[2007] TASSC 47
CITATION:Noye v Resource Management and Planning Appeal Tribunal [2007] TASSC 47
PARTIES: G F NOYE PTY LTD (ACN 009 538 309)
v
RESOURCE MANAGEMENT AND PLANNING APPEAL TRIBUNAL
BADHAM, Anthony J
TITLE OF COURT: SUPREME COURT OF TASMANIA
JURISDICTION: ORIGINAL
FILE NO/S: M49/2006
DELIVERED ON: 20 June 2007
DELIVERED AT: Hobart
HEARING DATE: 27 April 2007
JUDGMENT OF: Tennent J
CATCHWORDS:
Administrative Law – Judicial review – Grounds of review – Error of law.
Judicial Review Act 2000 (Tas), s17(2)(f).
Aust Dig Administrative Law [1030]
Administrative Law – Judicial review – Grounds of review – Generally – Lack of jurisdiction – Failure to consider relevant consideration – No evidence to justify making of decision.
Judicial Review Act 2000 (Tas), ss17(2)(d), (e), (h) and (i).
Aust Dig Administrative Law [1028]
REPRESENTATION:
Counsel:
Applicant: W A Ayliffe
Respondent: C M Schokman
Solicitors:
Applicant: Chris Boland Lawyers
Respondent: Ogilvie Jennings
Judgment Number: [2007] TASSC 47
Number of paragraphs: 48
Serial No 47/2007
File No M49/2006
G F NOYE PTY LTD (ACN 009 538 309) v RESOURCE MANAGEMENT
AND PLANNING APPEAL TRIBUNAL and ANTHONY J BADHAM
REASONS FOR JUDGMENT TENNENT J
20 June 2007
On 14 June 2005 the Assessment Committee for Dam Construction ("ACDC") constituted under the Water Management Act 1999 ("the WMA") issued a "Permit to construct a dam" pursuant to s157 to Anthony J Badham ("the respondent") in respect of an application he had made to carry out certain works ("the Dam works") on an existing dam at Premaydena ("the Dam").
The applicant in these proceedings appealed to the Resource Management and Planning Appeal Tribunal ("the Tribunal") against the decision to grant the permit. After a hearing, the Tribunal, in effect, confirmed the decision of the ACDC to issue the permit. The applicant has sought a review of the Tribunal's decision under the Judicial Review Act 2000 setting out five grounds of review. Prior to the hearing, the applicant abandoned ground 2. However, at the hearing he was given leave to reinstate it for the limited purpose of addressing an argument that the Tribunal failed to take into account a relevant consideration, namely the proposed use by the respondent of water from the Dam for commercial purposes, when considering the issue of detriment to the applicant under the WMA, s158(1)(c ) or (ca).
Background facts
The respondent and the applicant owned adjoining land at Premaydena. Predecessors in title to them both entered into an agreement dated 23 April 1968 ("the agreement") pursuant to which they agreed to build a dam which straddled the boundary between the two properties. The operative parts of the agreement were as follows:
"1 EACH party will allow the other to construct the dam and to accumulate water on the property of the other, the said dam and the accumulation of water being shown approximately on the plan drawn hereon.
2 EACH party shall be entitled to take such amount of water from the dam as they may require…
Continue reading Noye v Resource Management and Planning Appeal Tribunal
Sign in free to access the full text
- AGLC
- Noye v Resource Management and Planning Appeal Tribunal [2007] TASSC 47
- Case
- [2007] TASSC 47
- Decision Date
CaseChat Overview and Summary
The central legal issue before the court was whether the Tribunal had made an error of law in its decision-making process. Specifically, the applicant argued that the Tribunal had failed to properly consider relevant legislation and had not given adequate weight to particular evidence presented. The court had to determine whether these alleged errors warranted a quashing of the Tribunal's decision.
In examining the grounds for judicial review, the court found that the Tribunal had indeed made a significant error in its interpretation of the relevant planning legislation. The court held that the Tribunal had failed to consider a critical statutory provision that was pertinent to the appeal. Furthermore, the court noted that the Tribunal's decision-making process did not adequately account for all the evidence provided. Based on these findings, the court concluded that the Tribunal's decision was flawed and should be quashed.
The final orders of the court were to quash the decision of the Resource Management and Planning Appeal Tribunal and to remit the matter back to the Tribunal for reconsideration in light of the court's findings. The court emphasised that the Tribunal must adhere to proper legal principles and ensure that all relevant evidence and legislation are appropriately considered in future decision-making processes.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.