Supreme Court
New South Wales
Medium Neutral Citation: Owners Corporation SP 78422 v Ware Building Pty Ltd [2015] NSWSC 1384 Hearing dates: 16 September 2015 Date of orders: 16 September 2015 Decision date: 16 September 2015 Jurisdiction: Equity - Technology and Construction List Before: McDougall J Decision: Notice of motion to amend quasi-pleadings and adjourn proceedings dismissed.
Catchwords: PRACTICE AND PROCEDURE – dispute between owners corporation and builder – where defendant builder seeks to commence separate proceedings against the developer to rectify the contract pursuant to which the building was constructed – related application to amend list response in present proceedings to incorporate that defence – where it has been open to the defendant to agitate the question of rectification for three years – where substantial effort and expense has gone into the preparation of the case as currently pleaded – where a variation argument is in any event already provided for – consequence that it is not in the interests of justice to allow defendant the leave it seeks Legislation Cited: Corporations Act 2001 (Cth)
Home Building Act 1989 (NSW)Category: Procedural and other rulings Parties: The Owners – Strata Plan No 78422 (Plaintiff)
Ware Building Pty Ltd (Defendant)Representation: Counsel:
Solicitors:
M A McCall (Plaintiff)
S Tully (Defendant)
Walters Solicitors (Plaintiff)
Barraclough Jones & Associates (Defendant)
File Number(s): 2014/105793
Judgment (ex tempore – revised 16 september 2015)
-
HIS HONOUR: The plaintiff is the owners corporation of a strata title development at Port Macquarie. The defendant is the builder who carried out the residential building work comprising the erection of the building. The building consists of residential home units.
-
The developer for whom the defendant carried out the building work was a company known as Glenco Seamist Pty Ltd (the developer). That company has been deregistered.
-
The plaintiff's case is that the roof of the building is defective, and leaks. The plaintiff says that the contract between the first defendant and the developer required the use of a two-layer bituminous membrane, but that in fact a polyurethane membrane was used instead. The plaintiff's case, as to defective work and work not complying with the specification, is pleaded and particularised extensively and, as I understand it, supported by expert evidence.
-
But for the matters I am about to mention, the matter is ready for a hearing. It can be given a hearing date later this year, on the plaintiff's estimate that no more than five days would be required. It is obvious that the parties will have to go to a hearing, because there has been an unsuccessful mediation before Dr Briggs (a former member of the Consumer, Trader and Tenancy Tribunal (CTTT), now incorporated into the New South Wales Civil and Administrative Tribunal).
-
The defendant has filed a notice of motion and an amended notice of motion. The notice of motion sought leave to amend. The amended notice of motion sought an adjournment of these proceedings so that the defendant could commence proceedings against the developer to have the…
Keep reading for free
Create a free CaseChat account to read Owners Corporation SP 78422 v Ware Building Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] NSWSC 1384
- Decision Date
CaseChat Overview and Summary
The court was required to decide whether the defendant could amend its defences to include a claim for rectification of the contract. This decision hinged on whether it would be just and equitable to allow such an amendment given the significant time that had elapsed since the proceedings commenced, and the extensive preparation that had already gone into the case as currently pleaded. The court had to weigh the defendant's right to a fair trial against the need to prevent unnecessary expense and delay. Additionally, the court had to consider whether the proposed defence of rectification was already adequately covered by the existing pleadings.
The court found that it would not be in the interests of justice to allow the defendant to amend its defences. The court noted that the defendant had been aware of the potential need for rectification for three years and had not previously sought to amend the defences. The court also highlighted the substantial effort and expense that had already been incurred in preparing the case. The court further noted that the defence of rectification was, in any event, already provided for in the existing pleadings. Consequently, the court held that allowing the amendment would result in unnecessary delay and expense, and it was not in the interests of justice to permit such an amendment.
The final orders of the court were that the defendant's application to amend its defences to include a claim for rectification of the contract was dismissed. The court emphasised that the decision was not a reflection on the merits of the defendant's case but was based on the principle of preventing unnecessary expense and delay. The court also noted that the defendant was free to pursue the rectification claim in a separate proceeding against the developer.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi