| CITATION: | Paul Bongioletti Homes Pty Ltd v North and Anor [2012] QCATA 175 |
| PARTIES: | Paul Bongioletti Homes Pty Ltd (Applicant/Appellant) |
| v | |
| John Robert North (First Respondent) Steve Pershouse t/as Steve Pershouse Concreter (Second Respondent) |
| APPLICATION NUMBER: | APL171-11 |
| MATTER TYPE: | Appeals |
| HEARING DATE: | On the papers |
| HEARD AT: | Brisbane |
| DECISION OF: | Mr J Jerrard QC, Member |
| DELIVERED ON: | 13 September 2012 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | Leave to appeal is refused.1. The decision under appeal is amended by deleting from order 1 made on 18 April 2011 the figure “$15,546.60” and inserting instead the figure “$16,454.07”.2. The decision of the primary tribunal is otherwise confirmed.3. |
| CATCHWORDS: | APPEAL – LEAVE TO APPEAL – DAMAGES – GENERAL PRINCIPLES – GENERAL AND SPECIAL DAMAGES – where first respondent bought a house that did not have a termite barrier compliant with Australian building requirements – where Tribunal found appellant builder liable for loss to first respondent – whether leave to appeal should be granted – whether appellant builder breached duty of care to the developer by erecting a building without a complying termite barrier – whether conduct of second respondent constituted an intervening causative event Building Act 1975, ss 9, 10, 12, 30 Bryan v Moloney (1995) 182 CLR 609 |
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s 32 of Queensland Civil and Administrative Tribunal Act2009 (QCAT Act), but some further evidence was heard by leave granted in April 2012.
REASONS FOR DECISION
This is an appeal from a decision handed down on 18 April 2011, in which the learned Member ordered that the appellant pay to the first respondent damages in the sum of $15,546.60 within 28 days of the date of that order; and, further, that the appellant provide two durable notices for the under slab termite management system completed by the pest management company that installed a system, within 28 days of the date of that order. No orders were made in respect of the second respondent. I understand that the appellant company has not complied with either order. An application for leave to appeal, or an appeal, was lodged by the appellant on 17 May 2011, and this appeal has been on foot since then.
On 7 June 2011 an application by the appellant for a stay was refused, and on 16 August 2011 the appellant was given leave to be legally represented in the appeal. On 22 August 2011 directions were given that an application by the appellant for leave to lead further evidence, and the hearing of the appeal and the application for leave to appeal be decided on the papers. On 5 December 2011 a direction was given that it was unnecessary for the appellant to have leave to lead the further evidence (the contract between the developer and Mr North), because…
Keep reading for free
Create a free CaseChat account to read Paul Bongioletti Homes Pty Ltd v North and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2012] QCATA 175
- Decision Date
CaseChat Overview and Summary
The Court of Appeal found that the builder did indeed breach its duty of care by failing to install a compliant termite barrier, a fundamental requirement under Australian building standards. This breach directly resulted in the developer incurring costs to rectify the issue, which were subsequently passed on to the buyer. The court held that the buyer's conduct did not amount to an intervening causative event that would absolve the builder from liability. Consequently, the builder remained responsible for the damages incurred. The court also addressed the specific amount of damages awarded, adjusting the figure to reflect the correct calculation based on the evidence presented.
As a result, the appeal was dismissed, and leave to appeal was refused. The Court of Appeal amended the original decision to correct the amount of damages awarded, replacing the figure of $15,546.60 with $16,454.07. The overall decision of the primary tribunal was upheld, with the amended figure being the only change. This ruling reaffirmed the builder's liability for the damages incurred due to the non-compliant construction and clarified the financial responsibility in such cases.
Orders
Orders of the court
Leave to appeal is refused.1.
The decision under appeal is amended by deleting from order 1 made on 18 April 2011 the figure “$15,546.60” and inserting instead the figure “$16,454.07”.2.
The decision of the primary tribunal is otherwise confirmed.3.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi