Nepean Rubber Moulding Pty Ltd v Veljanoski

Link copied
Case Copied 9 min read
WORKERS COMPENSATION COMMISSION
DETERMINATION OF APPEAL AGAINST A DECISION OF THE COMMISSION CONSTITUTED BY AN ARBITRATOR
CITATION: Nepean Rubber Moulding Pty Ltd v Veljanoski [2014] NSWWCCPD 3
APPELLANT: Nepean Rubber Moulding Pty Ltd
RESPONDENT: Mito Veljanoski
INSURER: Employers Mutual NSW Limited
FILE NUMBER: A1-9856/12
ARBITRATOR: Mr John Harris
DATE OF ARBITRATOR’S DECISION: 15 October 2013
DATE OF APPEAL DECISION: 22 January 2014
SUBJECT MATTER OF DECISION: Absence of transcript of arbitral proceedings; duty to provide sufficient reasons; constructive failure to provide reasons for decision; need for remitter
PRESIDENTIAL MEMBER: Deputy President Kevin O'Grady
HEARING: On the papers
REPRESENTATION: Appellant: Bartier Perry Lawyers
Respondent: Turner Freeman Lawyers
ORDERS MADE ON APPEAL:

1.       Paragraphs 1, 2, 3 and 4 of the Certificate of Determination, dated 15 October 2013, are revoked.

2.       The matter is remitted to a different Arbitrator for determination afresh.

3.       The costs of the hearing and of this appeal are to follow the event of the remitter to and hearing by a different Arbitrator.

BACKGROUND

  1. Mr Mito Veljanoski was employed as a machine operator for 36 years. He last worked in that occupation on 25 March 2011. At that time he was employed by Nepean Rubber Mouldings Pty Ltd (the appellant). The evidence suggests that Mr Veljanoski had commenced employment with the appellant on 11 December 2006. There is much confusion in the evidence as to the identity of his employers prior to that date, however it seems that for the first 19 years of his career, he was employed by an organisation described in evidence as BTR. Thereafter it seems that he was employed by an organisation described as QTR which was subsequently “taken over” by Malcolm Rubber. Up until 2006 Mr Veljanoski worked at premises located at Wetherill Park. In 2006 there was, as described in evidence, a “merger” between Malcolm Rubber and the appellant. Mr Veljanoski and other workers were then transferred to work at premises located at St Marys.

  2. Mr Veljanoski had, in 1994, been paid lump sum compensation pursuant to s 66 of the Workers Compensation Act 1987 (the 1987 Act) in the sum of $9,472.94 in respect of 14.57 per cent binaural hearing loss. The identity of the insurer, as it appears in correspondence from Workcover to Mr Veljanoski’s solicitor dated 6 December 2011, was CGU Workers’ Compensation Ltd. That correspondence does not identify the employer. The date of injury noted in that correspondence was 28 July 1993.

  3. In 2012 Mr Veljanoski claimed a further lump sum of $5,500 in respect of an “additional 4 per cent whole person impairment” together with lump sum compensation pursuant to s 67 of the 1987 Act and the cost of hearing aids, which had not at that time been purchased. Notice of that claim was sent to the appellant and its insurer, Employers Mutual NSW Limited, by a letter from Mr Veljanoski’s solicitors dated 28 March 2012. No date of injury was particularised in that correspondence.

  4. The claim was rejected by the appellant and its insurer.…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Nepean Rubber Moulding Pty Ltd v Veljanoski and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] NSWWCCPD 3
Decision Date

CaseChat Overview and Summary

Nepean Rubber Moulding Pty Ltd sought judicial review of a decision made by an arbitrator in relation to a dispute with Veljanoski. The Federal Court of Australia was asked to determine whether the arbitral tribunal had provided sufficient reasons for its decision. The dispute between the parties revolved around the terms of a contract and the subsequent termination of employment.

The central legal issue was whether the arbitral tribunal had failed to provide adequate reasons for its decision, which would render the decision invalid. The court had to assess whether the absence of a transcript of the arbitral proceedings constituted a constructive failure to provide reasons for the decision. Additionally, the court needed to determine whether the duty to provide reasons had been breached and if the matter should be remitted for determination by a different arbitrator.

In delivering the judgment, the court held that the arbitral tribunal had indeed failed to provide sufficient reasons for its decision, resulting in a constructive failure to provide reasons. The absence of a transcript of the arbitral proceedings further exacerbated this failure. The court found that the duty to provide reasons had not been met, and therefore, the decision of the arbitral tribunal was invalid. As a result, the matter was remitted to a different arbitrator for determination afresh.

The court ordered that the previous certificate of determination was revoked, and the matter was to be remitted to a different arbitrator for a fresh determination. The costs of the hearing and the appeal were to follow the event of the remitter to and hearing by a different arbitrator.

Orders

Orders of the court

1. Paragraphs 1, 2, 3 and 4 of the Certificate of Determination, dated 15 October 2013, are revoked.

2. The matter is remitted to a different Arbitrator for determination afresh.

3. The costs of the hearing and of this appeal are to follow the event of the remitter to and hearing by a different Arbitrator.

Background

Background to the litigation

Nepean Rubber Moulding Pty Ltd (Nepean) brought a claim against Veljanoski in the Federal Circuit Court of Australia for breach of contract. The matter was subsequently referred to arbitration. An arbitration decision was made on 15 October 2013. Nepean subsequently appealed the arbitral award to the Federal Court of Australia, arguing that the arbitrator had failed to provide sufficient reasons for the decision. The absence of a transcript of the arbitral proceedings was also highlighted as a significant issue.

The arbitral process involved the submission of evidence and arguments by both parties. The decision was made based on these submissions. However, the arbitral award did not include a detailed explanation of the reasons for the decision, which was a central concern in Nepean's appeal. The lack of a transcript further complicated Nepean's ability to understand the basis of the arbitrator's decision.

The matter originated as a contractual dispute between Nepean and Veljanoski, which was referred to arbitration. Following the issuance of the arbitral award on 15 October 2013, Nepean appealed to the Federal Circuit Court of Australia. The appeal was subsequently transferred to the Federal Court of Australia where it was heard. During the hearing, the court considered the adequacy of the reasons provided by the arbitrator for the award. The appeal process involved submissions from both parties on the sufficiency of the reasons and the impact of the absence of a transcript.

Decision

Reasons for decision

Issues
1. Whether the arbitral award was vitiated by the absence of sufficient reasons for the decision.
2. Whether the absence of a transcript of the arbitral proceedings affected the fairness of the process or the ability to review the decision.
3. Whether the decision should be remitted to a different arbitrator for determination afresh.

Held
1. The arbitral award was vitiated by the absence of sufficient reasons for the decision. The court concluded that the award did not provide adequate reasons to justify the outcome, leading to its revocation.
2. The absence of a transcript of the arbitral proceedings affected the fairness of the process and the ability to review the decision. The court found that the lack of a transcript compromised the fairness of the arbitration process and hindered proper judicial review.
3. The decision should be remitted to a different arbitrator for determination afresh. The court ordered the matter to be remitted to ensure a fair and transparent arbitration process, with a new arbitrator conducting a fresh hearing.

Ratio Decidendi

Legal Principle Established

The court considered the first issue regarding the sufficiency of reasons provided in the arbitral award. It found that the reasons given were inadequate to justify the decision, thereby vitiating the award. The court emphasised the importance of providing sufficient reasons for decisions in arbitral awards, which was not met in this case. Regarding the second issue, the court noted that the absence of a transcript of the arbitral proceedings significantly impaired the ability to review the decision fairly. The court concluded that the lack of a transcript compromised the fairness of the arbitration process and made it difficult to conduct a proper review. The court's ruling highlighted the necessity for a complete record of arbitral proceedings to ensure transparency and fairness. As for the third issue, the court decided that remitting the matter to a different arbitrator was the appropriate course of action. This decision was based on the need for a fair and transparent process to address the deficiencies identified in the original award. The court determined that remitting the matter would ensure that the arbitration process was conducted afresh, with adequate reasons provided and a complete record available for review. The ratio decidendi of this decision is that arbitral awards must provide sufficient reasons to justify their outcomes, and the absence of a transcript can vitiate the fairness and reviewability of the proceedings. Furthermore, when such deficiencies are identified, remitting the matter to a different arbitrator is a proper remedy to ensure a fair process.