Norcast S.ár.L v Bradken Limited (No 3)

Link copied
Case Copied 16 min read

FEDERAL COURT OF AUSTRALIA

Norcast S.ár.L v Bradken Limited (No 3) [2013] FCA 283

Citation: Norcast S.ár.L v Bradken Limited (No 3) [2013] FCA 283
Parties: NORCAST S.ÁR.L v BRADKEN LIMITED, NICHOLAS FRANK HUGO GREINER and BRIAN HODGES
File number: VID 356 of 2012
Judge: GORDON J
Date of judgment: 28 March 2013
Date of hearing: Determined on the papers
Date of last submissions: 26 March 2013
Place: Melbourne
Division: GENERAL DIVISION
Category: No Catchwords
Number of paragraphs: 23
Counsel for the Applicant: Mr C M Scerri QC and Mr M Borsky
Solicitor for the Applicant: Allens
Counsel for the Respondents: Mr N J Young QC and Mr S H Parmenter
Solicitor for the Respondents: King & Wood Mallesons

IN THE FEDERAL COURT OF AUSTRALIA

VICTORIA DISTRICT REGISTRY

GENERAL DIVISION

VID 356 of 2012

BETWEEN:

NORCAST S.ÁR.L
Applicant

AND:

BRADKEN LIMITED
First Respondent

NICHOLAS FRANK HUGO GREINER
Second Respondent

BRIAN HODGES
Third Respondent

JUDGE:

GORDON J

DATE OF ORDER:

28 MARCH 2013

WHERE MADE:

MELBOURNE

THE COURT DECLARES THAT:

Cartel conduct

1.By entering into a bid rigging arrangement by no later than 8 March 2011, whereby Castle Harlan, Inc (Castle Harlan) agreed to bid for Norcast Wear Solutions, Inc (NWS) and the First Respondent (Bradken) agreed not to bid for NWS (Bid Rigging Arrangement), Bradken contravened s 44ZZRJ of the Competition and Consumer Act 2010 (Cth) (the CCA).

2.By giving effect to the Bid Rigging Arrangement during the period from 8 March to 6 July 2011, Bradken contravened s 44ZZRK of the CCA.

3.By making or arriving at the Bid Rigging Arrangement, Castle Harlan contravened s 44ZZRJ of the CCA.

4.By giving effect to the Bid Rigging Arrangement during the period from 8 March to 6 July 2011, Castle Harlan contravened s 44ZZRK of the CCA.

5.Bradken was a person involved, within the meaning of s 75B of the CCA, in the contraventions by Castle Harlan referred to in paragraphs 3 and 4 above (Castle Harlan cartel contraventions).

6.The Second Respondent (Greiner) and the Third Respondent (Hodges) were persons involved, within the meaning of s 75B of the CCA, in the contraventions by Bradken referred to in paragraphs 1 and 2 above and the Castle Harlan cartel contraventions.

Misleading or deceptive conduct

7.Bradken has, during the period from late February 2011 to 6 July 2011, in trade or commerce, engaged in conduct that was misleading or deceptive, or likely to mislead or deceive, in contravention of s 18 of Sch 2 to the CCA (ACL) by its silence about the Bid Rigging Arrangement and about the fact that Bradken and Castle Harlan were cooperating for the purpose of acquiring NWS and had a back to back sale arrangement.

8.Castle Harlan has, in trade or commerce, engaged in conduct that was misleading or deceptive, or likely to mislead or deceive, in contravention of s 18 of the ACL by:

8.1its silence during the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Norcast S.ár.L v Bradken Limited (No 3) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] FCA 283
Decision Date

CaseChat Overview and Summary

Norcast S.ár.L initiated legal proceedings against Bradken Limited, seeking damages for alleged misleading or deceptive conduct and breach of competition laws. The case revolved around the discovery of a bid rigging arrangement, where Bradken and Castle Harlan colluded to manipulate the acquisition of Norwest Steel (NWS). The Federal Court of Australia was tasked with determining the extent of the misleading or deceptive conduct, the damages owed, and other consequential matters.

The primary legal issues before the court were whether Bradken and Castle Harlan had indeed engaged in bid rigging, and if so, the extent to which this conduct misled Norcast. Additionally, the court needed to decide on the appropriate quantum of damages, pre-judgment interest, and whether a stay of execution of the judgment should be granted pending any appeal. The court also had to consider the statutory provisions governing interest rates and the conditions for a stay of execution.

The Federal Court found that Bradken and Castle Harlan had indeed engaged in misleading or deceptive conduct, which extended beyond the bid rigging arrangement to include their cooperation in acquiring NWS and a back-to-back sale arrangement. The court concluded that these findings warranted the declaration of misleading or deceptive conduct. Regarding the damages, the court awarded Norcast US$22,400,000, pre-judgment interest of US$2,940,690.41, and post-judgment interest at the applicable rates. The court also granted a stay of execution of the judgment pending appeal, contingent upon Bradken providing a bank guarantee of US$25,340,690.41.

The final orders mandated Bradken to pay Norcast the awarded damages and interest, with costs on a party and party basis until a certain date and on an indemnity basis thereafter. The stay of execution would last until the later of seven days after the appeal period expires or seven days after any appeal is finalized, provided Bradken deposited the required guarantee by a specified date. The security held by Norcast for Bradken's costs remained in escrow under the same conditions.

Orders

Orders of the court

11. The Respondents pay to the Applicant:

11.1 damages under s 82 of the CCA and/or s 236 of the ACL in the amount of US$22,400,000 (or the AU$ equivalent at the time of payment or execution);

11.2 pre-judgment interest in the amount of US$2,940,690.41 (or the AU$ equivalent at the time of payment or execution) calculated from 6 July 2011 to 28 March 2013 in accordance with s 51A of the Federal Court of Australia Act 1976 (Cth) (the FCA); and

11.3 post judgment interest on US$22,400,000 (or the AU$ equivalent at the time of payment or execution) calculated from 28 March 2013 in accordance with s 52 of the FCA at the rate or rates applicable pursuant to r 39.06 of the Federal Court Rules 2011 (Cth) (the Rules) from time to time.

12. The Respondents pay the Applicant’s costs of and incidental to this proceeding, including the costs of and incidental to proceeding VID 978 of 2011, in accordance with r 25.14(3) of the Rules:

12.1 on a party and party basis to 11:00 am on 15 May 2012; and

12.2 on an indemnity basis from that time onwards.

13. There be a stay of execution of paragraphs 11 and 12 above until the later of:

13.1 seven days from the date on which the time permitted for the Respondents to appeal from these orders has expired without an appeal being commenced; or

13.2 seven days from the date that final orders were made in any appeal from these orders, but on condition that the Respondents deposit, on or before 30 April 2013, US$25,340,690.41 (or the AU$ equivalent at the time of payment) into an interest bearing account set up and controlled by the Federal Court of Australia pursuant to Div 2.5 of the Rules.

14. The security provided by the Applicant for the Respondents’ costs of this proceeding in the amount of $227,500, held by the Applicant’s solicitors pursuant to an Escrow Agreement dated 25 July 2012 between the Applicant and the Respondents, remain in escrow until the later of:

14.1 seven days from the date on which the time permitted for the Respondents to appeal from these orders has expired without an appeal being commenced; or

14.2 seven days from the date that final orders are made in any appeal from these orders.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011 (Cth).

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

That submission ignores the findings made in the Reasons: see Reasons [306], [315] and [320]. The misleading or deceptive conduct by silence was not only a misrepresentation as to the Bid Rigging Arrangement but also in relation to Bradken and Castle Harlan’s cooperation for the purpose of acquiring NWS and the existence of a back to back sale arrangement. Those findings are important. The conclusion in relation to misleading or deceptive conduct does not depend upon the existence of the Bid Rigging Arrangement, although, having concluded that there was a Bid Rigging Arrangement, that arrangement was one element of it. Accordingly, the declaratory relief has been crafted to reflect all of the elements of the misleading or deceptive conduct.PRE-JUDGMENT INTEREST Section 51 of the FCA, provides that:(1)In any proceedings for the recovery of any money (including any debt or damages or the value of any goods) in respect of a cause of action that arises after the commencement of this section, the Court or a Judge shall, upon application, unless good cause is shown to the contrary, either: (a)order that there be included in the sum for which judgment is given interest at such rate as the Court or the Judge, as the case may be, thinks fit on the whole or any part of the money for the whole or any part of the period between the date when the cause of action arose and the date as of which judgment is entered; or (b)without proceeding to calculate interest in accordance with paragraph (a), order that there be included in the sum for which judgment is given a lump sum in lieu of any such interest. The Respondents accepted that an order for pre-judgment interest was appropriate. The orders reflect that fact. STAY OF EXECUTION The Respondents sought a stay of execution of the final orders pursuant to s 29 of the FCA and / or r 36.08(2) of the Federal Court Rules 2011 (Cth) (the Rules) until the later of:1.seven days from the date on which the time permitted for the Respondents to appeal from the judgment has expired without an appeal being commenced; or 2.seven days from the date that final orders were made in any appeal in these proceedings but on condition that the Respondents provided, on or before 30 April 2013, to the solicitors for Norcast, security for the total amount of the sum payable in accordance with orders 1, 2 and 3 and any interest thereon, by way of a bank guarantee in favour of Norcast. Norcast opposed the application for an order staying the execution of the judgment pending appeal. Alternatively, Norcast submitted that if an order were to be made staying the execution of the judgment, then such order should be made subject to a condition that the Respondents pay into the Litigants’ Fund the full amount of the judgment sum and that any interest earned on the money follow the event. The relevant principles are well established. The prima facie assumption must be that the judgment appealed from is correct and that the Court should not deprive a litigant of the benefit of a judgment in its favour: Powerflex Services Pty Ltd v Data Access Corporation (1996) 67 FCR 65 at 66. The question which then arises is whether the balance of convenience favours the grant of a stay? Unsurprisingly, the Respondents submitted that the answer to that question was yes for reasons that included that:1.Norcast is a limited company incorporated in, and which has its principal place of business in, Luxembourg;2.Luxembourg is a foreign jurisdiction with which Australia has no treaty or reciprocal arrangement in relation to the recognition or enforcement of judgments in civil matters;3.Norcast is a subsidiary of Pala, and neither Norcast nor Pala has any current assets or business presence in Australia;4.Norcast has previously provided security for the Respondents’ costs of this proceeding;5.in light of the matters referred to above, if no stay is granted and the appeal succeeds, there is a risk that the Respondents will be unable to recover the judgment sum from Norcast and the appeal will be rendered nugatory;6.on the other hand, if a stay is granted and the appeal fails, interest will accrue on the judgment sum, and Norcast will be protected by the bank guarantee which it is proposed will be required to be provided;7.there are arguable grounds of appeal including in relation to the proper construction and application of the complex facts of the cartel conduct provisions which have not previously been considered by the courts; and8.the disputed factual and legal issues were complex.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.