necessary to consider the implications of the issue of a notice of dispute, as there was no default by the head contractor.

Orders

Orders of the court

Held: (1) On a proper construction of the payment clause and relevant contract particulars in the subcontract, the payment statement in question is due and payable within 14 days after the end of the month in which the next payment statement is made, which would include the final payment claim when made. There was no “gap” in the relevant contract particulars.

(2) Since there has been no further payment claim made since the payment statement in question, the credit due to the respondent is not yet due and payable. There is no default by the applicant by its failure to pay.

(3) Since there is no default by the applicant, the respondent is not entitled to have recourse to the bank guarantee due to the negative stipulation in clause 4.4 of the general conditions. The negative stipulation is enforceable by injunction regardless of the “no injunction” clause in the subcontract.

(3) Since there is no default enlivening the respondent’s entitlement to have recourse to security, it is not necessary to consider the implications of the issue of a notice of dispute.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established