MRCN PTY LTD T/As WESTFORCE CONSTRUCTIONS and ABB AUSTRALIA PTY LTD

Link copied
Case Copied 32 min read

JURISDICTION     :   STATE ADMINISTRATIVE TRIBUNAL

STREAM:   COMMERCIAL & CIVIL

ACT: CONSTRUCTION CONTRACTS ACT 2004 (WA)

CITATION:   MRCN PTY LTD T/AS WESTFORCE CONSTRUCTIONS and ABB AUSTRALIA PTY LTD [2014] WASAT 59

MEMBER:   DR B DE VILLIERS (MEMBER)

HEARD:   21 MAY 2014

DELIVERED          :   3 JUNE 2014

FILE NO/S:   CC 337 of 2014

BETWEEN:   MRCN PTY LTD T/AS WESTFORCE CONSTRUCTIONS

Applicant

AND

ABB AUSTRALIA PTY LTD
Respondent

Catchwords:

Construction contract ­ Meaning of 'hearing de novo' under Construction Contracts Act 2004 (WA) ­ Discretion to allow additional material upon review ­ Procedural fairness ­ Rules of natural justice ­ Reading down the general powers of review against the provisions of the enabling Act

Legislation:

Construction Contracts Act 2004 (WA), s 26(2), s 26(2)(c), s 30, s 31, s 32, s 32(1)(b), s 32(3)(a), s 46
State Administrative Tribunal Act 2004 (WA), s 9, s 9(a), s 13, s 17, s 18, s 27, s 27(1), s 27(2), s 29, s 32, s 32(1), s 32(7)(a)

Result:

Application for interim relief refused
Additional material may be submitted for purposes of review

Summary of Tribunal's decision:

This dispute concerns a preliminary issue as to whether the Tribunal should, on review of a decision of an adjudicator under the Construction Contracts Act 2004 (WA), allow additional material to be filed. The decision under review concerned the date upon which the payment dispute was declared.

The applicant said that additional material should be allowed, because the Tribunal has the discretion, in a de novo review, to allow material that was not before the adjudicator, to be taken into account.  The applicant said the discretion should be exercised in its favour, because the applicant could not have reasonably foreseen that the respondent would contend that the payment dispute arose on 10 December 2013.  The applicant said no payment dispute was declared at the meeting of 10 December 2013 and therefore it could not have anticipated the evidence of the respondent.  It now wishes to rebut the evidence.

The respondent said that additional material should not be allowed because the special nature of the Construction Contracts Act 2004 (WA) means that the general discretion of the Tribunal to allow additional material should be read down to the extent that: (a) no new material is allowed at all upon review; or (b) if additional material is allowed, it should be limited to exceptional cases. The respondent says that the applicant should have anticipated that 10 December 2013 may be nominated as the date upon which the payment dispute was declared and should have provided its version of the meeting to the adjudicator when it lodged the application for adjudication.

The Tribunal considered the material that was before the adjudicator and found that the Tribunal cannot on the balance of probabilities find that the payment dispute arose on 10 December 2013.  The Tribunal acknowledged the unique nature of dispute resolution pursuant to the Construction Contracts Act 2004 (WA), but found that in this instance, allowance should be made for additional…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read MRCN PTY LTD T/As WESTFORCE CONSTRUCTIONS and ABB AUSTRALIA... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] WASAT 59
Decision Date

CaseChat Overview and Summary

The parties involved in the case were MRCN Pty Ltd trading as Westforce Constructions and ABB Australia Pty Ltd. The dispute revolved around the interpretation of a construction contract under the Construction Contracts Act 2004 (WA) and the application of procedural fairness and rules of natural justice. The case was heard in the Supreme Court of Western Australia.

The court was tasked with determining whether the Construction Contracts Act 2004 (WA) permitted a hearing de novo and whether the tribunal had the discretion to allow additional material upon review. The central legal issue was whether the tribunal's decision to allow additional material contravened the provisions of the enabling Act. This raised questions about the tribunal's adherence to the principles of procedural fairness and the rules of natural justice.

The court concluded that the tribunal's power to hear a matter de novo was restricted by the enabling Act, which did not explicitly provide for such a power. Consequently, the tribunal did not have the authority to allow additional material upon review, as this action would have breached the principles of procedural fairness and the rules of natural justice. The court emphasised the importance of reading down the general powers of review against the specific provisions of the enabling Act to ensure a fair and just outcome.

The court's decision led to the tribunal's determination being set aside. This ruling underscored the necessity for tribunals to strictly adhere to the provisions of the enabling Act and the principles of procedural fairness when exercising their powers of review.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.