CITATION: Olympia Group Pty Ltd v Tyrenian Group Pty Ltd [2010] NSWSC 319 HEARING DATE(S): 4 March 2010 JUDGMENT OF: Hammerschlag J EX TEMPORE JUDGMENT DATE: 4 March 2010 DECISION: Declaration in terms of paragraph 1 of the plaintiffs’ summons. Order in terms of paragraph 3 of the plaintiff’s summons. Defendant’s cross-summons dismissed. Defendant to pay the plaintiffs’ costs of the proceedings CATCHWORDS: CONTRACTS – building, engineering and related contracts – general contractual principles – parties – whether the first plaintiff or Olympia Group (NSW) Pty Limited (“Olympia NSW”) was party to the construction contract within the meaning of s 4 of the Building and Construction Industry Security of Payment Act 1999 (“the Act”) where Olympia NSW was the head contractor, where Olympia NSW had made payments to the defendant and where the first plaintiff was not carrying on business in the building and construction industry – whether the payment claim was effectively served on the plaintiffs – whether the payment claim was an abuse of the processes of the Act LEGISLATION CITED: Building and Construction Industry Security of Payment Act 1999 (NSW) CATEGORY: Principal judgment CASES CITED: Zebicon Pty Ltd v Remo Constructions Pty Ltd [2008] NSWSC 1408
Falgat Constructions Pty Ltd v Equity Australia Corporation Pty Ltd [2006] NSWCA 259
Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69PARTIES: Olympia Group Pty Ltd - First Plaintiff
Thomas Vivian Davidson - Second Plaintiff
Tyrenian Group Pty Ltd - DefendantFILE NUMBER(S): SC 2010/46881 COUNSEL: F. Kalyk [Plaintiffs]
M. Christie SC with L. Shipway [Defendant]SOLICITORS: Knight Lawyers [Plaintiffs]
Blackstone Waterhouse Lawyers [Defendant]
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
COMMERCIAL LIST
HAMMERSCHLAG J
4 MARCH 2010
2010/46881 OLYMPIA GROUP PTY LIMITED & ANOR -V- TYRENIAN GROUP PTY LIMITED
EX TEMPORE JUDGMENT
1 HIS HONOUR: The first plaintiff was incorporated on 13 May 2002. Olympia Group (NSW) Pty Limited, to which I shall refer as “Olympia NSW”, was incorporated on 2 January 2008. Both are associated with the second plaintiff, Mr Davidson.
2 According to Mr Davidson, the first plaintiff is in the business of property development but presently does not carry on any business activities. He says it has no place of business, as such, beyond its registered office (which is at a firm of accountants) and that it keeps all of its records and accounts there.
3 Olympia NSW is in the business of building and construction. According to Mr Davidson, it operates only at sites at which it is undertaking construction activity. It maintains a serviced office at Level 23, Tower 1, 520 Oxford Street, Bondi Junction for the receipt of correspondence and telephone calls, and as a place to convene meetings.
4 From about March 2009 Olympia NSW was engaged in quoting for work to be carried out for the Australian Government in relation to the upgrade of certain naval defence works, which it is not necessary for present purposes to describe (“the works” or “the…
Keep reading for free
Create a free CaseChat account to read Olympia Group Pty Ltd v Tyrenian Group Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] NSWSC 319
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether Olympia Group Pty Ltd, or Olympia NSW, was a party to the construction contract within the meaning of section 4 of the Act. Additionally, it was necessary to ascertain whether the payment claim made by Tyrenian Group Pty Ltd was effectively served on the plaintiffs. Furthermore, the court needed to decide if Tyrenian Group Pty Ltd's payment claim was an abuse of the processes outlined in the Act. The court's analysis focused on the statutory definitions and the legislative intent behind the Security of Payment Act, particularly concerning who could be considered a party to a construction contract and the procedural requirements for payment claims.
The court found that Olympia Group Pty Ltd was not a party to the construction contract as it was not carrying on business in the building and construction industry. Consequently, the court ruled that Olympia NSW was the relevant party to the contract. The court also held that the payment claim was not effectively served on the plaintiffs as it was addressed to Olympia Group Pty Ltd rather than Olympia NSW. Finally, the court concluded that Tyrenian Group Pty Ltd's payment claim was an abuse of the processes of the Act due to the misidentification of the party to whom the claim should have been addressed. Therefore, the court dismissed the defendant's claim for payment.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.