NORRIS v HANSON & HANSON
[1998] SASC S6882
Magistrates Appeal
OLSSON J
This is an appeal, by a defendant at first instance, against the decision of a stipendiary magistrate sitting in the Civil Jurisdiction of the Magistrates Court.
That decision is supported by detailed written reasons running to some 123 pages. These reflect a close analysis of oral evidence and argument which spanned many hearing days.
As readily appears from the reasons, the learned magistrate was confronted with differing versions of historical fact which were impossible to reconcile. At the end of the day he made specific findings of relative credibility as to the principal parties and certain of the other witnesses called. These findings formed what were, essentially, the linch pin of the conclusions to which he ultimately came.
One of the major features of his findings was that the learned magistrate generally preferred the evidence of the male respondent/defendant and his witnesses to that of the appellant. A perusal of the published reasons readily reveals that there was a substantial body of evidence which supported the conclusion to which he came in that regard. It was a view fairly open to him, with which, on well settled grounds of principle, it is quite inappropriate for this court to interfere.
I do not find it necessary, for present purposes, to embark on a fully definitive analysis of the evidence.
The litigation stemmed from an informal agreement made between the appellant and the respondents in late 1995, whereby the latter, an earthmoving and civil construction contractor, undertook to develop a private airstrip on a property at Springton which had been purchased by the former. Disputes arose between the parties both as to the fundamental terms of the contract and also whether the airstrip works, as executed, conformed with the obligations of the respondents, as originally agreed. Additionally, the claim involved questions concerning the construction of a dam on the property, as incidental to what were the main contract works.
A major issue which arose at trial was as to whether the works related to the airstrip were to be executed for a fixed contract price, or were to be performed on what might be described as a “charge up” basis, reflecting time and plant actually expended and used.
At trial it was virtual common ground that, at the time at which work actually got under way, both parties understood that it was to be performed for an agreed, “all up” sum, “subject to finding rock”.
There is no doubt that this was based on a document signed on behalf of the respondents and expressed in these terms:-
“ 6/9/95
Greg Norris
Springton SATo carry out works as discussed
1...... Cut & fill to desired falls and batters for airstrip
2...... Supply concrete pipes under airstrip and roadways Rocla 300 concrete pipes
3...... Excavate for dam
4...... Regrade existing road and roll
5...... Shape and form new section of road and supply and compact base material
6......…
Continue reading Norris v Hanson & Hanson No. Scgrg-98-101 Judgment No. S6882
Sign in free to access the full text
- AGLC
- Norris v Hanson & Hanson No. Scgrg-98-101 Judgment No. S6882 [1998] SASC 6882
- Case
- [1998] SASC 6882
- Decision Date
CaseChat Overview and Summary
The court examined the evidence presented and the findings made by the magistrate, which were detailed and based on the relative credibility of the parties and witnesses. The magistrate found that the contract was agreed to be performed for an hourly rate after the initial fixed price agreement was altered due to unforeseen hard rock encountered during the earthmoving activities. The court upheld the magistrate's findings, stating that it was a view fairly open to him and inappropriate for the court to interfere. The court further found that the scope of the work, as described by Norris, was to cut the tops off the hills and fill in the valleys along the length of the runway, and not to create an even gradient as Norris claimed.
The court also rejected the appellant's claims regarding the implied warranty of fitness for the purpose of the airstrip and the mitigation of damages concerning the dam. The court held that the appellant did not rely on the respondents' expertise and skill for constructing the airstrip, and the failure to create an even gradient was a matter within the appellant's expertise. Regarding the dam, the court found that the appellant got what was contracted for and could not now claim additional costs for a larger capacity dam.
Ultimately, the appeal was dismissed on both grounds, affirming the magistrate's decision.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.