Morley v See
Case
•
[2015] QCATA 127
•25 August 2015
Details
AGLC
Case
Decision Date
Morley v See [2015] QCATA 127
[2015] QCATA 127
25 August 2015
CaseChat Overview and Summary
In the matter of Morley v See, the appeal was brought before the court following a dispute between the parties regarding the applicability of section 42 of the Queensland Building and Construction Commission Act 1991. The primary concern was whether the contract between the parties fell under the definition of "building work" as outlined in the Act, and if so, whether it was excluded by any provisions in the Queensland Building and Construction Commission Regulation 2003. The lower court's decision, dated 2 March 2015, was challenged on these grounds, and the appellant sought leave to appeal.
The court was tasked with determining whether section 42 of the Act applied to the contract in question and if the work performed was indeed "building work" as defined by the Act. Additionally, the court had to consider whether any exclusions in Schedule 1AA, Item 11 of the Regulation applied to the work performed. These legal issues were central to the resolution of the dispute and the subsequent granting of leave to appeal.
The court examined the terms of the contract and the relevant statutory provisions. It found that the contract in question did fall within the definition of "building work" as outlined in the Act. However, the court also noted that the work was excluded from this definition by Schedule 1AA, Item 11 of the Regulation. As a result, the court concluded that the lower court's decision was incorrect and granted leave to appeal. The appeal was allowed, and the decision of 2 March 2015 was set aside. The appellant was not required to repay any amount to the respondent in relation to this matter.
The court's final orders included granting the application for leave to appeal, allowing the appeal, setting aside the decision of 2 March 2015, and relieving the appellant of any obligation to repay the respondent.
The court was tasked with determining whether section 42 of the Act applied to the contract in question and if the work performed was indeed "building work" as defined by the Act. Additionally, the court had to consider whether any exclusions in Schedule 1AA, Item 11 of the Regulation applied to the work performed. These legal issues were central to the resolution of the dispute and the subsequent granting of leave to appeal.
The court examined the terms of the contract and the relevant statutory provisions. It found that the contract in question did fall within the definition of "building work" as outlined in the Act. However, the court also noted that the work was excluded from this definition by Schedule 1AA, Item 11 of the Regulation. As a result, the court concluded that the lower court's decision was incorrect and granted leave to appeal. The appeal was allowed, and the decision of 2 March 2015 was set aside. The appellant was not required to repay any amount to the respondent in relation to this matter.
The court's final orders included granting the application for leave to appeal, allowing the appeal, setting aside the decision of 2 March 2015, and relieving the appellant of any obligation to repay the respondent.
Details
Key Legal Topics
Areas of Law
-
Civil Litigation & Procedure
Legal Concepts
-
Appeal
-
Limitation Periods
-
Contract Formation
-
Breach of Contract
Actions
Download as PDF
Download as Word Document
Citations
Morley v See [2015] QCATA 127
Most Recent Citation
QBCC v Morley [2016] QMC 8
Cases Cited
2
Statutory Material Cited
3
Pickering v McArthur
[2005] QCA 294
Moose Plastering Pty Ltd v Habul
[2014] QCATA 354
Pickering v McArthur
[2005] QCA 294