DISTRICT COURT OF QUEENSLAND
CITATION:
On Hing Pty Ltd v Phoenix Project Development Pty Ltd [2006] QDC 159
PARTIES:
ON HING PTY LTD ACN 088 965 860
Applicant
V
PHOENIX PROJECT DEVELOPMENT PTY LTD ACN 113 770 817
Respondent
FILE NO/S:
BD 4682/05
DIVISION:
Civil
PROCEEDING:
Application
ORIGINATING COURT:
District Court of Queensland
DELIVERED ON:
8 June 2006
DELIVERED AT:
Brisbane
HEARING DATE:
11 May 2006
JUDGE:
Alan Wilson SC, DCJ
ORDER:
Application refused
CATCHWORDS:
STAY – STAY OF ORDER THAT MONIES BE PAID OUT OF COURT – Monies paid into court after adjudication under Building and Construction Industry Payments Act 2004 – previous refusal of applicant’s application to set aside adjudicator’s order – whether stay of payment out to respondent should be ordered
Building and Construction Industry Payments Act 2004
Brodyn Pty Ltd v Davenport [2004] 61 NSWLR 421 at 449
McLaughlins Family Restaurant v Cordukes Ltd [2004] NSWCCA 447
Phoenix Project Development Pty Ltd v On Hing Pty Ltd [2006] QDC 075COUNSEL:
Mr P A Kronberg for the Applicant
Mr P R Franco for the RespondentSOLICITORS:
MCA Lawyers
Joseph Ho Lawyers
This is a further application in a matter previously dealt with in my judgment in Phoenix Project Development Pty Ltd v On Hing Pty Ltd [2006] QDC 075. An adjudicator appointed under the Building and Construction Industry Payments Act 2004 (BCIPA) ordered in December last year that On Hing pay a progress payment to Phoenix in the sum of $95,510 plus interest and Phoenix, as it was entitled to do, registered that order as a judgment in this court on 16 December 2005. The previous judgment dismissed On Hing’s application to set that judgment aside.
On Hing had paid the money into court and, in this application, seeks another order staying payment out to Phoenix until the determination of proceedings it now wishes to bring, here, which dispute Phoenix’s right to that payment under the contract between the parties. The matter was touched upon in the previous decision:
[15] Strictly speaking it is, then, unnecessary to deal with On Hing’s application for a stay of the judgment but, even if a different conclusion had been reached, this is not a case in which a stay would be warranted. The legislation clearly intends that progress payments and the like will be made with a minimum of delay and court involvement, and adjusted later if necessary; there is no suggestion that hardship has been caused to On Hing by its payment into Court; there is a probable risk of hardship, however, to Phoenix since it requires money to pay subcontractors; there is no evidence of any risk if the money is paid to Phoenix; and, even on the most generous view of the evidence presented by On Hing, its case could never be described as a strong one.
The matters now relied upon by On Hing for a stay were not raised at the earlier hearing. It is asserted, for the first time, that the contract…
Keep reading for free
Create a free CaseChat account to read On Hing Pty Ltd v Phoenix Project Development Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2006] QDC 159
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether a stay of the order that required the applicant to pay the monies to the respondent should be granted. This involved a consideration of the applicant's previous unsuccessful application to set aside the adjudicator's order and the implications of the payment of the monies into court as per the Act. The court was required to balance the rights of the parties and the statutory framework governing the adjudication process.
The court considered the applicant's previous unsuccessful attempt to set aside the adjudicator's order and the statutory mandate that monies be paid into court following an adjudication. The court concluded that the statutory process should be allowed to proceed as required, and the applicant's request for a stay was refused. The reasoning was based on the statutory obligation to pay the monies into court and the unsuccessful attempt to set aside the adjudicator's decision.
No orders were made in favour of the applicant. The court's decision upheld the requirement for the monies to be paid out of court to the respondent as per the adjudicator's order. The court's refusal to grant a stay meant that the statutory process would proceed as mandated by the Building and Construction Industry Payments Act 2004.
Orders
Orders of the court
Application refused
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.