QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
O’Toole & Anor v Qld Building Company Pty Ltd [2018] QCAT 257
PARTIES:
JOHN O’TOOLE
and
KYM O’TOOLE
(applicants)v QLD BUILDING COMPANY PTY LTD
(respondent)
APPLICATION NO/S:
BDL147-18
MATTER TYPE:
Building matters
DELIVERED ON:
08 August 2018
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
Member Cranwell
ORDERS:
1. The application for building disputes filed on
1 June 2018 is dismissed.2. John O’Toole and Kym O’Toole are to pay Qld Building Company Pty Ltd costs as agreed or, failing agreement within 28 days, as assessed on the Magistrates Court scale of costs.
CATCHWORDS:
ADMINISTRATIVE LAW – ADMINISTRATIVE TRIBUNALS – QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL – where applicants did not comply with process established by Queensland Building and Construction Commission to attempt to resolve a building dispute before commencing proceeding – where application dismissed for lack of jurisdiction
Queensland Building and Construction Commission Act 1991 (Qld), s 77
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 100Harley v Di Russo [2018] QCATA 46
Lyons v Dreamstarter Pty Ltd [2012] QCATA 71REPRESENTATION:
Applicant:
Aitchison Reid Pty Ltd
Respondent:
Construct Law Group Pty Ltd
APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld).
REASONS FOR DECISION
Mr and Mrs O’Toole (‘the applicants’) lodged an application for domestic building disputes on 1 June 2018. They sought payment of $110,109.18 from Qld Building Company Pty Ltd (‘the respondent’).
The application for domestic building disputes contains the following statement:
Please note – the Applicant has not submitted a formal notification letter from the QBCC as required. The Applicant lodged their QBCC complaint form on 31 May 2018. The delay in lodging the QBCC complaint form is due to misinformation that was provided to the Applicant as to their options for resolving the issues experienced with the Respondent. As such, the QBCC is yet to assess the complaint. The purpose of filing this application at this point in time is to attempt to preserve the time limits within which the Applicant has to make a claim, including under section 51 of the Domestic Building Contracts Act 2000 for proceedings for breach of warranties (which legislation was in effect at the time the Applicant entered into the contract with the Respondent). The QBCC complaint form has been submitted within the time limit that the QBCC has to issue a direction to rectify or remedy under section 72A(4) of the Queensland Building and Construction Commission Act 1991.
On 6 July 2018, the respondent lodged an application for miscellaneous matters, seeking to have the application for building disputes dismissed. The respondent claimed that the applicants have not complied with s 77 of the Queensland Building and Construction Commission Act 1991 (Qld) (‘the QBCC Act’).
Section 77 of the QBCC Act relevantly provides:
Tribunal may decide building dispute
(1) A person involved in a building dispute may apply, as provided under the QCAT…
Keep reading for free
Create a free CaseChat account to read O'Toole v Qld Building Company Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] QCAT 257
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the Tribunal was whether it had jurisdiction to hear the building dispute application when the applicants did not comply with the pre-litigation dispute resolution process mandated by the Queensland Building and Construction Commission. The applicants argued that they had attempted to resolve the dispute but had not followed the exact process as stipulated by the Commission. The Tribunal needed to assess whether non-compliance with the mandatory process deprived it of jurisdiction to hear the matter.
In addressing the jurisdictional issue, the Tribunal considered the legislative framework and the mandatory nature of the dispute resolution process. It determined that the statutory process was a prerequisite for the Tribunal to have jurisdiction over building disputes. Since the applicants did not comply with this process, the Tribunal concluded that it lacked the jurisdiction to hear the application. Consequently, the Tribunal dismissed the application and ordered that the applicants pay the respondent’s costs as agreed or, failing agreement, as assessed on the Magistrates Court scale of costs. This decision underscores the importance of adhering to statutory dispute resolution requirements in administrative matters.
Orders
Orders of the court
1. The application for building disputes filed on
1 June 2018 is dismissed.
2. John O’Toole and Kym O’Toole are to pay Qld Building Company Pty Ltd costs as agreed or, failing agreement within 28 days, as assessed on the Magistrates Court scale of costs.