PETER STANNARD HOMES PTY LTD and NG

Link copied
Case Copied 11 min read
JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
STREAM : COMMERCIAL & CIVIL
ACT : BUILDERS' REGISTRATION ACT 1939 (WA)
CITATION : PETER STANNARD HOMES PTY LTD and NG
[2007] WASAT 301
MEMBER : DR B DE VILLIERS (MEMBER)
HEARD : 23 OCTOBER 2007
DELIVERED : 23 NOVEMBER 2007
FILE NO/S : CC 846 of 2007
BETWEEN : PETER STANNARD HOMES PTY LTD
Applicant
AND
MAY CHEN NG
Respondent
Catchwords: 

Building disputes review - Error in law - What is meant by a delay in construction - Intent of the parties is clearly expressed in contract

Legislation:

Builders Registration Act 1939 (WA), s 41(1)

Result:

Application for leave to review the decision of the Building Disputes Tribunal succeeds

[2007] WASAT 301

Category: B

Representation:

Counsel:

Applicant : Mr S Pentony
Respondent : N/A

Solicitors:

Applicant : Hotchkin Hanly
Respondent : N/A

Case(s) referred to in decision(s):

Tangent Nominees Pty Ltd and Edwards & Anor [2005] WASAT 119
Wilson v Metaxas (1989) WAR 285

[2007] WASAT 301

REASONS FOR DECISION OF THE TRIBUNAL:

Summary of Tribunal's decision

1              The applicant sought leave to review a decision of the Building

Disputes Tribunal (BDT) pursuant to s 41(1) of the Builders Registration
Act 1939 (WA) (BR Act).

2              The applicant contended that the BDT erred in law in its decision

that the respondent was not liable to pay an additional sum due to the delay in commencement of construction of the house. The error would, if unreversed, cause a substantial injustice to the applicant.

3              The respondent contended that the BDT did not err in law and that

the delay was caused by the actions of the applicant. The applicant can therefore not claim an additional sum due to the delay. The respondent further contended that if it was necessary for the BDT to clarify its reasoning in regard to what caused the delay, the matter should be referred back to the BDT.

4              The Tribunal found that the BDT erred in law since the construction

it gave to the contract could not be substantiated. The contract allowed for the builder to increase the contract sum if a delay is suffered and the delay cannot be attributed to the failure of the builder to comply with an obligation arising under the contract.

Background

5              The application was lodged on 29 April 2007 and the first directions

hearing took place on 14 June 2007. At the first directions hearing, the Tribunal ordered the BDT to provide its reasons for decision, particularly in regard to the issue under consideration. The next directions hearing took place on 8 August 2007 at which further programming orders were made for the leave to review application to be heard.

6              The Tribunal explained to the parties that the application for leave to

review would be progressed in two phases. This was done in particular to assist the respondent who was not legally represented. The first step of the review process is aimed solely on the question whether leave to review should…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read PETER STANNARD HOMES PTY LTD and NG and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2007] WASAT 301
Decision Date

CaseChat Overview and Summary

In the case of Peter Stannard Homes Pty Ltd and NG, the dispute revolves around a building contract between the parties, specifically focusing on the issue of delay and its consequences. The matter was brought before the court for review of a decision made by the Building Disputes Tribunal. The tribunal had previously ruled on a complaint lodged by the respondent against the appellant regarding delays in the construction of a property.

The legal issues the court was required to decide primarily concerned the interpretation of the contract between the parties and the nature of any delay in construction. Key questions included whether the appellant had delayed the completion of the property and, if so, whether this constituted a breach of contract. The court also needed to determine the extent of any damages owed by the appellant to the respondent due to the delay. Additionally, the court had to consider whether the tribunal had erred in law by not adequately considering the intent of the parties as expressed in the contract.

The court found that the Building Disputes Tribunal had erred in its interpretation of the contract and the applicable law. The tribunal had failed to properly consider the intent of the parties as clearly expressed in the contract. In particular, the tribunal did not sufficiently account for the provisions that outlined the consequences of delays. The court concluded that the tribunal's decision was therefore flawed and required review. The court granted leave to review the tribunal's decision, indicating that the tribunal had not correctly applied the law in relation to the delay and its consequences. The matter was adjourned to a directions hearing to finalise the programming orders for the hearing.

Orders

Orders of the court

1. Leave is granted to review the decision of the Building Disputes Tribunal decision dated 1 May 2007 (Complaint No 16906/1&2). 2. The matter is adjourned to a directions hearing on 6 December 2007 at which programming orders for the hearing will be finalised.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.