SUPREME COURT OF QUEENSLAND
CITATION:
Northbuild Construction P/L v Discovery Beach Project P/L [2009] QCA 235
PARTIES:
NORTHBUILD CONSTRUCTION PTY LTD
ACN 011 063 764
(appellant/applicant)
v
DISCOVERY BEACH PROJECT PTY LTD
ACN 100 500 981
(respondent/respondent)FILE NO/S:
Appeal No 7853 of 2007
SC No 11269 of 2006DIVISION:
Court of Appeal
PROCEEDING:
Application for Stay of Execution
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED EX TEMPORE ON:
18 August 2009DELIVERED AT:
Brisbane
HEARING DATE:
18 August 2009
JUDGE:
Holmes JA
ORDERS:
1. Application for stay dismissed;
2. Applicant pay respondent’s costs of application.
CATCHWORDS:
PROCEDURE – COSTS – RECOVERY OF COSTS – where applicant ordered to pay respondent’s costs following unsuccessful appeal – where applicant seeks stay of enforcement of costs order – where applicant has an order for costs and an interim award against respondent from an arbitration and anticipates an award in its favour – where applicant contends respondent impecunious and will dissipate any costs paid to it so that applicant will be unable to recover any amount awarded to it – where respondent asserts it is not insolvent and has paid more under an interim award than applicant will receive – whether applicant has discharged evidential onus – whether application for stay should be granted
COUNSEL:
C A Wilkins for the applicant
D O’Brien for the respondentSOLICITORS:
Crouch & Lyndon for the applicant
Clayton Utz for the respondent
HOLMES JA: The applicant, Northbuild, was the builder on a north coast hotel project, while Discovery Beach Project Pty Ltd was the developer.
Northbuild was unsuccessful in an appeal concerning a dispute resolution process between the two. It was ordered to pay costs which were assessed in an amount of $29,234.77. The certificate of the costs assessor was duly filed and, as Rule 740 of the Uniform Civil Procedure Rules required, the Registrar ordered payment of that amount, his order taking effect as a judgment of the Court.
On 6 August, Discovery Beach obtained the issue of an enforcement warrant. Northbuild applies under Rule 800 or, alternatively, in the inherent jurisdiction of this Court for a stay of the enforcement of the Registrar's order.
The basis of that application is essentially Northbuild's contention that it will receive a substantial award against Discovery Beach from an arbitration, but that Discovery Beach's financial position is such that it is likely to dissipate any costs paid to it immediately, leaving Northbuild with no prospect of recovery of any amount awarded to it by the arbitrator.
The arbitrator's award indicates that Northbuild was successful in having findings made by him in its favour. Northbuild contends that it can expect an award in excess of $1.3 million together with costs as a result. It already has in its favour an order for costs in relation to an interim award, the amount of which is yet to be determined, but in respect of which it contends it is likely to receive something in the order of $30,000, as I understand it;…
Keep reading for free
Create a free CaseChat account to read Northbuild Construction P/L v. Discovery Beach Project P/L and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2009] QCA 235
- Decision Date
CaseChat Overview and Summary
The court was required to decide whether Northbuild Construction had discharged the evidential onus to show that Discovery Beach Project was impecunious and would dissipate any costs paid to it. The court also needed to determine whether the application for a stay should be granted under the circumstances presented. The primary consideration was whether the applicant had provided sufficient evidence to support its claims regarding the respondent's financial status and the risk of dissipation of assets. The court examined the submissions and evidence provided by both parties to assess the likelihood of the applicant's ability to recover any awarded costs if the stay was not granted.
After thorough deliberation, the court dismissed the application for a stay of enforcement of the costs order. The court found that Northbuild Construction had not discharged the evidential onus required to support its claims of the respondent's impecuniosity and the risk of dissipation of assets. Consequently, the application for a stay was dismissed, and Northbuild Construction was ordered to pay Discovery Beach Project's costs of the application. This decision underscored the importance of substantiating claims with adequate evidence when seeking to avoid the enforcement of a costs order.
Orders
Orders of the court
1. Application for stay dismissed;
2. Applicant pay respondent’s costs of application.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.