| JURISDICTION | : | STATE ADMINISTRATIVE TRIBUNAL |
| STREAM | : | COMMERCIAL & CIVIL |
| ACT | : | BUILDERS' REGISTRATION ACT 1939 (WA) |
| CITATION | : | PETER STANNARD HOMES PTY LTD and NG [2007] WASAT 301 |
| MEMBER | : | DR B DE VILLIERS (MEMBER) |
| HEARD | : | 23 OCTOBER 2007 |
| DELIVERED | : | 23 NOVEMBER 2007 |
| FILE NO/S | : | CC 846 of 2007 |
| BETWEEN | : | PETER STANNARD HOMES PTY LTD Applicant |
| AND | ||
| MAY CHEN NG Respondent | ||
| Catchwords: |
Building disputes review - Error in law - What is meant by a delay in construction - Intent of the parties is clearly expressed in contract
Legislation:
Builders Registration Act 1939 (WA), s 41(1)
Result:
Application for leave to review the decision of the Building Disputes Tribunal succeeds
[2007] WASAT 301
Category: B
Representation:
Counsel:
| Applicant | : | Mr S Pentony |
| Respondent | : | N/A |
Solicitors:
| Applicant | : | Hotchkin Hanly |
| Respondent | : | N/A |
Case(s) referred to in decision(s):
Tangent Nominees Pty Ltd and Edwards & Anor [2005] WASAT 119
Wilson v Metaxas (1989) WAR 285
[2007] WASAT 301
REASONS FOR DECISION OF THE TRIBUNAL:
Summary of Tribunal's decision
1 The applicant sought leave to review a decision of the Building
Disputes Tribunal (BDT) pursuant to s 41(1) of the Builders Registration
Act 1939 (WA) (BR Act).2 The applicant contended that the BDT erred in law in its decision
that the respondent was not liable to pay an additional sum due to the delay in commencement of construction of the house. The error would, if unreversed, cause a substantial injustice to the applicant.
3 The respondent contended that the BDT did not err in law and that
the delay was caused by the actions of the applicant. The applicant can therefore not claim an additional sum due to the delay. The respondent further contended that if it was necessary for the BDT to clarify its reasoning in regard to what caused the delay, the matter should be referred back to the BDT.
4 The Tribunal found that the BDT erred in law since the construction
it gave to the contract could not be substantiated. The contract allowed for the builder to increase the contract sum if a delay is suffered and the delay cannot be attributed to the failure of the builder to comply with an obligation arising under the contract.
Background
5 The application was lodged on 29 April 2007 and the first directions
hearing took place on 14 June 2007. At the first directions hearing, the Tribunal ordered the BDT to provide its reasons for decision, particularly in regard to the issue under consideration. The next directions hearing took place on 8 August 2007 at which further programming orders were made for the leave to review application to be heard.
6 The Tribunal explained to the parties that the application for leave to
review would be progressed in two phases. This was done in particular to assist the respondent who was not legally represented. The first step of the review process is aimed solely on the question whether leave to review should…
Keep reading for free
Create a free CaseChat account to read PETER STANNARD HOMES PTY LTD and NG and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2007] WASAT 301
- Decision Date
CaseChat Overview and Summary
The legal issues the court was required to decide primarily concerned the interpretation of the contract between the parties and the nature of any delay in construction. Key questions included whether the appellant had delayed the completion of the property and, if so, whether this constituted a breach of contract. The court also needed to determine the extent of any damages owed by the appellant to the respondent due to the delay. Additionally, the court had to consider whether the tribunal had erred in law by not adequately considering the intent of the parties as expressed in the contract.
The court found that the Building Disputes Tribunal had erred in its interpretation of the contract and the applicable law. The tribunal had failed to properly consider the intent of the parties as clearly expressed in the contract. In particular, the tribunal did not sufficiently account for the provisions that outlined the consequences of delays. The court concluded that the tribunal's decision was therefore flawed and required review. The court granted leave to review the tribunal's decision, indicating that the tribunal had not correctly applied the law in relation to the delay and its consequences. The matter was adjourned to a directions hearing to finalise the programming orders for the hearing.
Orders
Orders of the court
1. Leave is granted to review the decision of the Building Disputes Tribunal decision dated 1 May 2007 (Complaint No 16906/1&2). 2. The matter is adjourned to a directions hearing on 6 December 2007 at which programming orders for the hearing will be finalised.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.