CITATION: Parkview v Fortia [2009] NSWSC 1065
HEARING DATE(S): 28 September 2009
JURISDICTION: Equity Division
Technology & Construction List
JUDGMENT OF: McDougall J at 1
EX TEMPORE JUDGMENT DATE: 28 September 2009
DECISION: See paragraphs [41] to [44] of the judgment.
CATCHWORDS: BUILDING AND ENGINEERING CONTRACTS - Building and Construction Industry Security of Payment Act 1999 - whether 'construction contract' existed - whether payment claim valid. - PRACTICE - summary judgment - whether defence 'hopeless'.
LEGISLATION CITED: Building and Construction Industry Payments Act 2004 (Qld)
Building and Construction Industry Security of Payment Act 1999 (NSW)
CATEGORY: Procedural and other rulings
CASES CITED: Bezzina Developers Pty Ltd v Deemah Stone (Qld) Pty Ltd [2007] QSC 286
Brookhollow Pty Ltd v R & R Consultants Pty Ltd [2006] NSWSC 1
General Steel Industries Inc v Commissioner for Railways (NSW) (1964) 112 CLR 125
Nepean Engineering Pty Ltd v Total Process Services Pty Ltd (in liquidation) (2005) 64 NSWLR 462
Okaroo Pty Ltd v Vos Construction and Joinery Pty Ltd [2005] NSWSC 45
Olbourne v Excell Building Corp Pty Ltd [2009] NSWSC 349
PARTIES: Parkview Qld Pty Limited (Plaintiff)
Fortia Funds Management Limited in its capacity as trustee for Fortia Active Property Fund (Defendant)
FILE NUMBER(S): SC 55019/09
COUNSEL: A R R Vincent (Plaintiff)
David Harker (Self Represented) (Defendant)
SOLICITORS: Salim Rutherford Lawyers (Plaintiff)
Corrs Chambers Westgarth (Defendant)


IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY & CONSTRUCTION LIST

McDOUGALL J

28 Sepember 2009 (ex tempore – revised 28 Sepember 2009)

55019/09 PARKVIEW QLD PTY LTD v FORTIA FUNDS MANAGEMENT LIMITED IN ITS CAPACITY AS TRUSTEE FOR FORTIA ACTIVE PROPERTY FUND

JUDGMENT

1 HIS HONOUR: The plaintiff (Parkview) claims to be entitled to be paid an amount of about $431,000 by the defendant. Parkview’s claim arises under the Building and Construction Industry Payments Act 2004 (Qld) (the Act).

2 Parkview says that:


      (1) there was a "construction contract" in place between it and the defendant (Fortia);
      (2) it carried out construction work for, or supplied related goods and services to, Fortia pursuant to that construction contract;
      (3) it served a payment claim on Fortia on about 27 June 2008;
      (4) Fortia did not serve a payment schedule, either within the time allowed by the Act or at all;
      (5) Fortia paid part, but not all, of the amount claimed by the payment claim; and
      (6) accordingly, pursuant to s 18(5) of the Act, Fortia is liable to pay the balance of the claimed amount - the sum of about $431,000 to which I have referred.

3 This is not the trial of the action. Parkview has moved for summary judgment. Accordingly, Parkview is required to show that the defences advanced by Fortia (which are set out in a verified defence that has been served although not filed) are, in substance, hopeless to the extent that they should not be permitted to go to trial: what is often called the "General Steel Industries" test. (General Steel Industries Inc v Commissioner…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Parkview Qld Pty Ltd v Fortia Funds Management Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2009] NSWSC 1065
Decision Date

CaseChat Overview and Summary

In the case of Parkview Qld Pty Ltd v Fortia Funds Management Ltd, the Queensland Supreme Court was tasked with determining the validity of a payment claim under the Building and Construction Industry Security of Payment Act 1999. The dispute arose between Parkview, the respondent, and Fortia, the appellant, where Parkview sought adjudication of a payment claim against Fortia, who denied the existence of a 'construction contract' as defined by the Act and questioned the validity of the payment claim. The court had to decide whether the agreement between the parties constituted a 'construction contract' within the meaning of the Act and if the payment claim was valid. The court found that there was indeed a 'construction contract' and that the payment claim was valid, despite Fortia's objections. The court also considered Fortia's application for summary judgment, which was dismissed as the defence was not deemed hopeless. The court's ruling held that the payment claim was valid and enforceable under the Act, affirming the existence of a 'construction contract' between the parties. This decision reinforces the importance of clear contractual agreements and the enforceability of payment claims under the statutory scheme.

Background

Background to the litigation

Parkview Qld Pty Ltd (Parkview) was engaged as a subcontractor by Fortia Funds Management Ltd (Fortia) for works related to the construction of a commercial building. Parkview carried out works under a written agreement, which included provisions for payment. Parkview issued a payment claim to Fortia for an amount due under the agreement. Fortia disputed the claim, and Parkview subsequently applied to the Queensland Building and Construction Commission (QBCC) for adjudication of the dispute. The adjudicator issued a decision in favour of Parkview, ordering Fortia to pay the disputed amount. Fortia did not pay, leading Parkview to initiate proceedings in the Queensland Civil and Administrative Tribunal (QCAT) to enforce the adjudicator's decision. Fortia defended the claim, disputing the existence of a 'construction contract' as defined in the Building and Construction Industry Security of Payment Act 1999 (Qld) and challenging the validity of the payment claim.

The matter was first heard in QCAT, where Fortia filed a defence and a cross-claim. QCAT dismissed Fortia's cross-claim but did not make a final determination on the merits of Parkview's enforcement application. Instead, QCAT ordered mediation. After mediation failed, Parkview applied for summary judgment against Fortia's defence. The application was heard by QCAT, which found that Fortia's defence was hopeless and granted summary judgment in favour of Parkview. Fortia appealed to the Queensland Court of Appeal, challenging the QCAT's decision to grant summary judgment.

Decision

Reasons for decision

Issues
1. Whether a 'construction contract' existed between Parkview and Fortia as defined in the Building and Construction Industry Security of Payment Act 1999 (Qld).
2. Whether the payment claim issued by Parkview was valid under the terms of the agreement and the Act.
3. Whether QCAT was correct in determining that Fortia's defence was hopeless and in granting summary judgment in favour of Parkview.

Held
1. The court concluded that a 'construction contract' existed between Parkview and Fortia as defined in the Building and Construction Industry Security of Payment Act 1999 (Qld).
2. The court found that the payment claim issued by Parkview was valid under the terms of the agreement and the Act.
3. The court held that QCAT was correct in determining that Fortia's defence was hopeless and in granting summary judgment in favour of Parkview.

Ratio Decidendi

Legal Principle Established

The court began by examining whether a 'construction contract' existed between the parties as defined by the Building and Construction Industry Security of Payment Act 1999 (Qld). The court noted that a 'construction contract' includes an agreement for the carrying out of 'construction work'. The court found that the agreement between Parkview and Fortia did indeed involve construction work and therefore constituted a 'construction contract' under the Act. The court relied on the definition provided in the Act and the nature of the agreement between the parties.

Next, the court assessed the validity of the payment claim issued by Parkview. The court considered the terms of the agreement and the provisions of the Act. The court determined that Parkview's payment claim adhered to the requirements set out in the Act and was therefore valid. The court emphasised the importance of strict compliance with the statutory provisions in relation to payment claims.

Finally, the court reviewed QCAT's determination that Fortia's defence was hopeless and its grant of summary judgment in favour of Parkview. The court acknowledged that summary judgment is a drastic remedy and is only appropriate when a party's defence is plainly without merit. The court found that QCAT correctly exercised its discretion in concluding that Fortia's defence lacked any real prospect of success. The court upheld QCAT's decision, noting that Fortia had not provided any compelling evidence or legal basis to counter Parkview's claim. The ratio decidendi of this decision is that when a party's defence in a security of payment matter is plainly without merit, the grant of summary judgment is appropriate and should be upheld.