LAND COURT OF QUEENSLAND
CITATION: New Acland Coal Pty Ltd v Oakey Coal Action Alliance Inc. & Ors (No 2) [2021] QLC 44 PARTIES: New Acland Coal Pty Ltd
ACN 081 022 380
(applicant)v Oakey Coal Action Alliance Inc.
(active party objector)and
Frank Ashman, Lynn Ashman, Glenn Beutel, John Cook, Patricia Cook, Darling Downs Environment Council Inc, Hazel Green, Angela Mason, Paul Mason, Geralyn McCarron, Merilyn Plant, Sid Plant, Tanya Plant, Janet Schick, John Schick, Jane Scholefield, Max Scholefield, Desley Spies, Kevin Spies, Cheryl Vonhoff, David Vonhoff, Steven Ward, Fay Wieck, Grant Wieck, Noel Wieck and Simon Wieck
(MRA objectors)and
Frank Ashman, Lynn Ashman, Glenn Beutel, Russell Byron, Clean Air Queensland, Christopher Cleary, Naomi Cleary, John Cook, Patricia Cook, Paul Evans, Pamela (“Aileen”) Harrison, Karen Lavin, Carolyn Lunt, John Millane, Merilyn Plant, Sid Plant, Tanya Plant, Nardi Rowe, Frances Scarano, Jane Scholefield, Max Scholefield, Desley Spies, Kevin Spies, John Standley, Cheryl Vonhoff, David Vonhoff, Steven Ward, Pamole White, Grant Wieck, Noel Wieck and Simon Wieck
Angela Mason (s 186(d) objector)
(EPA objectors)and
Chief Executive, Department of Environment and Science
(statutory party)FILE NOs: MRA026-21 (MLA 700002)
MRA027-21 (MLA 50232)
EPA028-21 (EPML 00335713)PROCEEDING: Remitted hearing of applications for, and objections to, mining leases and related environmental authority DELIVERED ON: 17 December 2021 DELIVERED AT: Brisbane HEARD ON: 26, 27 & 28 October 2021; 1, 2, 5, 8, 10, 11, 15 & 25 November 2021 HEARD AT: Toowoomba and Brisbane MEMBER: PG Stilgoe OAM RECOMMENDATION: I make the following recommendations, pursuant to s 269(1) of the Mineral Resources Act 1989, to the Minister for Resources, as the Minister responsible for the Mineral Resources Act 1989:
1. I recommended that MLA 700002 and MLA 50232 be granted.
2. The recommendation stated in paragraph 1 is subject to the condition that it does not take effect unless and until:
(a) The applicant applies to the Coordinator-General to amend the environmental authority (EPML 00335713) to account for the conditions as amended by the hearing and/or these reasons;
(b) The Coordinator-General amends those stated conditions; and
(c) The Department of Environment and Science, as the administering authority for the Environmental Protection Act 1994, incorporates the stated conditions (as amended by the Coordinator-General) in the draft environmental authority.
3. Subject to the condition stated in paragraph 2, I recommend the administering authority approve the application to amend EPML 00335713 on the conditions stated in the draft environmental authority, subject to such additions and amendments as are necessary to give effect to these reasons.
4. If the condition in paragraph 2 is not fulfilled by 31 May 2022 or, if before that date the Coordinator-General decides not to amend those stated conditions, I recommend the Department of Environment and Science, as the administering authority for the Environmental Protection Act 1994, refuse the application to amend EPML 00335713.
5. I direct the Registrar to provide, as soon as practicable, a copy of these recommendations and the reasons to:
(a) The…
Keep reading for free
Create a free CaseChat account to read New Acland Coal Pty Ltd v Oakey Coal Action Alliance Inc. (N... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] QLC 44
- Decision Date
CaseChat Overview and Summary
The primary legal issues the court had to address were whether to recommend the grant of the leases under section 269 of the Mineral Resources Act 1989, and if so, under what conditions. The court also had to consider the implications of section 58(1) of the Human Rights Act 2019, which requires the court to take into account the impact of the mining leases on human rights. The court was required to balance these considerations against the statutory requirements of the Mineral Resources Act.
In making its determination, the court carefully weighed the statutory factors under section 269(4) of the Mineral Resources Act 1989, including the economic benefits of the leases, the environmental impacts, and the public interest. The court found that while the leases would have some adverse environmental effects, these impacts could be adequately managed. The court also concluded that the human rights impacts would be adequately managed, and the balance of competing factors favoured granting the leases. Consequently, the court recommended the grant of the leases with specific conditions attached to ensure the proper management of environmental and human rights impacts.
The court imposed several conditions to mitigate potential adverse impacts, including a requirement for New Acland Coal to apply to the Coordinator-General to amend the environmental authority. Additionally, the court recommended that the administering authority approve the application to amend the environmental authority if the applicant complied with the conditions. Conversely, if the applicant did not apply to the Coordinator-General or if the Coordinator-General declined to amend the conditions, the court recommended that the administering authority refuse the application to amend the environmental authority. This nuanced approach aimed to balance economic benefits with environmental and human rights considerations.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi