National Cable Installations Pty Ltd

Case

[2022] FWCA 1838

7 JUNE 2022


[2022] FWCA 1838

FAIR WORK COMMISSION

DECISION

Fair Work Act 2009

s.185—Greenfields enterprise agreement

National Cable Installations Pty Ltd

(AG2022/1682)

National Cable Installation Pty Ltd – Rozelle Interchange and Western Harbour Tunnel Enabling Works, ETU Electrical System Fit Out Greenfield Agreement 2022 – 2024

Electrical contracting industry

COMMISSIONER CIRKOVIC

MELBOURNE, 7 JUNE 2022

Application for approval of the National Cable Installation Pty Ltd - Rozelle Interchange and Western Harbour Tunnel Enabling Works, ETU Electrical System Fit Out Greenfield Agreement 2021 – 2024.

  1. An application has been made for approval of an enterprise agreement known as the National Cable Installation Pty Ltd - Rozelle Interchange and Western Harbour Tunnel Enabling Works, ETU Electrical System Fit Out Greenfield Agreement 2021 - 2024 (the Agreement) pursuant to s.182(4) of the Fair Work Act 2009 (the Act) by National Cable Installations Pty Ltd. The agreement is a single enterprise agreement that is a greenfields agreement.

  1. The matter was allocated to my Chambers on 6 June 2022.

  1. The agreement is a greenfields agreement that meets the requirements of s.172(2)(b) of the Act.

  1. In accordance with s.187(5)(a) of the Act, I am satisfied that the Communications Electrical Electronic Energy Information Postal Plumbing and Allied Services Union of Australia (CEPU) is entitled to represent the industrial interests of a majority of employees who will be covered by the Agreement in relation to the work that is to be performed under it.

  1. Pursuant to s.53(2)(b) of the Act I note that the Agreement was made with the CEPU and that the Agreement covers this organisation.

  1. I am satisfied that each of the requirements of ss.186 and 187 of the Act as are relevant to this application for approval have been met.

  1. I am satisfied that it is in the public interest to approve the Agreement.

  1. The Agreement is approved and, in accordance with s.54 of the Act, will operate from 7 days from the date of approval of the Agreement. The nominal expiry date is 31 December 2023.


COMMISSIONER

Printed by authority of the Commonwealth Government Printer

<AE516172  PR742332>