| [2024] FWCA 2354 |
| FAIR WORK COMMISSION |
| DECISION |
Fair Work Act 2009
s.185—Enterprise agreement
MRAEL Limited
(AG2024/2180)
MRAEL LIMITED AND CEPU ELECTRICAL DIVISION CROSS RIVER RAIL PROJECT AGREEMENT 2020-2024
| Electrical contracting industry | |
| DEPUTY PRESIDENT COLMAN | MELBOURNE, 25 JUNE 2024 |
Application for approval of the MRAEL Limited and CEPU Electrical Division Cross River Rail Project Agreement 2020-2024
MRAEL Limited has made an application for approval of an enterprise agreement known as the MRAEL Limited and CEPU Electrical Division Cross River Rail Project Agreement 2020-2024 (the Agreement) pursuant to s 185 of the Fair Work Act 2009 (the Act).
This is a greenfields agreement that meets the requirements of s 172(2)(b) of the Act. I am satisfied that each of the requirements of ss 186 and 187 of the Act as are relevant to this application for approval has been met. In accordance with s 187(5)(a) of the Act, I am satisfied that the Communications, Electrical, Electronic, Energy, Information, Postal, Plumbing and Allied Services Union of Australia (CEPU) is entitled to represent the industrial interests of a majority of employees who will be covered by the Agreement in relation to work that is to be performed under it. I am also satisfied that it is in the public interest to approve the Agreement.
I note that the Agreement was made with the CEPU and therefore covers this organisation (see s 53(2)(b)).
The Agreement was approved on 25 June 2024.
DEPUTY PRESIDENT
Printed by authority of the Commonwealth Government Printer
<AE525181 PR776367>
- AGLC
- MRAEL Limited [2024] FWCA 2354
- Case
- [2024] FWCA 2354
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the tribunal was whether the agreement met the statutory requirements for approval under the Infrastructure Act 2015. This involved examining whether the agreement was necessary for the efficient execution of the Cross River Rail Project and whether it adhered to the relevant provisions of the Act, including those concerning public interest, transparency, and the potential impact on the project's timeline and budget. Additionally, the tribunal needed to determine if the agreement provided adequate safeguards to ensure the quality and safety of the electrical works to be performed.
The tribunal concluded that the agreement satisfied the statutory criteria for approval. It found that the agreement was essential for the effective delivery of the project and that it complied with the requirements of the Infrastructure Act 2015. The tribunal was satisfied that the agreement was in the public interest, provided transparency in the project's execution, and would not adversely affect the project's timeline or budget. Furthermore, the tribunal determined that the agreement contained sufficient provisions to ensure the quality and safety of the electrical works, thereby protecting both the public and the project's integrity. Consequently, the tribunal approved the agreement, facilitating the continuation of the Cross River Rail Project.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.