Novawest Contracting Pty Ltd v Altona Industrial Centre Pty Ltd

Link copied
Case Copied 13 min read

SUPREME COURT OF VICTORIA

COURT OF APPEAL

S APCI 2010 0167

NOVAWEST CONTRACTING PTY LTD Applicant
v
ALTONA INDUSTRIAL CENTRE PTY LTD Respondent

---

JUDGES TATE JA and HARGRAVE AJA
WHERE HELD MELBOURNE
DATE OF HEARING 8 April 2011
DATE OF JUDGMENT 2 May 2011
MEDIUM NEUTRAL CITATION [2011] VSCA 104
JUDGMENT APPEALED FROM Novawest Contracting Pty Ltd v Altona Industrial Centre Pty Ltd and CPG Australia Pty Limited [2010] VCC 1804 (Judge Ginnane)

---

PRACTICE AND PROCEDURE – Application for leave to appeal from interlocutory decisions of County Court – Decisions not attended with sufficient doubt to justify leave – Application refused. 

---

Appearances: Counsel Solicitors
For the Appellant Dr K P Hanscombe SC with
Ms K Bowshell
Patrick J Cannon Coburn & Associates Pty Ltd
For the Respondent Ms K E Judd SC with
Mr M T Settle
HorseForce Legal

TATE JA:

  1. I agree with Hargrave AJA.

HARGRAVE AJA:

  1. The applicant for leave to appeal, Novawest Contracting Pty Ltd, is a building and construction contractor.  The respondent, Altona Industrial Centre Pty Ltd, is the owner and developer of land in Altona.  Altona Industrial engaged Novawest to perform construction works on the land for the purposes of the development.  There were two contracts, one for the first three stages of the development (‘primary contract’) and one for the fourth stage of the development (‘further contract’). 

  1. Each of the contracts was, relevantly, in identical terms.  It incorporated General Conditions of Contract (AS 2124-1992).  Each of the contracts contained the following liquidated damages provision:

35.6     Liquidated Damages for Delay in Reaching Practical Completion

If the Contractor fails to reach Practical Completion by the Date for Practical Completion, the Contractor shall be indebted to the Principal for liquidated damages at the rate stated in the Annexure for every day after the Date for Practical Completion to and including the Date of Practical Completion or the date that the Contract is terminated under clause 44, whichever first occurs.[1] 

[1]Emphasis added. 

  1. The Annexure stated in each case that the agreed amount for liquidated damages is $500 per day with no limit on the amount which can be claimed. 

  1. The primary contract states that the Date for Practical Completion was 7 May 2004. 

  1. The further contract states that the Date for Practical Completion of stage 4 was 15 July 2005. 

  1. The first three stages of the development, under the primary contract, are alleged to have been completed.  The fourth stage of the development, under the

further contract, is alleged not to have been completed. 

  1. The respondent contends that each of the dates for practical completion were extended by the Superintendent under the contracts to a date which was ‘earlier than 28 March 2008’.  In an affidavit sworn by the Superintendent, he deposed that he no longer works for the employer employing him at the time he acted as Superintendent under the contracts, and cannot recall the exact dates to which he extended the times for practical completion under the contracts, other than to say that…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Novawest Contracting Pty Ltd v Altona Industrial Centre Pty... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2011] VSCA 104
Decision Date

CaseChat Overview and Summary

The case of Novawest Contracting Pty Ltd versus Altona Industrial Centre Pty Ltd involved an application for leave to appeal from interlocutory decisions made in the County Court. The dispute pertained to the interpretation of a contract between the parties, specifically focusing on the obligations and rights of the parties under the contract. The County Court had made several decisions that Novawest Contracting found unsatisfactory and sought to appeal.

The central legal issues that the court had to address were whether the interlocutory decisions of the County Court were attended with sufficient doubt to justify the grant of leave to appeal. Additionally, the court had to consider whether there were any errors in the County Court's interpretation of the contract and its application of relevant legal principles. The application for leave to appeal was essentially a challenge to the County Court's exercise of its discretion in making those interlocutory decisions.

In examining the application, the court assessed the arguments presented by both parties and considered the merits of the case. The court found that the decisions of the County Court were not attended with sufficient doubt to warrant an appeal. The reasoning of the County Court was thorough and well-reasoned, and there was no clear error in the interpretation of the contract or application of the law. Therefore, the court was satisfied that the County Court had exercised its discretion appropriately in making the interlocutory decisions. Consequently, the application for leave to appeal was refused.

As a result of the court's decision, the interlocutory decisions of the County Court remained in place, and no appeal was permitted. The court's refusal of the application for leave to appeal affirmed the County Court's jurisdiction and discretion in handling the interim matters of the case.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established