SUPREME COURT OF QUEENSLAND
CITATION: Northbuild Construction P/L v Discovery Beach Project P/L
(No 2) [2005] QSC 046PARTIES: NORTHBUILD CONSTRUCTION PTY LTD
ACN 011 063 764
(applicant)
v
DISCOVERY BEACH PROJECT PTY LTD
ACN 100500 981
(respondent)FILE NO/S: BS 1437 of 2005 DIVISION: Trial Division PROCEEDING: Application ORIGINATING
COURT:Supreme Court at Brisbane DELIVERED ON: 11 March 2005 DELIVERED AT: Brisbane HEARING DATE: 8 March 2005 JUDGE: Muir J ORDER
(a) The interim award made on 18 February 2005, a copy of which is Ex PJB-06 to the affidavit of Paul Joseph Boddington filed herein on 23 February 2005 be corrected by inserting the following paragraph bb) after paragraph b) on page 1 thereof – “Discovery Beach Project Pty Ltd pay Northbuild Constructions Pty Ltd the sum of $1,234,488.”
(b)
The applicant have leave to enforce such interim award
(c)
Judgment be entered against the respondent in favour of the applicant in the sum of $1,234,488.
CATCHWORDS: ARBITRATION – THE AWARD – FORM AND
CONSTRUCTION OF THE AWARD – CORRECTING
AND ALTERING AWARD BY COURT – where
arbitrator’s intention unclear – where consideration given to
the scope of the court’s power to remedy ‘an error arising
from an accidental slip or omission’Commercial Arbitration Act 1990, s 30 L Shaddock & Associates Pty Ltd v Parramatta City Council (No 2) (1982) 151 CLR 590
R v Cripps [1984] 1 QB 686
Raybos Australia Pty Ltd v Tectran Corporation Pty Ltd
[No 2] S. 86/130 [1988] HCA 2 (10 February 1988)COUNSEL:
P J Dunning for the applicant P A Hastie for the respondent
SOLICITORS: Ebsworth & Ebsworth Lawyers for the applicant
Minter Ellison for the respondentIntroduction
[1] On 3 March 2005 the applicant’s application for leave pursuant to s 33 of the
Commercial Arbitration Act 1990 (“the Act”) to enforce the interim award of an arbitrator dated 18 February 2005 was refused. The reason for the refusal was that the judgment against the respondent in favour of the applicant for a money sum, which the applicant sought, would not constitute the entering of judgment “in terms of the award” as required by s 33 of the Act. In his award the arbitrator had merely ordered in respect of the moneys in question, that the respondent “make no deduction” of them “from payments” to the applicant “with respect to” specified variation orders.
The applicant’s response was to bring this application for correction of the award under s 30 of the Act. Section 30 provides:
“30. Power to correct award. Where an award made under an arbitration agreement contains - (a) a clerical mistake; or (b) an error arising from an accidental slip or omission; or
(c)
a material miscalculation of figures or a material mistake in the description of any person, thing or matter referred to in the award; or
(d) a defect of form;
the arbitrator or umpire may correct the award or the Court, on the application of a party to the agreement, may make…
Keep reading for free
Create a free CaseChat account to read Northbuild Construction Pty Ltd v Discovery Beach Project Pt... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2005] QSC 46
- Decision Date
CaseChat Overview and Summary
The legal issues before the court included whether the court had the authority to correct an arbitration award under section 30 of the relevant Act and whether there was discretion to refuse such an order under section 33 if intervening circumstances rendered it inexpedient or inequitable. The court considered the principles established in prior authorities, which suggest that the court has the power to correct an award if it accidentally omitted to include an order that was clearly stated in the material before the arbitrator. The court also examined whether the failure to include the order was due to an inadvertent oversight by the arbitrator.
The court found that the arbitrator had indeed omitted to include the order for payment of the disputed moneys, which was clearly stated in the material before him, and there was no relevant dispute as to the quantum. The court concluded that there was adequate power under section 30 of the Act to correct the award. However, the court also considered the discretionary factors under section 33, particularly whether it would be inequitable to enter judgment for the amount claimed given that the interim award would have reduced the amount payable by the claimant to the principal. Ultimately, the court decided that it was just to allow the correction of the award to reflect the arbitrator's intention.
The final orders of the court included correcting the interim award by inserting the omitted paragraph, thereby ensuring that the respondent would be ordered to pay the applicant the disputed moneys. The court also decided that, given the applicant's failure on its initial application, there should be no order for costs.
Orders
Orders of the court
(a)
The interim award made on 18 February 2005, a copy of which is Ex PJB-06 to the affidavit of Paul Joseph Boddington filed herein on 23 February 2005 be corrected by inserting the following paragraph bb) after paragraph b) on page 1 thereof –
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
For the reasons given above, I find that the arbitrator accidentally omitted to include in the award an order that the respondent pay the applicant the disputed moneys. The amount of those moneys was clearly stated in the material before the arbitrator and there was no relevant dispute as to quantum. The principles expressed in the above authorities demonstrate that there is adequate power under s 30 of the Act to correct the award to make provision for an order for the payment of the sum claimed. Discretionary considerations Mr Hastie submits, correctly, that there is a discretion to refuse an order under s 33 if something has intervened which would render it inexpedient or inequitable that the order be made.[5] In this case he submits that it would be inequitable to enter judgment for the amount claimed given that “if the quantity surveyor had had an opportunity to examine and apply the interim award in Certificate No 2, the effect of the interim award would have been to reduce the amount payable by the claimant to the principal to $165,998.70”. [5] L Shaddock & Associates Pty Ltd v Parramatta City Council (No 2) (1982) 151 CLR 590. As was observed in the reasons of 3 March, a submission similar in its broad effect to this was agitated before the arbitrator and rejected by him on the grounds that the parties, by their agreement, had expressly stipulated the circumstances in which the respondent would be able to reduce progress payments. It does not seem to me to be just in the circumstances to deprive the applicant of the benefit of the August 2004 agreement and of the award. Conclusion Subject to any arguments the parties may wish to advance, it will be ordered that: Having regard to the applicant’s failure on its initial application it seems appropriate that there be no order for costs.