SUPREME COURT OF QUEENSLAND
CITATION:
North Queensland Pipeline No 1 Pty Ltd & Anor v QNI Resources Pty Ltd & Anor [2020] QSC 158
PARTIES:
NORTH QUEENSLAND PIPELINE NO 1 PTY LTD
ABN 64 100 946 281(first plaintiff)
and
NORTH QUEENSLAND PIPELINE NO 2 PTY LTD
ABN 60 100 946 263
(second plaintiff)v
QNI RESOURCES PTY LTD
ABN 14 054 117 921
(first defendant)
and
QNI METALS PTY LTD
ABN 56 066 656 175(second defendant)
FILE NO:
8063 of 2018
DIVISION:
Trial Division
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
5 June 2020
DELIVERED AT:
Brisbane
HEARING DATE:
29 May 2020
JUDGE:
Applegarth J
ORDER:
1. Pursuant to r 171 of the Uniform Civil Procedure Rules 1999 (Qld), paragraphs 59 – 62 of the amended defence and paragraph 2(c) of the reply to the answer to the counterclaim be struck out.
2. Leave granted for the defendants to file an amended defence and counterclaim and amended reply to the answer to the counterclaim to:
a. amend paragraphs 17 and 27 of the defence; and
b. raise the contention that to the extent they are liable under cl 41.6.3 of the GTA, their only liability is one for damages for breach of contract in respect of an alleged secondary obligation.
3. Subject to any submissions as to costs, the defendants pay the plaintiffs’ costs of and incidental to the application dated 7 May 2020 insofar as it related to the application to strike out paragraphs 59 – 62 of the amended defence and paragraph 2(c) of the reply to the answer to the counterclaim.
4. The costs of the balance of the application be costs in the cause.
CATCHWORDS:
PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – PLEADINGS – STRIKING OUT – DISCLOSING NO REASONABLE CAUSE OF ACTION OR DEFENCE – where each plaintiff sues each defendant for sums alleged to be amounts due and owing under a gas transportation agreement – where damages for breach of contract are not claimed – where the defendants plead that “the plaintiffs had an obligation to take all reasonable steps to mitigate or minimise any loss and damage consequent upon the alleged breach” – where the defendants accept that a failure to mitigate is not a defence to an action to recover a debt – where the defendants contend that notwithstanding the form of the action as one in debt, in substance, it is an action for damages – where the defendants contend that to the extent they are liable, their only liability is for damages for breach of contract – where that contention is not presently pleaded in the defence – where the defendants accept that the plaintiffs’ claims in debt are at least arguable - whether the mitigation allegations made by the defendants should be struck out for failure to disclose a reasonable defence
Keep reading for free
Create a free CaseChat account to read North Queensland Pipeline No 1 Pty Ltd v QNI Resources Pty L... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] QSC 158
- Decision Date
CaseChat Overview and Summary
The legal issues centered on the nature of the plaintiffs' claim and the scope of permissible defences. The defendants argued that despite the plaintiffs' claims being framed as debts owed under the contract, the essence of the claim was for damages. They contended that a failure to mitigate could be a defence to such a claim, even though it was not a defence to an action for debt. The defendants also suggested that their liability, if any, would only be for damages for breach of contract, not the debt claimed. The court had to determine whether these contentions, particularly the mitigation allegations, disclosed a reasonable defence.
The court found that the mitigation allegations did not disclose a reasonable defence because they did not align with the form of the plaintiffs' action, which was for debt. The court noted that the defendants accepted the plaintiffs' claims were at least arguable and that a failure to mitigate was not a defence to a debt claim. The court held that the mitigation allegations were irrelevant to the plaintiffs' claims and could mislead the plaintiffs. Consequently, the court ordered the mitigation allegations be struck out, while allowing the defendants to amend their defence to properly plead their contention about liability for damages for breach of contract.
In summary, the court ruled that the mitigation allegations did not constitute a reasonable defence to the plaintiffs' debt claims and ordered them to be struck out. The defendants were granted leave to amend their defence to properly plead their contention about liability for damages, and the plaintiffs were awarded costs related to the application for striking out the mitigation allegations.
Orders
Orders of the court
1. Pursuant to r 171 of the Uniform Civil Procedure Rules 1999 (Qld), paragraphs 59 – 62 of the amended defence and paragraph 2(c) of the reply to the answer to the counterclaim be struck out.
2. Leave granted for the defendants to file an amended defence and counterclaim and amended reply to the answer to the counterclaim to:
a. amend paragraphs 17 and 27 of the defence; and
b. raise the contention that to the extent they are liable under cl 41.6.3 of the GTA, their only liability is one for damages for breach of contract in respect of an alleged secondary obligation.
3. Subject to any submissions as to costs, the defendants pay the plaintiffs’ costs of and incidental to the application dated 7 May 2020 insofar as it related to the application to strike out paragraphs 59 – 62 of the amended defence and paragraph 2(c) of the reply to the answer to the counterclaim.
4. The costs of the balance of the application be costs in the cause.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi