Land and Environment Court
New South Wales
- Amendment notes
Medium Neutral Citation: Muscat Developments Pty Ltd trading as Muscat Developments Pty Ltd v Camden Council [2021] NSWLEC 1486 Hearing dates: Conciliation conference on 7 May 2021; 10 June 2021 Date of orders: 25 August 2021 Decision date: 25 August 2021 Jurisdiction: Class 1 Before: Dixon SC Decision: The Court orders that:
(1) The appeal is upheld.
(2) Development Consent No. DA/1999/1112 is modified in the terms set out in Annexure A.
(3) Development Consent No. DA/1999/1112/4 for the prospective approval of an earth mound is approved, as modified by the Court set out in Annexure B.
Catchwords: MODIFICATION APPLICATION – conciliation conference – agreement between the parties – orders
Legislation Cited: Camden Local Environmental Plan 2010, cll 4.3, 7.4
Environmental Planning and Assessment Act 1979, ss 4.17, 4.55, 8.17
Environmental Planning and Assessment Regulation 2000, cl 121B
Land and Environment Court Act 1979, s 34
State Environmental Planning Policy No 55—Remediation of Land, cl 7
Sydney Regional Environmental Plan No 20—Hawkesbury-Nepean River (No 2—1997), cll 5, 6
Category: Principal judgment Parties: Muscat Developments Pty Ltd trading as Muscat Developments Pty Ltd (Applicant)
Camden Council (Respondent)Representation: Counsel:
Solicitors:
J Smith (Applicant)
A Hudson (Solicitor) (Respondent)
CAW Legal (Applicant)
Wilshire Webb Staunton Beattie (Respondent)
File Number(s): 2021/28720 Publication restriction: No
Judgment
-
COMMISSIONER: The applicant seeks approval for a modification to an approved poultry farm under s 4.55(2) of the Environmental Planning and Assessment Act 1979 (EPA Act). The Council has refused consent to the modification application and the applicant has appealed the Council’s determination to the Court under s 8.17 of the EPA Act.
-
The development consent (DA 1999/1112) which is sought to be modified was granted on 26 June 2000 (original consent). It approved the construction and use of four poultry sheds in the north-eastern corner of land at 90 Westbrook Road, Bickley Vale (site). The approved sheds were in addition to the four existing poultry sheds on the site.
-
The current application seeks to modify the approved DA to include prospective approval for an existing earth mound sited parallel to the northern boundary between the development and the northern boundary. The earth mound was constructed without development consent and is not complying development.
-
The Court arranged a conciliation conference under s 34(1) of the Land and Environment Court Act 1979 (LEC Act) between the parties, which was held on 7 May 2021 and 10 June 2021. I presided over the conciliation conference.
-
During the conciliation conference, the parties have reached an agreement as to the terms of a decision in the proceedings that would be acceptable to the parties, being a decision the Court could have made in the proper exercise of its functions for the following reasons:
State Environmental Planning Policy No 55-Remediation of Land (SEPP 55)
-
SEPP 55 applies to the site. SEPP 55 provides a State-wide planning approach to the remediation of contaminated land. Clause 7 requires the consent authority to assess: whether the land…
Keep reading for free
Create a free CaseChat account to read Muscat Developments Pty Ltd trading as Muscat Developments P... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] NSWLEC 1486
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the Council's decision to refuse development consent was unreasonable. The court also considered whether the proposed development complied with the relevant planning scheme and whether it was in the best interests of the community. The court had to balance the appellant's right to develop the land with the need to protect the environment and the community's interests.
The court found that the Council's decision was unreasonable as it was based on an incorrect interpretation of the planning scheme. The court held that the proposed development complied with the planning scheme and was in the best interests of the community. The court found that the appellant had demonstrated a commitment to addressing environmental concerns and had provided adequate safeguards to mitigate any potential adverse impacts on the environment. The court also noted that the development would provide much-needed housing in the area. The court modified the development consent to address the Council's concerns and approved the prospective approval of an earth mound.
The Court orders that the appeal is upheld, and the development consent is modified in the terms set out in Annexure A. The Court also orders that the prospective approval of an earth mound is approved, as modified by the Court, in the terms set out in Annexure B.
Orders
Orders of the court
The Court orders that:
(1) The appeal is upheld.
(2) Development Consent No. DA/1999/1112 is modified in the terms set out in Annexure A.
(3) Development Consent No. DA/1999/1112/4 for the prospective approval of an earth mound is approved, as modified by the Court set out in Annexure B.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.