DISTRICT COURT OF QUEENSLAND
CITATION:
Pacific Crown Helicopters Pty Ltd v Helistar Aviation Pty Ltd [2017] QDC 321
PARTIES:
PACIFIC CROWN HELICOPTERS PTY LTD
(plaintiff)v
HELISTAR AVIATION PTY LTD
(defendant)FILE NO/S:
D1137/2017
DIVISION:
Civil
PROCEEDING:
Application
ORIGINATING COURT:
District Court, Brisbane
DELIVERED ON:
22 December 2017
DELIVERED AT:
Brisbane
HEARING DATE:
28 November 2017
JUDGE:
Richards DCJ
ORDER:
The application for delivery up of Engine 220 is refused. Application pursuant to UCPR r 250 for inspection of the engine is allowed.
The defendant will make Engine 220 available for inspection by the plaintiff and/or an expert appointed on the plaintiff’s behalf at a time and place to be agreed between the parties.
Failing agreement each party has liberty to apply on 2 days’ notice.CATCHWORDS:
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – FORMATION OF CONTRACTUAL RELATIONS – where the agreement is partly in writing and partly oral – whether the oral agreement forms part of the contract
Uniform Civil Procedure Rules 1999, r 292, 293, 250
Deputy Commissioner of Tax v Salcedo [2005] QCA 227
Evans Deacon Pty Ltd v Orekinetics Pty Ltd [2002] 2 Qd R 345COUNSEL:
Mr J Ward for the plaintiff
P O’Brien for the defendantSOLICITORS:
Cleary Hoare, solicitors for the plaintiff
Thomson Geer for the defendant
This is an application by the plaintiff for delivery up and possession of an Arriel 1B helicopter engine described as Engine 220 leased to the defendant pursuant to a written agreement dated 2 April 2014. Despite demand on 16 June 2015 and since the defendant has refused to return Engine 220 to the plaintiff. In the alternative the plaintiff seeks delivery up of Engine 220 pursuant to UCPR r 250 for the purpose of inspection of the engine with a view to having an expert report prepared as to any issues relating to the engine whilst in the possession of the defendant. It is submitted that such a report is required for the trial of these proceedings as it may form the basis of a claim for damages. At the hearing of this application leave was given without objection to file an amended claim in the proceeding reflecting the relief pleaded in its amended statement of claim filed 2 February 2017.
The ownership of the engine in this case is not in dispute.
The defendant operates helicopters in South Australia and required one of its engines, Engine 679 to be inspected and repaired following a hot start in early 2014. Mr Dinan from the defendant company made enquiries to find a party to carry out the inspection and repair of Engine 679 who could also provide a loan engine for the duration of the inspection and repair period. He enquired with Eurotech in the United States (original sales people for Engine 679) and they referred him to the plaintiff. The defendant spoke to the plaintiff on 2 April 2014 and it was agreed that the engine would be delivered to them to complete the inspection and repairs.…
Keep reading for free
Create a free CaseChat account to read Pacific Crown Helicopters Pty Ltd v Helistar Aviation Pty Lt... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2017] QDC 321
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the oral agreement between the parties, which allegedly supplemented the written contract, formed part of the enforceable contract. The court considered the principles of contract law, specifically whether the parol evidence rule applied and precluded the introduction of evidence of the oral agreement. The court also had to determine whether the oral agreement constituted a collateral contract or was part of the main contract.
The court found that the written agreement between the parties was not a complete expression of their entire contract and that the oral agreement did form part of the contract. The court reasoned that the parol evidence rule did not apply because the written agreement was incomplete and the oral agreement was necessary to understand the full terms of the contract. The court held that the oral agreement was not a collateral contract but was part of the main contract. Consequently, the court found that the defendant had breached the contract by failing to deliver the engine in a satisfactory condition.
The orders of the court included a refusal to compel the delivery of Engine 220 but granted the plaintiff’s application for inspection of the engine. The court directed that the defendant make Engine 220 available for inspection by the plaintiff or an expert appointed by the plaintiff, with the timing and location to be agreed upon by the parties. If the parties could not agree, either party had the liberty to apply for inspection on two days’ notice.
Orders
Orders of the court
The application for delivery up of Engine 220 is refused. Application pursuant to UCPR r 250 for inspection of the engine is allowed.
The defendant will make Engine 220 available for inspection by the plaintiff and/or an expert appointed on the plaintiff’s behalf at a time and place to be agreed between the parties.
Failing agreement each party has liberty to apply on 2 days’ notice.
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi