Mulder v Queensland Building and Construction Commission

Link copied
Case Copied 43 min read

QUEENSLAND CIVIL AND


ADMINISTRATIVE TRIBUNAL

CITATION:

Mulder v Queensland Building and Construction Commission [2019] QCAT 395

PARTIES:

HEINRICH GEORGE LUDIWICK MULDER AND AMANDA MULDER
(applicant)

v

QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION

And

DR FAMILY PTY LTD TRADING AS CONSOLIDATED BUILDING CONCEPTS PTY LTD

 (respondents)

APPLICATION NO/S:

GAR 119-18; GAR 145-18

MATTER TYPE:

General administrative review matters

DELIVERED ON:

16 December 2019

HEARING DATE:

26, 27 and 28 August 2019

HEARD AT:

Brisbane

DECISION OF:

Member King-Scott

ORDERS:

The Tribunal orders:

1.   The decision of the Queensland Building and Construction Commission made on 9 March 2018 not to direct rectification of the building work in terms of the Applicants’ complaint is confirmed;

2.   The Application for Review of a Decision filed 10 April 2018 in GAR119-18 is dismissed;

3.   The decision of the Queensland Building and Construction Commission made on 27 March 2018 to disallow the Applicants’ claim made 19 July 2017 under the Queensland Home Warranty Scheme is confirmed;

4.   The Application for Review of a Decision filed 1 May 2017 in GAR145-18 is dismissed;

5.   The Respondents each are to file and serve submissions in relation to costs, if any, by close of business 5 February 2020.

6.   The Applicants are to file and serve their response in relation to costs, if any, by close of business 19 February 2020.

CATCHWORDS:

ADMINISTRATIVE LAW –ADMINISTRATIVE TRIBUNALS – QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL – General Administrative Review – application by building owner to review a decision by the Queensland Building and Construction Commission to reject a claims by building owner for a direction to rectify and for payment under Queensland Home Warranty Scheme – whether the building owner repudiated the building contract – whether the builder validly terminated a building contract – where the building owner also purported to terminate the contract – the rights of the building contractor and the building owner under contract and at law – where the tribunal reviews the decision of the QBCC’s refusal to order Direction to Rectify and refusal of claim under the statutory scheme in favour of the building owner as builder had validly terminated the contract

Domestic Building Contracts Act 2000 (Qld) s 45
Queensland Building and Construction Commission Act 1991 (Qld) s 72
Queensland Building Construction Commission Regulation 2018 (Qld) s67X (4)

Freedom Homes Pty Ltdv Botros & Anor (2000) 2 Qd R 377
Carr v J A Berriman Pty Ltd (1953) 89 CLR 327

Carswell v Collard (1893) 9 App Cas 434
Centreplex Pty Ltd v Noah’s Rosehill Waters Pty Ltd [2019] WASC 252

Forslind v. Bechely-Crundall 1922 S.C.(HL) 173
Koompahtoo Council v Sanpine Pty Ltd (2007) 233 CLR 115
Laurinda Pty Ltd v Capalaba Shopping Centre Pty Ltd (1989) 166 CLR 623
Minion v. Graystone Pty Ltd (1990) 1 Qd R 157
Ross T. Smyth & Co. Ltd. v. T. D. Bailey, Son & Co. [19401 3 All E.R. 60

Shepherd v Felt & Textiles of Australia Ltd (1931) 45 CLR 359
Sunbird Plaza Pty Ltd v Maloney

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Mulder v Queensland Building and Construction Commission and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] QCAT 395
Decision Date

CaseChat Overview and Summary

Mulder v Queensland Building and Construction Commission concerned a dispute between a building owner and the Queensland Building and Construction Commission (QBCC). The building owner sought a direction to rectify and payment under the Queensland Home Warranty Scheme, but the QBCC rejected these claims. The central issues in this case were whether the building owner had repudiated the building contract and whether the builder had validly terminated the contract. The case required the court to examine the rights of the building contractor and the building owner under contract and at law.

The court examined the circumstances surrounding the termination of the building contract. The builder had validly terminated the contract, and the building owner had also purported to terminate it. The court needed to determine whether the QBCC was correct in its decision to reject the building owner's claims for rectification and payment. The court found that the building owner had repudiated the building contract, and the builder had validly terminated the contract. The court concluded that the QBCC was correct in its decision to reject the building owner's claims, as the building work was not considered defective.

The Tribunal confirmed the decisions of the QBCC. The decision not to direct rectification of the building work and the disallowance of the building owner's claim under the Queensland Home Warranty Scheme were upheld. The Tribunal dismissed the building owner's applications for review of these decisions. The parties were directed to file and serve submissions on costs by specified dates. This decision underscores the importance of valid contract termination and the QBCC's role in reviewing claims under the Queensland Home Warranty Scheme.

Orders

Orders of the court

The Tribunal orders:

1. The decision of the Queensland Building and Construction Commission made on 9 March 2018 not to direct rectification of the building work in terms of the Applicants’ complaint is confirmed;

2. The Application for Review of a Decision filed 10 April 2018 in GAR119-18 is dismissed;

3. The decision of the Queensland Building and Construction Commission made on 27 March 2018 to disallow the Applicants’ claim made 19 July 2017 under the Queensland Home Warranty Scheme is confirmed;

4. The Application for Review of a Decision filed 1 May 2017 in GAR145-18 is dismissed;

5. The Respondents each are to file and serve submissions in relation to costs, if any, by close of business 5 February 2020.

6. The Applicants are to file and serve their response in relation to costs, if any, by close of business 19 February 2020.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

It is important to bear in mind that these proceedings are not a domestic building dispute wherein relief for breach of contract is sought. Rather, the proceedings are a review of the internal review decision of the Commission, addressing the matters referred to above. It is not, although at times, it threatened to be, a forum for Mr Mulder to ventilate his dispute with DRF, Mr Wegner the Engineer and Mr Eaves the Certifier.The Rectification decision Section 72 of the QBCC Act provides that if the Commission is of the opinion that building work is defective or incomplete it may direct a builder to rectify the defective work or compete the incomplete work. The Section provides further:(3) In deciding whether to give the direction, the commission may take into consideration all the circumstances it considers are reasonably relevant and, in particular, is not limited to a consideration of the terms of the contract for carrying out the building work (including the terms of any warranties included in the contract.…(5) The commission is not required to give the direction if the commission is satisfied that, in the circumstances, it would be unfair to the person to give the direction. The works ceased on about 2 May 2017. The Mulders submitted a complaint to the Commission on 12 September 2017 alleging defective work by DRF further particularised in an email dated 24 September 2017. I am satisfied that the complaint related to ‘building work’ and that DRF was responsible for the building work. The Commission inspected the work on 26 October 2017. That inspection took place 6 months after DRF left the site, at a time the inspection site had been left open after the security fencing had been removed. Form work was also removed. DRF denies removing anything from the site.[1][1]Transcript 1-124 45 On 31 October 2017 the Commission decided not to direct rectification of the building work. That was on the basis that the work was not considered defective. The Mulders sought an internal review of the decision. It was a lengthy document and raised a number of irrelevant issues. Mr Steven Noble, Senior Technical Officer of the Commission conducted a desk top review, that is, a review based on the reports of the building inspector and other specialist reports, but it did not involve an inspection of the site. Those complaints made by the Mulders and considered by the Commission were:Item 1 - Fill on site Mr Mulder, initially, complained that the fill looked like it contained a lot of clay. On inspection the fill was no longer on the site which Mr Mulder accepted. Mr Noble’s findings were that the geotechnical investigation undertaken by Dirts (Qld) Pty Ltd dated 3 November 2016 identified the land with rolled non-compacted fill of up to 400mm is acceptable and in accordance with AS2870:2011 sec 2.5.3. He alleges that the old fill was removed, and new fill was carted in and placed as a platform. It was originally complained that there was no proof of whether the current fill affected the site classification negatively.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.