Morris v Protec Pty Ltd

Link copied
Case Copied 8 min read

[2010] QDC 504

DISTRICT COURT

CIVIL JURISDICTION

JUDGE JONES

No 4284 of 2005

PAUL ANDREW MORRIS AND ANOTHER Plaintiffs

and

PROTEC PTY LTD AND ANOTHER Defendants

BRISBANE

..DATE 25/11/2010

ORDER

HIS HONOUR:  I will give my reasons now but I reserve my right to tidy my reasons up.

This is an application brought by the plaintiff applicant to seek leave to proceed pursuant to rule 389 and in particular subrule 2 of the Uniform Civil Procedure Rules.

Proceedings commenced in November 2005.  Originally there were two defendants involved - Protec Pty Ltd, the respondent to this application, and Walters Investments Pty Ltd.  For reasons it is not necessary to go into other than perhaps to note that the action against the second defendant, Walters, was compromised and therefore there are no longer any proceedings on foot against the second defendant.

The last formal step in the action was April 2006 when the first defendant filed its defence.  To that extent then four and a half-odd years have passed since the last step in the action.  That is in the context of a matter that was commenced only some five years ago.

The arguments have substantially centred around three matters.  Namely, the delay, the prospects of success and the question of prejudice.  Other issues were raised when counsel for the respective parties were dealing with those matters, but I think it is reasonable to say that they were the three main issues agitated.

The reasons for the delay are in the main addressed in an affidavit by Mr John Davies, the solicitor acting for the plaintiff, and an affidavit sworn by the plaintiffs filed 1 November 2010.

In respect of the affidavit of the plaintiffs in paragraph 5 they say, "We have always wanted to advance the proceeding to a conclusion, but understood that there were communication delays and difficulties with the solicitors for the first defendant and a refusal by them to agree to a date for mediation."

In paragraph 6 they say, "As small business operators we are certainly unable to focus on this litigation on a daily basis and have been concerned about the cost of litigation."  And in paragraph 10 say that if they were granted leave to proceed they would undertake to pursue litigation diligently.

I should note that in respect of paragraph 6 while it is asserted that they are concerned about cost it has not been asserted and it certainly could not be reasonably inferred that for any significant part of delay the plaintiffs were unable to fund the prosecution of the action.

Of particular significance here is the affidavit of Mr Davies.  In paragraph 7 he asserts, "I have always been concerned at the cost of the litigation for the plaintiffs having regard to the quantum of the claim.  For this reason I have deliberately adopted a course of attempting to resolve the litigation by alternate dispute resolution means, including negotiation and mediation."

In paragraph 8 he asserts, "To this extent I accept…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Morris v Protec Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2010] QDC 504
Decision Date

CaseChat Overview and Summary

The case of Morris v Protec Pty Ltd involves an application brought by the plaintiffs, Paul Andrew Morris and another, seeking leave to proceed with their legal action against the defendants, Protec Pty Ltd and another. The application was filed under rule 389 of the Uniform Civil Procedure Rules, specifically subrule 2, in the context of a dispute that originated in November 2005. The proceedings against the second defendant, Walters Investments Pty Ltd, have since been settled, leaving only Protec Pty Ltd as a defendant. The primary issues before the court were the delay in proceeding with the case, the prospects of success for the plaintiffs, and whether the defendants had suffered any prejudice as a result of the delay.

The court analysed the affidavits submitted by the plaintiffs and their solicitor, Mr John Davies, to assess the reasons for the delay. The plaintiffs cited communication issues with the defendant's solicitors and a refusal to agree on a mediation date as contributing factors to the delay. They also mentioned their inability to focus on the litigation due to their small business operations and concerns about the costs of litigation. Mr Davies admitted responsibility for some of the delay, acknowledging his strategy to resolve the dispute through alternative means, such as negotiation and mediation, which he believed would help control costs. However, the court found that there were significant periods of inactivity without any explanation, particularly between September 2006 and October 2007, and again from June 2009 to September 2010.

Regarding the prospects of success, the plaintiffs' claims against Protec Pty Ltd included allegations of breach of duty of care and contravention of the Trade Practices Act. The plaintiffs argued that had they been properly informed about the technical data sheets provided by Protec Pty Ltd, they would have terminated their contract with the second defendant. However, the court found it difficult to establish a causal relationship between Protec Pty Ltd's actions and the plaintiffs' subsequent actions, and the basis for the trade practices claim was unclear. Given the significant delay, lack of a strong explanation for it, and the relatively poor prospects of success, the court concluded that the application should be refused.

In summary, the court dismissed the plaintiffs' application for leave to proceed, finding that the delay was unjustified and the prospects of success were not strong. The court also noted that no material prejudice had been demonstrated by the defendants, which would not have altered the decision even if the delay and prospects of success were considered less severe. The plaintiffs were ordered to pay the costs of the application to the defendants.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established