| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL COURT
TECHNOLOGY ENGINEERING AND CONSTRUCTION LIST
S ECI 2017 00236
| PHHH INVESTMENTS NO 2 PTY LTD (ACN 602 191 506) | Plaintiff |
| v | |
| UNITED COMMERCIAL PROJECTS PTY LTD (ACN 110 860 360) | First Defendant |
| and | |
| HARRY McIVER | Second Defendant |
---
JUDGE: | RIORDAN J |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 17 January 2018 |
DATE OF JUDGMENT: | 31 January 2018 |
CASE MAY BE CITED AS: | PHHH Investments No 2 Pty Ltd v United Commercial Projects Pty Ltd |
MEDIUM NEUTRAL CITATION: | [2018] VSC 15 |
---
BUILDING CONTRACTS – Building and Construction Industry Security of Payment Act 2002 (Vic) – Whether an adjudication determination given after the period permitted under s 22(4) of the Act is invalid – Out of time determination is not invalid – Requirements of s 22(4) of the Act not jurisdictional.
BUILDING CONTRACTS – Building and Construction Industry Security of Payment Act 2002 (Vic) – Agreement to an extension und s 22(4) of the Act – Whether claimant’s offer to agree to an extension of time constituted an implied agreement – No implied agreement for extension of time.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr N J Phillpott | Noble Lawyers |
| For the First Defendant | Mr N A Andreou | MacPherson Kelley |
HIS HONOUR:
By Originating Process filed 4 October 2017, the plaintiff (‘PHHH’) seeks orders including an order in the nature of certiorari that the adjudication determination (‘the Determination’) purportedly made by the second defendant (‘the Adjudicator’) dated 7 August 2017 pursuant to s 23 of the Building and Construction Industry Security of Payment Act 2002 (‘the Act’) be quashed.
PHHH claims that the determination should be set aside on the ground that the Adjudicator committed jurisdictional error or erred in law by making the Determination in excess of the time permitted by s 22(4) of the Act.
The claim raises two questions, being:
(a)Did the emailed letter of 25 July 2017 from the solicitors for the first defendant (‘United Commercial Projects’) to the Adjudicator constitute an implied agreement to an extension of time within the meaning of s 22(4)(b) of the Act?
(b)If no, is a determination, which is made out of the time prescribed in s 22(4) (‘an out of time determination’), void?
In summary, for the reasons that follow, I have decided that:
(a)the emailed letter of 25 July 2017 from the solicitors for the first defendant (‘United Commercial Projects’) to the Adjudicator did not constitute agreement to an extension within the meaning of s 22(4)(b) of the Act; but
(b)the Determination is valid despite the fact that it was made after the time prescribed in s 22(4) of the Act.
Background
PHHH is the owner of a commercial building at 282–284 Victoria Street, Brunswick (‘the Site’), which is the site of a kindergarten and childcare centre.
United Commercial Projects is a construction company that undertakes both domestic and commercial construction work in Melbourne.
On or about 16 March 2016, PHHH and United Commercial Projects entered into…
Keep reading for free
Create a free CaseChat account to read PHHH Investments No 2 Pty Ltd v United Commercial Projects P... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] VSC 15
- Decision Date
CaseChat Overview and Summary
The court examined whether the requirements of section 22(4) of the Act were jurisdictional, and concluded they were not. It found that the adjudicator's determination was not invalid merely because it was issued late, provided the adjudicator had jurisdiction to make the determination. Regarding the extension of time, the court found no evidence of an implied agreement to extend the time for the issuance of the determination. The court held that the claimant's offer to agree to an extension of time did not constitute an implied agreement for an extension of time.
The court ruled that the adjudicator's determination was valid and enforceable despite being issued late. It further found that there was no implied agreement for an extension of time. The court ordered that the respondent pay the amount determined by the adjudicator, plus interest and costs.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi