Peggy Patrick & Ors on behalf of Yurriyangem Taam; Maggie John & Ors on behalf of Malarngowem; Ike Simpson & Ors on behalf of Wajarri Yamatji; Wyamba Aboriginal Corporation on behalf of its members; LW (name...
[2013] NNTTA 65
•11 June 2013
NATIONAL NATIVE TITLE TRIBUNAL
Peggy Patrick & Ors on behalf of Yurriyangem Taam; Maggie John & Ors on behalf of Malarngowem; Ike Simpson & Ors on behalf of Wajarri Yamatji; Wyamba Aboriginal Corporation on behalf of its members; LW (name withheld for cultural reasons) & Ors on behalf of Njamal / Western Australia / Thundelarra Exploration Ltd; Rumble Resources Pty Ltd; Rumble Ashburton Pty Ltd; Dourado Resources Ltd; Bookaburna Minerals Pty Ltd [2013] NNTTA 65 (11 June 2013)
Applications No: WO2012/0331; WO2012/0332; WO2012/0674; WO2012/1262; WO2013/0405; WO2013/0491
IN THE MATTER of the Native Title Act 1993 (Cth)
- and -
IN THE MATTER of an inquiry into expedited procedure objection applications
Native title parties as listed in the attached schedule (native title parties)
- and -
State of Western Australia (Government party)
- and –
Grantee parties as listed in the attached schedule (grantee parties)
DECISION TO DISMISS EXPEDITED PROCEDURE OBJECTION APPLICATIONS
Tribunal: Member Dan O’Dea
Place: Perth
Date: 11 June 2013Catchwords: Native title – future acts – proposed grant of exploration permits – expedited procedure objection applications – applications for exploration permits withdrawn – expedited procedure objection applications dismissed.
Legislation:Native Title Act 1993 (Cth), ss 29, 148(a)
REASONS FOR DECISION TO DISMISS EXPEDITED PROCEDURE OBJECTION APPLICATIONS
[1] On the dates specified in the attached Schedule, the State of Western Australia (“the government party”) gave notice under s 29 of the Native Title Act 1993 (Cth) of its intention to grant various exploration permits to the grantee parties specified therein and included in the notices a statement that it considered that the grants attracted the expedited procedure.
[2] On the dates specified in the attached Schedule, the native title parties lodged expedited procedure objection applications with the Tribunal.
[3] On the dates specified in the attached Schedule, the Department of Mines and Petroleum on behalf of the government party advised the Tribunal that each of the grantee parties had discontinued or withdrawn their application for an exploration permit and as a result the matters were discontinued.
Decision
[4] The expedited procedure objection applications specified in the attached schedule are dismissed pursuant to s 148(a) of the Native Title Act 1993 (Cth).
Dan O’Dea
Member11 June 2013
SCHEDULE – DETERMINATION
| Tenement | Government Party Notification | Objection Application Lodged | Objection Application No. | Grantee Party | Native Title Party & Application No. | Date of Withdrawal |
| E80/4399 | 14/12/2011 | 16/04/2012 | WO2012/0331 | Thundelarra Exploration Ltd | Peggy Patrick & Ors on behalf of Yurriyangem Taam (WC2010/013) | 24/05/2013 |
| E80/4399 | 14/12/2011 | 16/04/2012 | WO2012/0331 | Thundelarra Exploration Ltd | Maggie John & Ors on behalf of Malarngowem (WC1999/044) | 24/05/2013 |
| E09/1954 | 07/03/2012 | 09/07/2012 | WO2012/0674 | Rumble Resources Pty Ltd | Ike Simpson & Ors on behalf of Wajarri Yamatji (WC2004/010) | 21/05/2013 |
| E52/2761 | 25/07/2012 | 26/11/2012 | WO2012/1262 | Dourado Resources Ltd | Ike Simpson & Ors on behalf of Wajarri Yamatji (WC2004/010) | 3/05/2013 |
| E08/2434 | 15/03/2013 | 05/04/2013 | WO2013/0405 | Rumble Ashburton Pty Ltd | Wyamba Aboriginal Corporation (WCD2009/002) | 21/05/2013 |
| E45/3979 | 16/01/2013 | 13/05/2013 | WO2013/0491 | Bookaburna Minerals Pty Ltd | LW (name withheld for cultural reasons) & Ors on behalf of Njamal (WC1999/008) | 16/05/2013 |