LAND COURT OF QUEENSLAND
CITATION: Palmer Gold NQ Pty Ltd v Strathleven WAR(NQ) Pty Ltd [2015] QLC 21 PARTIES: Palmer Gold NQ Pty Ltd
(applicant)v Strathleven WAR (NQ) Pty Ltd
(respondent)FILE NO: MRA 508-14 DIVISION: General Division PROCEEDING: Determination of compensation for renewal of mining lease DELIVERED ON: 6 July 2015 DELIVERED AT: Brisbane HEARD ON: Submissions closed on 12 February 2015 HEARD AT: Heard on the papers MEMBER: G.J Smith, Judicial Registrar ORDERS: 1. Compensation is determined in the total sum of Three Thousand Seven Hundred and Forty dollars. ($3,740.00).
2. The miner is to pay compensation to the respondent in the amount set out on Order 1 hereof within three (3) months of the issue of Mining Lease 7220 by DNRM.
CATCHWORDS: MINING LEASE – determination of compensation -renewal - factors to be considered - no material provided by either party.
Mineral Resources Act 1989, ss 279, 279A, 281.
Land Court Rules 2000, Rule 36AUnimin Australia Limited v Freeman [2007] QLC 76
Eacham Abrasive Blasting Pty Ltd v Gundersen & Anor
[2014] QLC 38Oosen v Emu Creek Bar-Barrum Aboriginal Corporation (2008) QLC 23
Re Fitzgerald & Anor (2009) QLC 15
Re Fitzgerald and Hughes (2009) QLC 73
Re Kimmoth & Poole (2009) QLC 117
Palmer Gold NQ Pty Ltd v Strathleven WAR(NQ) Pty Ltd [2014]QLC 42APPEARANCES: Not applicable
This matter involves a referral to the Land Court pursuant to s 279A of the Mineral Resources Act 1989 (MRA) for the determination of compensation in respect of the renewal of a mining lease.
Background
On 4 July 2012, Palmer Gold NQ Pty Ltd (the miner) applied for the renewal of Mining Lease 7220 over land located approximately 113 km south-west of Laura in the Mareeba District. The land is within the Cook Shire local government area. Further renewal is sought for a period of 10 years. The purpose of the proposed renewal is for the mining of Heavy Mineral Sand together with gold, tin, garnet, and zircon.
Access to the mining lease area is over an 18 km track across land owned by Strathleven WAR (NQ) Pty Ltd (the respondent). The land is more particularly described as Lot 434 on SP136214. Mapping data supplied by the Department of Natural Resources and Mines (DNRM) indicates that approximately 25 ha of ML 7220 is located within Lot 434 on SP136214.
Relevant Legislation
Section 279 of the MRA provides that a mining lease shall not be granted or renewed unless an agreement in relation to compensation has been filed or, in the absence of such an agreement, a determination of compensation has been made by the Land Court. In this matter, no agreement has been lodged with the Department of Natural Resources and Mines (DNRM) and the matter has been referred to the Land Court for determination.
Section 281 of the MRA identifies the matters which must be considered by the Court in determining the compensation. In particular, s 281(3)(a) provides that an owner of…
Keep reading for free
Create a free CaseChat account to read Palmer Gold NQ Pty Ltd v Strathleven War(NQ) Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] QLC 21
- Decision Date
CaseChat Overview and Summary
In addressing the issue, the tribunal noted that both parties had failed to provide any material or submissions to assist in the determination of the compensation. Despite this, the tribunal proceeded to make a determination based on the available information and statutory provisions. The tribunal considered the statutory framework governing mining leases and the factors typically relevant to such compensation, including the value of the mining lease, any potential benefits to the public, and the terms of the original lease. Given the lack of submissions from either party, the tribunal relied on the statutory guidelines and made its decision based on the evidence available.
The tribunal determined that the compensation should be set at Three Thousand Seven Hundred and Forty dollars ($3,740.00). This amount was based on a consideration of the statutory provisions and the tribunal's assessment of the relevant factors in the absence of any submissions from the parties. Additionally, the tribunal ordered that the miner, Palmer Gold NQ Pty Ltd, was to pay the compensation to Strathleven War(NQ) Pty Ltd within three months of the issuance of Mining Lease 7220 by the Department of Natural Resources and Mines (DNRM).
Orders
Orders of the court
1. Compensation is determined in the total sum of Three Thousand Seven Hundred and Forty dollars. ($3,740.00).
2. The miner is to pay compensation to the respondent in the amount set out on Order 1 hereof within three (3) months of the issue of Mining Lease 7220 by DNRM.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi