JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
STREAM: COMMERCIAL & CIVIL
ACT: BUILDING SERVICES (COMPLAINT RESOLUTION and ADMINISTRATION) ACT 2011 (WA)
CITATION: OWNERS OF STRATA PLAN NO 43417 and PINDAN PTY LTD [2012] WASAT 243
MEMBER: MS L WARD (MEMBER)
MR D MILLER (SESSIONAL MEMBER)
HEARD: 7 AND 8 JUNE 2012
DELIVERED : 18 DECEMBER 2012
FILE NO/S: CC 306 of 2012
CC 311 of 2012
BETWEEN: OWNERS OF STRATA PLAN NO 43417
Applicant
AND
PINDAN PTY LTD
Respondent
Catchwords:
32 unit residential strata complex Internal and external cracks in plaster Standards to apply HB 1612005 'Guide to plastering' AS 28701996 'Residential slabs and footings: Construction' Soil site classification Cornice cracking AS 25982007 'Gypsum linings: Application and finishing' Causes of plaster cracking Shower ponding Water ingress Mouldings Remedial work order - Reasonable costs of remedying
Legislation:
Builders Registration Act 1939 (WA), s 12A(1), s 12A(2), s 12A(3), s 12A(1aa)
Building Code of Australia Volume 2 1996
Building Code of Australia, s 3.8.1
Building Services (Complaint Resolution and Administration Act 2011 (WA), s 9, s 11(1), s 11(1)(d), s 36(1)(b), s 38(1), s 38(1)(a), s 38(1)(b), s 134
State Administrative Tribunal Act 2004 (WA), s 98
Strata Titles Act 1985 (WA)
Result:
Application successful in part
Summary of Tribunal's decision:
Plaster cracks or water ingress feature throughout 23 of the units in a 32 unit multilevel residential complex on the Mandurah Canals. The development was completed by Pindan Pty Ltd in mid2003.
Most of the outstanding complaints relate to cracks in the plaster in various internal and external locations throughout much of the complex. The cracking is widespread throughout the complex and is similar in kind and extent.
The owners submit that irrespective of the cause of the cracking complaints, whether it is settlement or deflection of the concrete slab, the builder should have taken extra care with the construction, especially given the site classification of the soil as Class S. The owners submit that the width and extent of the cracking in the plaster is beyond the accepted tolerances, and is therefore the builder's responsibility. There is no evidence that the defects arose from or were made worse due to a lack of owner maintenance.
The Tribunal found that as submitted by the owners, the accepted tolerances in relation to cracks in plaster were set out in HB 161-2005 'Guide to plastering', rather than the AS 2870-1996 'Residential slabs and footings: Construction'. Most of the cracking exceeded the tolerance allowed for in HB 161-2005 'Guide to plastering' and in those cases it was ultimately found to have been a builder generated defect.
In relation to the water ingress issues, the builder was found to be responsible in relation to the majority of the complaints where it had failed to comply with the relevant parts of the Building Code of Australia.
Ultimately, the owners' application was successful in part.
Category: B
Representation:
Counsel:
Applicant: Mr P Hassett
Respondent: Mr…
Keep reading for free
Create a free CaseChat account to read OWNERS OF STRATA PLAN NO 43417 and PINDAN PTY LTD and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] WASAT 243
- Decision Date
CaseChat Overview and Summary
The primary legal issues the court had to decide were the applicable standards and codes for the plastering work in the strata complex, the causes of the plaster cracking, and the appropriate steps for remediation. The court needed to determine whether the contractor had met the required standards and whether the cracking was due to issues such as shower ponding, water ingress, or soil site classification. Additionally, the court had to consider whether the remediation costs claimed by the plaintiffs were reasonable.
In its decision, the court found that the standards applicable to the plastering work in the strata complex were HB 161-2005 'Guide to plastering', AS 2870-1996 'Residential slabs and footings: Construction', and AS 2598-2007 'Gypsum linings: Application and finishing'. The court held that the cracking in the plasterwork was primarily due to shower ponding and water ingress, which were exacerbated by inadequate drainage and poor workmanship. The court also found that the remediation costs claimed by the plaintiffs were reasonable, taking into account the extent of the damage and the need to address the underlying issues causing the cracking. The court ordered the contractor to undertake the necessary remedial work and to pay the reasonable costs of the remediation.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi