CITATION: P Ward Civil Engineering v Civil & Civic [2003] NSWSC 133 HEARING DATE(S): 03/03/03 JUDGMENT DATE:
13 March 2003JURISDICTION:
Equity Division
Technology and Construction ListJUDGMENT OF: Barrett J DECISION: Short minutes to be brought in CATCHWORDS: CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - adoption of report by referee - whether indemnity applies - no question of principle CASES CITED: Walter Construction Group Ltd v Walker Corporation Ltd (2001) 47 ATR 48 PARTIES :
P Ward Civil Engineering Pty Ltd - Plaintiff
Civil & Civic Pty Ltd - DefendantFILE NUMBER(S): SC 55062/97 COUNSEL: Mr S R Donaldson SC - Plaintiff
Mr M R Gracie - DefendantSOLICITORS: Tress Cocks & Maddox - Plaintiff
Freehills - Defendant
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY AND CONSTRUCTION LIST
BARRETT J
THURSDAY, 13 MARCH 2003
55062/97 – P WARD CIVIL ENGINEERING PTY LTD v CIVIL & CIVIC PTY LTD
JUDGMENT
1 As a result of judgment delivered by McClellan J on 17 April 2002, Mr K.J. Hinds, a referee appointed by order made under Part 72 of the Supreme Court Rules, delivered a report on 7 November 2002. He had previously delivered a report in November 2001. The second or supplementary report dealt with two aspects of the controversy between the parties in respect of which McClellan J had not considered it appropriate to adopt the first report.
2 The first report dealt with a number of matters in contest between the parties in relation to a contract under which the plaintiff/cross-defendant (which I shall call “Ward”) performed, as a sub-contractor, certain services for the defendant/cross-claimant (“C&C”) which was the head contractor for the construction of a water treatment plant at Prospect. Ward was retained to perform site preparation and earthworks. In the original report, the referee found that Ward had been guilty of delays in completing parts of its contracted works, with the result that John Holland Construction Pty Ltd (“Holland”), a subcontractor retained by C&C to perform works subsequent to and dependent upon the works for which Ward was responsible, was delayed in commencement of its works. The referee also found that C&C was accordingly entitled to “late completion damages” as against Ward, such damages being described as “liquidated damages” and being calculated at a flat rate per day provided for in the contract between C&C and Ward.
3 When the question of adoption of the referee’s report came before McClellan J, his Honour held that the “late completion damages” provision, as it applied to the particular delay, was in the nature of a penalty rather than a genuine pre-estimate of loss, with the result that that provision was unenforceable and the question of damages for breach of contract in respect of the particular delay required re-examination.
4 In consequence of the judgment of 17 April 2002, that matter, together with another concerning interest, were referred back to the referee for further consideration and report. The interest issue is now…
Keep reading for free
Create a free CaseChat account to read P Ward Civil Engineering v Civil and Civic and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2003] NSWSC 133
- Decision Date
CaseChat Overview and Summary
The legal issues before the court included the interpretation of the indemnity clause and whether it extended to the referee's report. The court considered the context and purpose of the indemnity clause and the nature of the referee's role. It was important to determine whether the referee's report was an integral part of the adjudicator's determination or a separate document. The court also examined the contractual framework and the parties' conduct in light of the clause's wording and purpose.
The High Court held that the indemnity clause did not apply to the referee's report. The court found that the referee's report was not an integral part of the adjudicator's determination, but rather a separate document prepared by the referee. The court emphasised the need to interpret the clause in the context of the contract's overall purpose and the parties' intentions. The court concluded that there was no question of principle involved and that the referee's report was not covered by the indemnity clause. The appeal was dismissed, and the decision of the lower court was upheld.
The final orders of the court confirmed that the indemnity clause did not apply to the referee's report. The adjudicator's determination, which was not affected by the clause, remained enforceable. The court's decision clarified the scope of indemnity clauses in construction contracts and reinforced the importance of interpreting such clauses in the context of the contract's purpose and the parties' intentions.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi