Morley v See

Case [2015] QCATA 127


CITATION:

Morley v See [2015] QCATA 127

PARTIES: Wade Morley
(Applicant/Appellant)
v
Andrew See
(Respondent)
APPLICATION NUMBER: APL127-15
MATTER TYPE: Appeals
HEARING DATE: 17 July 2015
HEARD AT: Brisbane
DECISION OF: Senior Member Stilgoe OAM
Member Traves
DELIVERED ON: 25 August 2015
DELIVERED AT: Brisbane
ORDERS MADE:

1.    Application for leave to appeal granted.

2.    The appeal is allowed.

3.    The decision of 2 March 2015 is set aside.

4.    The appellant is not required to repay the respondent any of the amount paid to him by the respondent in relation to this matter. 

CATCHWORDS:

APPEAL – LEAVE TO APPEAL – MINOR CIVIL DISPUTE - whether s42 of the Queensland Building and Construction Commission Act 1991 (Qld) applied - whether the contract between the parties was for “building work” within the meaning of the Queensland Building and Construction Commission Act 1991 (Qld) – whether the work was excluded from the definition of “building work” in Schedule 2 by Schedule 1AA, Item 11 of the Queensland Building and Construction Commission Regulation 2003 (Qld)

Queensland Civil and Administrative Tribunal Act 2009 (Qld) s 142(3), s 147(2)
Queensland Building and Construction Commission Act 1991 (Qld) s42, Schedule 2
Queensland Building and Construction Commission Regulation 2003 (Qld), Schedule 1AA, Item 11

Moose Plastering Pty Ltd v Habul [2014] QCATA 354
Pickering v MacArthur [2005] QCA 294

APPEARANCES and REPRESENTATION (if any):

Applicant: Wade Morley

Respondent:

Andrew See

REASONS FOR DECISION

  1. Wade Morley carried out certain work relating to the unblocking and repair of a stormwater drain for Andrew See on 15 October 2013. He charged $4,323 for the work which included $1,430 for re-paving the affected area. Although Mr See had asked Mr Morley to arrange for the re-paving to be done, Mr See paid the paving contractors directly.  

  2. This dispute relates to the remainder of the work - the unblocking and repair of a stormwater drain - for which Mr Morley charged $2,893.

  3. At the time Mr Morley did the work for Mr See he did not hold a Plumbing and Drainage trade contractor’s licence under the Queensland Building and Construction Commission Act 1991 (Qld).

  4. The Tribunal found on 2 March 2015 that Mr Morley was required to hold a contractor’s licence to do the relevant work because the work was “building work” within the meaning of the QBCC Act. The Tribunal found it was “building work” because it constituted “drainage work in connection with a building” within the meaning of Schedule 2 of the Act.

  5. Being unlicensed, the tribunal found that Mr Morley was in breach of s 42 of the QBCC Act and was therefore only entitled to recover “reasonable remuneration” for the work within the meaning of s 42(4) of the Act. Mr Morley was ordered to repay part of the fees paid to him by Mr See for doing the work.

  6. Mr Morley has applied for leave to appeal that decision.

Leave to Appeal

  1. As this is an appeal from a decision of the Tribunal in its minor…

Continue reading Morley v See

Sign in free to access the full text

Details
AGLC
Morley v See [2015] QCATA 127
Case
[2015] QCATA 127
Decision Date

CaseChat Overview and Summary

In the matter of Morley v See, the appeal was brought before the court following a dispute between the parties regarding the applicability of section 42 of the Queensland Building and Construction Commission Act 1991. The primary concern was whether the contract between the parties fell under the definition of "building work" as outlined in the Act, and if so, whether it was excluded by any provisions in the Queensland Building and Construction Commission Regulation 2003. The lower court's decision, dated 2 March 2015, was challenged on these grounds, and the appellant sought leave to appeal.

The court was tasked with determining whether section 42 of the Act applied to the contract in question and if the work performed was indeed "building work" as defined by the Act. Additionally, the court had to consider whether any exclusions in Schedule 1AA, Item 11 of the Regulation applied to the work performed. These legal issues were central to the resolution of the dispute and the subsequent granting of leave to appeal.

The court examined the terms of the contract and the relevant statutory provisions. It found that the contract in question did fall within the definition of "building work" as outlined in the Act. However, the court also noted that the work was excluded from this definition by Schedule 1AA, Item 11 of the Regulation. As a result, the court concluded that the lower court's decision was incorrect and granted leave to appeal. The appeal was allowed, and the decision of 2 March 2015 was set aside. The appellant was not required to repay any amount to the respondent in relation to this matter.

The court's final orders included granting the application for leave to appeal, allowing the appeal, setting aside the decision of 2 March 2015, and relieving the appellant of any obligation to repay the respondent.

Orders

Orders of the court

1. Application for leave to appeal granted.

2. The appeal is allowed.

3. The decision of 2 March 2015 is set aside.

4. The appellant is not required to repay the respondent any of the amount paid to him by the respondent in relation to this matter.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.