Murray & Roberts Australia Pty Ltd v G B Lifestyles Pty Ltd [No 2]

Link copied
Case Copied 12 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

IN CIVIL

CITATION:   MURRAY & ROBERTS AUSTRALIA PTY LTD -v- G B LIFESTYLES PTY LTD [No 2] [2014] WASC 9

CORAM:   MARTIN CJ

HEARD:   12 NOVEMBER 2013 & ON THE PAPERS

DELIVERED          :   17 JANUARY 2014

FILE NO/S:   ARB 2 of 2013

BETWEEN:   MURRAY & ROBERTS AUSTRALIA PTY LTD

Applicant

AND

G B LIFESTYLES PTY LTD
Respondent

Catchwords:

Commercial arbitration - Appeal from decision of arbitrator - Denial of natural justice or procedural fairness - Decision of arbitrator based on construction of contract neither party raised or argued - Issues to be remitted where not doing so would usurp arbitrator's function

Legislation:

Commercial Arbitration Act 1985 (WA), s 38(5)
Commercial Arbitration Act 2012 (WA), s 43

Result:

Appeal allowed
Interim award quashed
Matter remitted to arbitrator
Application to vary order for costs dismissed

Category:    B

Representation:

Counsel:

Applicant:     Mr P J Ward

Respondent:     Mr P G Clifford

Solicitors:

Applicant:     Ashurst Australia

Respondent:     Alan Rumsley

Case(s) referred to in judgment(s):

Murray & Roberts Australia Pty Ltd v G B Lifestyles Pty Ltd [2013] WASC 345

Straits Exploration (Australia) Pty Ltd v Murchison United NL [2005] WASCA 241; (2005) 31 WAR 187

MARTIN CJ: 

Summary

  1. For reasons which I published on 16 September 2013, see Murray & Roberts Australia Pty Ltd v G B Lifestyles Pty Ltd [2013] WASC 345, I ordered that the appellant, Murray & Roberts Australia Pty Ltd, be granted leave to appeal from an interim award issued by an arbitrator pursuant to s 38(5) of the Commercial Arbitration Act 1985 (WA) (the Act) on certain grounds, and that the question of whether leave be granted in relation to another ground be adjourned to the hearing of the appeal. I also ordered that the respondent pay the appellant's costs of the application for leave to appeal, to be taxed if not agreed, and that the parties exchange written submissions in relation to the appeal which was, with their consent, to be determined on the papers. Those submissions have now been exchanged, and the matter was mentioned briefly before me in the course of a hearing of other proceedings between the same parties.

  2. For the reasons which follow I have concluded that:

    (a)the appeal should be allowed and the interim award issued by the arbitrator quashed;

    (b)leave to appeal in respect of ground 3 of the grounds of appeal should be refused;

    (c)the matter should be remitted to the arbitrator to receive further evidence and any further submissions of the parties; and

    (d)the respondent's application to vary the order for costs made in respect of the application for leave to appeal should be dismissed.

The application for leave to appeal

  1. The arbitration the subject of these proceedings was commenced prior to the commencement of the operation of the Commercial Arbitration Act 2012 (WA), with the consequence that the legal regime governing the arbitration is provided by the Act (see s 43 of the 2012 Act). Consistently with established procedure relating…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Murray & Roberts Australia Pty Ltd v G B Lifestyles Pty Ltd... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] WASC 9
Decision Date

CaseChat Overview and Summary

In the matter of Murray & Roberts Australia Pty Ltd v G B Lifestyles Pty Ltd, the dispute revolves around the interpretation of a contract and the procedural fairness of the arbitration process. The parties had agreed to resolve their disputes through arbitration, and the case was heard by an arbitrator who made a decision on the construction of the contract. Murray & Roberts Australia Pty Ltd, the appellant, appealed the decision on the grounds that the arbitrator had denied natural justice by deciding the case on a basis that neither party had raised or argued. The court was required to determine whether the arbitrator's decision was indeed procedurally unfair and, if so, whether the court should remit the matter to the arbitrator or decide the issue itself.

The court found that the contention that the arbitrator had denied procedural fairness was strongly arguable, as the arbitrator had based the decision on a construction of the contract that neither party had put forward. However, the court also noted that the appellant contended that instead of remitting the matter to the arbitrator, the court should decide the issue itself by determining whether the contract conferred an option to put the blast unit to the respondent, which option was never exercised. The court rejected this contention, stating that it would usurp the functions of the arbitrator to determine the issue itself. The court held that there were arguments in support of the appellant's contention, but there were also considerations which pointed against it. Therefore, it was appropriate to remit the matter to the arbitrator for determination.

The court's reasoning was based on the principle that the parties had agreed to resolve their disputes by arbitration, and the court should respect and give effect to such agreements. The court held that it was not appropriate for the court to usurp the functions of the arbitrator by deciding the issue itself, as this would undermine the parties' agreement to resolve their disputes by arbitration. The court found that the issues should be remitted to the arbitrator for determination, as it was consistent with the parties' agreement to resolve their disputes by arbitration.

The final orders of the court were to remit the matter to the arbitrator for determination of the issues in relation to the construction of the contract and the procedural fairness of the arbitration process. The court held that it was not appropriate for the court to decide the issue itself, as this would usurp the functions of the arbitrator and undermine the parties' agreement to resolve their disputes by arbitration. The court's decision reinforces the principle that courts respect and give effect to parties' agreements to resolve their disputes by arbitration, and that the court should approach its supervisory powers in that light.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established

It is of the utmost significance to the resolution of the competing contentions now advanced by the parties that, by their contract, they agreed that their dispute should be resolved by arbitration, and not by litigation. It is now well established that courts respect and give effect to such agreements, and approach both the exercise of the court's inherent jurisdiction and the supervisory powers conferred upon the court by the Act in that light (see for example Straits Exploration (Australia) Pty Ltd v Murchison United NL [2005] WASCA 241; (2005) 31 WAR 187). In support of its application for leave to appeal the appellant contended that the arbitrator had denied the parties procedural fairness by deciding the case on a basis which neither party had put. I concluded that this contention was strongly arguable, and neither party now contends that I should not find that the arbitrator erred in this way. However, the appellant now contends that rather than remit the matter to the arbitrator for the purpose of receiving further evidence and submissions in relation to those issues, I should instead resolve them by deciding that the contract, properly construed, conferred upon it an option to put the blast unit to the respondent, which option was never exercised. That proposition was rejected by the arbitrator for reasons which he enunciated in his interim award, in favour of his conclusion that the contract gave rise to a call option capable of exercise by the respondent. Having found that the parties were denied procedural fairness in relation to that conclusion, in my view it would inappropriately usurp the functions which the parties agreed to confer upon the arbitrator for the court itself to determine whether, on its proper construction, the contract gave rise to a put option capable of exercise by the appellant or a call option capable of exercise by the respondent. I might have taken a different view if I was satisfied, on the basis of the materials before the court and the argument which had been presented to the court, that there was only one way in which the contract between the parties could be construed, and that a construction of the contract in any way other than that for which the appellant contends would be a manifest error of law on the part of an arbitrator. However, that is not the view which I take. While there are arguments in support of the construction for which the appellant contends, there are considerations which point against that construction, as the arbitrator found in his interim award. On the other hand, he may well have been influenced in that conclusion by his view that the contract, properly construed, gave rise to a call option capable of exercise by the respondent, which conclusion should, for the reasons I have given, be set aside by reason of denial of procedural fairness. In these circumstances it is consistent with the agreement of the parties to resolve their disputes by arbitration that these issues be remitted to the arbitrator for determination. This is essentially the conclusion which I foreshadowed in my earlier reasons at [86].