Nick Manevski v Ben Jennings

Case [2014] NSWCATCD 179


NSW Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Nick Manevski v Ben Jennings [2014] NSWCATCD 179
Decision date: 12 September 2014
Before: D Goldstein, Senior Member
Decision:

1. The respondent Ben Jennings must pay the applicant Nick Manevski the sum of $15,907.38 within 14 days of the date of this order.

2. Either party is at liberty to make a costs application in these proceedings.

3. Any costs application pursuant to section 53 of the Consumer, Trader and Tenancy Tribunal Act 2001 or rule 20 of the Consumer, Trader and Tenancy Tribunal Regulation 2009 must be lodged in the Tribunal and served on the costs respondent within 21 days of the date of this order either attaching or referring to the documents relied upon in support of the application.

4. The costs respondent will have 21 days after the date he receives the costs application referred to above, to lodge in the Tribunal and serve on the costs applicant his submissions, if any, in response to the costs application, such submissions either attaching or referring to the documents relied upon.

5. The cost applicant will have 14 days after the date he receives the cost respondent's submissions to lodge in the Tribunal and serve on the costs respondent his submissions, if any, in reply, such submissions either attaching or referring to the documents relied upon.

6. The Tribunal will determine any costs application on the basis of the papers lodged in the Tribunal.

Catchwords: Whether applicant entitled to damages for own labour, defective work.
Legislation Cited: Home Building Act 1989
Consumer, Trader and Tenancy Tribunal Act 2001
Cases Cited: Laurence Peter Thomas v Powercor Australia Limited [2011] VSC 586
Texts Cited: None cited
Category:Principal judgment
Parties: Nick Manevski (applicant)
Ben Jennings (respondent)
File Number(s):HB 13/59143
Publication restriction:Unrestricted

reasons for decision

APPLICATION

  1. In these proceedings the applicant seeks the sum of $53,884.00 from the respondent for rectification of allegedly defective residential building work carried out by the respondent under a contract with the applicant. The applicant also claimed in connection with work allegedly contracted for, but not carried out.

  1. The applicant was having work carried out as an owner builder at premises situate at 33 Fisher Street Wollongong.

  1. In these reasons for decision I will refer to the applicant as the owner builder and to the respondent as the builder.

  1. These proceedings were finally heard in Wollongong on 1 August 2014. Neither party was legally represented.

  1. The contract the subject of these proceedings was dated 8 October 2008 and consisted of a simple quotation. The contract does not comply with the provisions of the Home Building Act 1989 (the 'Act'), although nothing turns on that since the builder makes no claim against the owner builder in these proceedings.

  1. The work that the builder was to carry out was described in the quotation as:

(a)   Build wall frames & trusses;

(b)   Bearers and joists;

(c)   Rear verandah;

(d)   Cladding, wall & gable;

(e)   Colourbond roofing;

(f)…

Continue reading Nick Manevski v Ben Jennings

Sign in free to access the full text

Details
AGLC
Nick Manevski v Ben Jennings [2014] NSWCATCD 179
Case
[2014] NSWCATCD 179
Decision Date

CaseChat Overview and Summary

Nick Manevski brought a claim against Ben Jennings, asserting that Jennings had failed to complete a building project to an acceptable standard and that Manevski was entitled to damages for his own labour and defective work. The dispute was heard by the Consumer, Trader and Tenancy Tribunal. The central legal issues in the case were whether Manevski was entitled to compensation for his own labour and whether Jennings had breached the terms of their agreement by delivering substandard work.

The tribunal examined the terms of the agreement between the parties and the evidence presented regarding the quality of Jennings' work. It found that Jennings had indeed delivered substandard work, falling short of the standards agreed upon in the contract. Furthermore, Manevski had incurred additional costs to rectify the deficiencies in Jennings' work, justifying his claim for compensation for his own labour. Based on these findings, the tribunal ruled that Manevski was entitled to damages for his own labour and the defective work. It ordered Jennings to pay Manevski the sum of $15,907.38 within 14 days of the order. The tribunal also outlined the procedure for any costs applications that either party might wish to make in relation to the proceedings.

Orders

Orders of the court

1. The respondent Ben Jennings must pay the applicant Nick Manevski the sum of $15,907.38 within 14 days of the date of this order.

2. Either party is at liberty to make a costs application in these proceedings.

3. Any costs application pursuant to section 53 of the Consumer, Trader and Tenancy Tribunal Act 2001 or rule 20 of the Consumer, Trader and Tenancy Tribunal Regulation 2009 must be lodged in the Tribunal and served on the costs respondent within 21 days of the date of this order either attaching or referring to the documents relied upon in support of the application.

4. The costs respondent will have 21 days after the date he receives the costs application referred to above, to lodge in the Tribunal and serve on the costs applicant his submissions, if any, in response to the costs application, such submissions either attaching or referring to the documents relied upon.

5. The cost applicant will have 14 days after the date he receives the cost respondent's submissions to lodge in the Tribunal and serve on the costs respondent his submissions, if any, in reply, such submissions either attaching or referring to the documents relied upon.

6. The Tribunal will determine any costs application on the basis of the papers lodged in the Tribunal.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.