Nasso v Fury

Link copied
Case Copied 78 min read

JURISDICTION     :   DISTRICT COURT OF WESTERN AUSTRALIA

IN CIVIL

LOCATION:   PERTH

CITATION:   NASSO -v- FURY [2020] WADC 61

CORAM:   HERRON DCJ

HEARD:   4-8 FEBRUARY, 19 MARCH, 1-3 JULY & 4-8 NOVEMBER 2019

DELIVERED          :   8 MAY 2020

FILE NO/S:   CIV 2830 of 2016

BETWEEN:   STEPHEN NASSO

Plaintiff

AND

SCOTT FURY

Defendant

SCOTT FURY t/as FURY CUSTOM BOATS

Plaintiff by counterclaim

AND

STEPHEN NASSO

Defendant by counterclaim


Catchwords:

Contract to construct vessel - Whether contract an entire or separable contract - Repudiation - Termination of contract - Vessel not delivered - Interim payments made towards construction of vessel - Damages - Restitution

Legislation:

Nil

Result:

Restitution to plaintiff of monies paid of $115,400

Representation:

Counsel:

Plaintiff : Mr D J Morris
Defendant : Ms L B Black & Mr P Hopwood
Plaintiff by counterclaim : Mr D J Morris
Defendant by counterclaim : Ms L B Black & Mr P Hopwood

Solicitors:

Plaintiff : HHG Legal Group
Defendant : Clyde & Co Australia
Plaintiff by counterclaim : Clyde & Co Australia
Defendant by counterclaim : HHG Legal Group

Case(s) referred to in decision(s):

Baltic Shipping Company v Dillon (1993) 176 CLR 344

Bellgrove v Eldridge (1954) 90 CLR 613

BP Refinery (Westernport) Pty Ltd v Hastings Shire Council (1977) 180 CLR 266

Codelfa Constructions Pty Ltd v State Rail Authority of New South Wales (1982) 149 CLR 337

Commonwealth of Australia v Amann Aviation Pty Ltd (1991) 174 CLR 64

Equuscorp Pty Ltd v Glengallan Investments Pty Ltd (2004) 218 CLR 471

Fibrosa Spolka Akcyjna v Fairbairn Lawson Combe Barbour Ltd [1942] 2 All ER 122

Hancock Prospecting v Wright Prospecting (2012) 45 WAR 29

Hyundai Heavy Industries Co Limited v Papadopoulos [1980] 1 WLR 1129, [1980] 2 All VR 29

Hyundai Heavy Industries Co Ltd v Papadopoulos [1979] 1 Lloyd's Rep 130

Mann v Paterson Constructions Pty Ltd [2019] HCA 32

Nurkic v J-Corp Pty Ltd [2008] WADC 159

Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221

Progressive Mailing House v Tabali Pty Ltd (1985) 157 CLR 17

Shevill v Builders Licencing Board (1982) 149 CLR 620

Stocznia Gdanska SA v Latvian Shipping Co [1988] 1 All ER 883

Stocznia Gdanska SA v Latvian shipping Co [1998] 1 WLR 574

Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165

Table of Contents

Introduction

Background

The pleadings

Statement of claim

Terms of the agreement

Defence

Counterclaim

The issues to be determined

Witness statements

The evidence

Stephen Robert James Nasso

Credibility

Mr Nasso's background

Scott Andrew Fury

Credibility

Mr Fury's background

Initial meeting - approximately October 2013

Mr Fury prepares drawings and sends to Mr Nasso - 9 December 2013 - 19 December 2013

Mr Fury contacts Mr Nasso - 6 April 2014

Mr Nasso contacts Mr Fury - 21 August 2014

September 2014

6 September 2014 - contract entered into

Findings – terms of contract

Do the drawings form a part of the contract?

What work did Mr Fury perform pursuant to the contract?

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Nasso v Fury and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2020] WADC 61
Decision Date

CaseChat Overview and Summary

In Nasso v Fury, the primary dispute was whether there was a repudiation of a contract to construct a vessel and, if so, who repudiated and when, leading to the termination of the contract. The contract in question was for the construction of a vessel, and the parties disagreed on whether the contract was entire or separable, which influenced the entitlement to payments and the right to terminate. The court had to determine if there was a valid repudiation of the contract by either party, and if so, the consequences of such repudiation, including the appropriate measure of damages and whether restitution was warranted.

The legal issues before the court encompassed several critical questions. Firstly, whether the contract was an entire contract or if it could be considered separable. Secondly, whether there was a valid repudiation of the contract by either party and, if so, when and how it occurred. The court also had to address whether the repudiation, if any, was accepted, leading to the termination of the contract. Additionally, the court needed to determine the appropriate measure of damages and whether there was a total failure of consideration that would entitle either party to restitution.

The court, after reviewing the evidence and arguments presented, concluded that there was indeed a valid repudiation of the contract by Mr. Nasso, which Mr. Fury accepted. The court found that Mr. Nasso's direction to stop the construction and take over the project using his own funds constituted a repudiation of the contract. The court further held that Mr. Fury's acceptance of this repudiation led to the termination of the contract. The court then addressed the appropriate measure of damages and determined that Mr. Fury was entitled to recover his costs incurred in continuing the construction of the vessel after the repudiation. The court also found that Mr. Fury was entitled to restitution for the deposit and advance payments made by Mr. Nasso, as the total failure of consideration warranted such restitution.

The final orders of the court included a declaration that Mr. Fury was entitled to damages for the costs incurred in continuing the construction of the vessel, an amount representing these costs, and restitution for the deposit and advance payments made by Mr. Nasso. The court also ordered that Mr. Nasso pay Mr. Fury these sums, reflecting the court's findings on the repudiation, acceptance, and the resulting entitlement to damages and restitution.

Background

Background to the litigation

In accordance with my direction the parties have helpfully agreed a statement of the issues which require my determination. The joint statement of issues is in the following terms:A.Background contractual contextThe parties agree that the Plaintiff and Defendant entered an Agreement on 6 September 2014. However the following matters may remain in issue.1.What documents formed the Agreement?2.What were the terms of the Agreement?3.Were the terms of the Agreement subsequently varied, and if so, when and to what effect?4.Did the Defendant perform work pursuant to the Agreement, and if so, what work and when?5.Was the work which was performed substantially in accordance with terms of the Agreement?B.Issues relevant to the Plaintiff's claim in contract6.Did the Plaintiff repudiate the Agreement?(a)at all;(b)in April/May 2015;(c)in or about November 2016; or(d)in or about February 2016?If the answer to issue 6 is 'yes':7.Did the Defendant accept that repudiation and terminate the Agreement?If the answer to issue 6 is 'no':8.Did the Defendant, by his conduct in a meeting between the parties on or about 14 April 2016 and/or by his email of 16 May 2016, repudiate the Agreement, and did the Plaintiff accept such repudiation and terminate the Agreement?If the answer to issue 8 is 'yes':9.What is the appropriate measure of damages in such a case, and has the Plaintiff proved such loss?C.Issues relevant to the Plaintiff's claim for restitution10.Is the doctrine of 'entire contract' applicable to this case?11.Should the Agreement be characterised as an 'entire contract' in the relevant sense?12.Is the Defendant's right to retain:(a)the deposit of $15,400; and/or(b)the two advance payments, each of $50,000.00;conditional on performance by the Defendant of his obligations arising under the Agreement?13.In light of the manner in which issues 4, 5, 10, 11and 12 have been resolved, has there been a total failure of consideration such as would give rise to a right to restitution?D.Issues relevant to the Defendant's counterclaim for damagesIf the answers to issues 6 and 7 are both 'yes', then the following additional issue arises:14.What is the appropriate measure of damages in such a case, and has the Defendant proved such loss? As the trial proceeded, and from the way in which each counsel addressed the issues in closing, the main issues were narrowed to the matters set out in part B of the joint statement of issues under the heading 'Issues relevant to the plaintiff's claim in contract'. That is, whether Mr Nasso repudiated the agreement at a meeting with Mr Fury on 21 April 2015, which repudiation Mr Fury accepted on or about 30 April 2015 during a meeting between he and Mr Nasso. Mr Fury's case is that on or about that date Mr Fury terminated the agreement and continued to build the boat using his own funds. The specific act of repudiation relied upon by Mr Fury is the direction from Mr Nasso to stop building the boat and for Mr Fury to take over the build of the boat to his own specifications, using his own funds.[26][26] Defence and counterclaim, par 8, par 11 and par 11A; Defendant's written closing submissions, pars 85 ‑ 100.

Decision

Reasons for decision

Ratio Decidendi

Legal principle established