QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Nicol v Queensland Building and Construction Commission & anor [2022] QCAT 236
PARTIES:
JOHN NICOL (applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION (respondent)
JENNIFER VALES (respondent)
APPLICATION NO/S:
GAR122-19
MATTER TYPE:
General administrative review matters
DELIVERED ON:
3 June 2022
HEARING DATE:
15 March 2021
4 May 2021
HEARD AT:
Brisbane
DECISION OF:
Member Paratz AM
ORDERS:
1. The decision of the Queensland Building and Construction Commission made on 5 March 2019, to allow the insurance claim under the statutory insurance scheme, is confirmed.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – where the Queensland Building and Construction Commission made a decision that a residential building contract had been properly terminated – where the builder used timber rather than steel for certain beams– where it was held that the builder was in substantial breach of the Contract
APPEARANCES & REPRESENTATION:
Applicant:
Self-Represented
QBCC:
Jennifer Vales:
M. Robinson of Robinson Locke Litigation Lawyers
Self-Represented
REASONS FOR DECISION
Jennifer Vales (‘the owner’) entered into a ‘QBCC Level 2 Renovation, Extension and Repair Contract’ (‘the contract’) dated 22 April 2018 with John Nicol (‘the builder’) for work on her house in Brisbane, Queensland.
The owner and the builder fell into dispute as to completion of the contract, and the owner terminated the contract by email on 29 October 2018.
The owner subsequently made a claim upon the statutory insurance scheme administered by the Queensland Building and Construction Commission (‘the QBCC‘).
The QBCC made a decision on 4 February 2019 to disallow the owner’s insurance claim. The owner sought an internal review of that decision.
The QBCC made an internal review decision on 5 March 2019 to allow the owners insurance claim under the statutory insurance scheme.
The builder filed an Application to review the decision of the QBCC of 5 March 2019 in the Tribunal.
The Application was heard by me by an oral hearing on 15 March 2021 and 4 May 2021. I reserved my decision, and gave directions for the filing of submissions by the builder in response to the closing submissions of the other parties, which were subsequently received.
These are my reasons in the matter.
The decision of the QBCC
The internal review decision of the QBCC made on 5 March 2019 was as follows:[1]
I have decided to allow the applicant’s insurance claim under the statutory insurance scheme. The contract between the parties was validly terminated.
[1]QBCC decision notice 5 March 2019, p 1.
The background to the decision was described in the internal review decision as follows:[2]
It is agreed by both parties that the affected party (John Nicol) was contracted to carry out renovations to the existing home of the property pursuant to a QBCC level 2 Renovation, Extension and Repair contract with the applicant (Jennifer Vales) dated 22 April 2018. The works are described at item 3 as ‘House renovations; see plans quote specs’. The progress payment schedule divided the work into stage…
Keep reading for free
Create a free CaseChat account to read Nicol v Queensland Building and Construction Commission and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] QCAT 236
- Decision Date
CaseChat Overview and Summary
The Tribunal found that the full engineering plans were indeed provided to the builder at the time of signing the contract, contrary to the builder's claims. The Tribunal was satisfied that the contract clearly required steel beams for the relevant area of the renovation, and the builder's decision to use timber beams was not documented as a variation or agreed upon by the owner or her father, Milan Vales. The use of timber beams led to structural deficiencies that prevented certification and completion of the contract. The Tribunal concluded that the builder's actions constituted a substantial breach of the contract under clause 26.4, which permitted the owner to terminate the contract. Given that the contract was lawfully terminated, the decision of the QBCC to allow the owner’s insurance claim under the statutory insurance scheme was confirmed.
The Tribunal's decision was grounded in the clear terms of the contract, the evidence presented by the parties, and the statutory provisions governing the insurance scheme. The Tribunal found that the owner's termination of the contract was justified based on the builder's substantial breach, and thus the QBCC's decision to allow the insurance claim was correct. The Tribunal ordered that the decision of the QBCC made on 5 March 2019 be confirmed.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi