Reported Decision: 139LGERA 28
[2006] NSWCA 159
Land and Environment Court
of New South Wales
CITATION: Mosca v Roads and Traffic Authority of NSW [2004] NSWLEC 676 PARTIES: APPLICANT:
RESPONDENT:
Mosca
Roads and Traffic Authority of NSWFILE NUMBER(S): 30121 of 2003 CORAM: Bignold J KEY ISSUES: Compensation :- compulsory acquisition of land. Part of Applicant's land acquired for Western Sydney Orbital Road-Land included in Urban Release Programme-effect of public work on land value-disregarding decreases in value caused by blight. LEGISLATION CITED: Land Acquisition (Just Terms Compensation) Act 1991 CASES CITED: Blacktown City Council v Lasseter (CA 40147/94 5 December 1996);
Constantino v Roads and Traffic Authority (2004) NSWLEC 517;
Griffith City Council v Polegato (1990) 71 LGRA 208;
Housing Commission of NSW v San Sebastian Pty Ltd (1978) 140 CLR 196);
Stocks and Parkes Investments v The Minister (1971) 25 LGRA 243;
Woollams v The Minister (1957) 2 LGRA 338;
Yates-Property Corp Pty Ltd v Darling Harbour Authority (1991) 73LGRA 47)DATES OF HEARING: 03-06/11/03, 16-24/02/04, 08/06/04, 17/06/04, 22/06/04 DATE OF JUDGMENT: 12/03/2004 LEGAL REPRESENTATIVES: RESPONDENT:
APPLICANT:
Mr J Webster, SC with Mr J Whyte, Barrister
SOLICITORS
Thorntons
Mr J Maston, Barrister
SOLICITORS
Corrs Chambers Westgarth
JUDGMENT:
THE LAND AND
ENVIRONMENT COURT
OF NEW SOUTH WALES
BIGNOLD J
3 December 2004
JUDGMENT30121 OF 2003 MOSCA v ROADS AND TRAFFIC AUTHORITY OF NEW SOUTH WALES
:
1 This is an objection pursuant to the Land Acquisition (Just Terms Compensation) Act 1991, s 66(1) against the amount of compensation in the sum of $911,170 offered by the Respondent in respect of its compulsory acquisition of a portion of the Applicant’s land situate at Skipton Lane, Prestons which occurred on 4 October 2002. That was the date of the publication in Government Gazette No 163 of a Notice of Compulsory Acquisition in respect of that land, (together with several other parcels of land variously situate at Prestons, Hoxton Park and Hinchinbrook), which lands were collectively acquired for the “purposes of the Roads Act 1993”.
2 As so often occurs in cases of disputed compensation claims under the Just Terms Act, the Applicant’s claim for an amount considerably greater than the amount offered by the Respondent was countered at the hearing by the Respondent contending for an amount of compensation far less than the amount originally offered in the statutory Compensation Notice.
3 It is common ground that the particular purpose under the Roads Act for which the described lands were acquired was for the purposes of the Western Sydney Orbital (WSO) being a major road forming a connecting adjunct to the National Highway by linking it between the M5 Motorway situate at Prestons in the south and the M2 Motorway situate at Baulkham Hills in the north. (More recently, this section of road has been nominated as the M7 Westlink.)
4 The land compulsorily acquired from the Applicant is shown as lot 5 in Deposited Plan 1045043 (prepared on behalf of the Respondent and registered on…
Keep reading for free
Create a free CaseChat account to read Mosca v Roads and Traffic Authority of NSW and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2004] NSWLEC 676
- Decision Date
CaseChat Overview and Summary
The court found that the blight caused by the WSO, which had been in the planning and implementation stages for nine years prior to the compulsory acquisition, had significantly affected the value of the applicant's land. The sustained blight had frozen the development potential of the affected lands, leading to a decrease in their value. The court held that this decrease in value, due to the blight created by the WSO, had to be disregarded in determining the market value of the compulsorily acquired land, as required by the Just Terms Act. The court also decided how this decrease in value should be disregarded, concluding that the only reasonable and practical manner to give effect to the statutory imperative was to treat the applicant's land as being in a condition that would enable its residential potential to be realisable in the ordinary course of development.
Based on the court's findings, it determined the compensation payable to the applicant. The court awarded $941,260 for the market value of the compulsorily acquired land and $278,740 for the decrease in value of the retained land caused by the WSO, resulting in total compensation of $1,220,000. The court reserved the question of whether compensation for disturbance was payable, leaving it for the parties to agree or for the court to determine if necessary. The question of costs was also reserved. The court ordered that the exhibits be returned and granted liberty to restore on three days' notice.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi