Monadelphous Engineering Pty Ltd v Wiggins Island Coal Export Terminal Pty Limited

Link copied
Case Copied 24 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Monadelphous Engineering Pty Ltd & Anor v Wiggins Island Coal Export Terminal Pty Limited [2015] QCA 290

PARTIES:

MONADELPHOUS ENGINEERING PTY LTD & MUHIBBAH CONSTRUCTION PTY LTD TRADING AS MONADELPHOUS MUHIBBAH MARINE
ABN 76 609 605 632

(appellants)v
WIGGINS ISLAND COAL EXPORT TERMINAL PTY LIMITED
ACN 131 210 038
(respondent)

FILE NO/S:

Appeal No 6770 of 2015
SC No 12118 of 2014

DIVISION:

Court of Appeal

PROCEEDING:

General Civil Appeal

ORIGINATING COURT:


Supreme Court at Brisbane – [2015] QSC 160

DELIVERED ON:

18 December 2015

DELIVERED AT:

Brisbane

HEARING DATE:

13 November 2015

JUDGES:

Holmes CJ and Applegarth and Boddice JJ
Separate reasons for judgment of each member of the Court, each concurring as to the order made

ORDER:

The appeal is dismissed with costs.

CATCHWORDS:

CONTRACTS – BUILDING ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – OTHER MATTERS – where the respondent contracted the appellants’ firm to perform construction work in relation to the construction of a coal export terminal – where the respondent purported to call on bank guarantees to secure performance of its contractual obligations – where the appellants claimed that the contract was governed by the Queensland Building and Construction Commission Act 1991 (Qld) such that the respondent was precluded from calling upon the guarantees – where the primary judge found that the contract was not a “building contract” for the purposes of the Act – where the primary judge relied upon an earlier decision of this Court – where that decision considered the meaning of “building works” and “building contract” under the Act – whether that decision was wrong and should be overruled

Acts Interpretation Act 1954 (Qld), s 35C
Queensland Building and Construction Commission Act 1991 (Qld), s 3(a)(i), s 3(a)(ii), s 67AAA, pt 4A, sch 2
Queensland Building and Construction Commission Regulation 2003 (Qld), s 5, sch 1AA

Gett v Tabet (2009) 254 ALR 504; [2009] NSWCA 76, cited
Marshall v Marshall [1999] 1 Qd R 173; [1997] QCA 382, cited
McNab Constructions Australia Pty Ltd v Queensland Building Services Authority (2011) 27 BCL 345; [2010] QCA 380, cited
Monadelphous Engineering Pty Ltd & Anor v Wiggins Island Coal Export Terminal Pty Ltd [2014] QCA 330, followed
Monadelphous Engineering Pty Ltd & Muhibbah Construction Pty Ltd trading as Monadelphous Muhibbah Marine v Wiggins Island Coal Export Terminal Pty Ltd [2015] QSC 160, considered
Morton Engineering Co Pty Ltd v Stork Wescon Australia Pty Ltd (1999) 15 BCL 192; [1998] QSC 102, cited
Morton Engineering Co Pty Ltd v Stork Wescon Australia Pty Ltd [2000] 2 Qd R 148; [1999] QCA 61, cited
Nguyen v Nguyen (1990) 169 CLR 245; [1990] HCA 9, cited
Silk Bros v State Electricity Commission (Vic) (1943) 67 CLR 1; [1943] HCA 2, cited
Sweeney v Volunteer Marine Rescue Currumbin Inc[2000] QCA 445, cited

COUNSEL:

P J Dunning QC, with S R…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Monadelphous Engineering Pty Ltd v Wiggins Island Coal Expor... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2015] QCA 290
Decision Date

CaseChat Overview and Summary

Monadelphous Engineering Pty Ltd, the appellant, engaged in a contractual dispute with Wiggins Island Coal Export Terminal Pty Limited, the respondent, concerning the construction of a coal export terminal. The appellant, a firm of engineering contractors, was contracted by the respondent to perform certain construction work. When the respondent faced financial difficulties, it attempted to call on bank guarantees provided by the appellant to secure the appellant's performance of the contractual obligations. The appellant argued that the contract was subject to the Queensland Building and Construction Commission Act 1991 (Qld), and therefore, the respondent was not permitted to call upon the guarantees. The primary judge ruled in favour of the respondent, determining that the contract did not constitute a "building contract" under the Act. This finding was based on a previous decision of the Court which had considered the definitions of "building works" and "building contract" under the Act.

The central legal issue before the Court was whether the primary judge's interpretation of the Act was correct, specifically whether the contract in question was a "building contract" for the purposes of the Act. The Court was required to determine whether the primary judge's reliance on the earlier decision of the Court was justified, and if not, whether that earlier decision should be overruled. The Court needed to examine the definitions of "building works" and "building contract" under the Act and consider whether the construction work performed by the appellant fell within those definitions.

The Court found that the primary judge's interpretation of the Act was correct and dismissed the appeal. The Court held that the construction work in question did not constitute "building works" as defined by the Act and that the contract was therefore not a "building contract." The Court considered the reasoning of the earlier decision to be sound and did not find any grounds to overrule it. As a result, the respondent was entitled to call upon the bank guarantees provided by the appellant. The appeal was dismissed with costs.

In summary, the Court dismissed the appeal and affirmed the primary judge's decision that the contract was not a "building contract" under the Queensland Building and Construction Commission Act 1991 (Qld). The Court found no reason to depart from the earlier decision of the Court and upheld the respondent's right to call upon the bank guarantees provided by the appellant. The appeal was dismissed with costs awarded to the respondent.

Orders

Orders of the court

The appeal is dismissed with costs.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.