Mobile Building System International Pty Ltd v Hua

Link copied
Case Copied 32 min read
CITATION: Mobile Building System International Pty Ltd v Hua [2013] QCAT 636
PARTIES: Mobile Building System International Pty Ltd
(Applicant)
v
Koji Hua
(Respondent)
APPLICATION NUMBER: BDL271-12
MATTER TYPE: Building matters
HEARING DATE: 22 – 23 April 2012
HEARD AT: Brisbane
DECISION OF: Member McLean Williams
DELIVERED ON: 28 November 2013
DELIVERED AT: Brisbane
ORDERS MADE:

1.    The applicant is to pay to the respondent the sum of $168,149.50: within 28 days of the date of these orders.

2.    Pursuant to s .39 of the Domestic Building Contracts Act, the applicant is to deliver to the respondent all original contract related documents and building certificates within 28 days of the date of these orders.

CATCHWORDS:

Residential building dispute – termination of contract – whether properly terminated – entitlement of homeowner to terminate for failure to remedy breaches – whether builder entitled to claim for undocumented variations – whether builder entitled to claim progress payments in circumstances where work under that stage incomplete and special conditions requiring all works for that stage to be “fully completed”.

Domestic Building Contracts Act 2000 ss39, 65, 69, 84, 93

Shepherd v Felt & Textiles of Australia Ltd (1931) 45 CLR 339
Bellgrove v Eldridge (1954) 90 CLR 613
QCoal P/L & Anor v Cliffs Coal P/L & Anor [2010] QSC 479
Velvet Glove Holdings Pty Ltd v Mount Isa Mines Limited [2011] QSC 95

APPEARANCES and REPRESENTATION (If any):

APPLICANT: Mr Nicholas Vale
RESPONDENT: Mr Tim Matthews of Counsel, instructed by Romans & Romans, Lawyers.

REASONS FOR DECISION

Preliminary

  1. Mobile Building System International Pty Ltd (the applicant) is a residential building company operated by Mr Nicholas Vale. 

  2. On 29 August 2012, the applicant commenced these proceedings against the respondent, Mr Koji Hua, seeking payment of $127,960.35 that the applicant contends it is still owed for outstanding stage payments, variations, and default interest.  These claims arise in relation to a residential duplex that the applicant constructed for Mr Hua, at 18 Sapium Street, at Kingston. 

  3. In his response to that claim filed on 12 September 2012, Mr Hua contends that no monies are owed for progress payments, by reason that the stages claimed (being stages 5 and 6) have not been fully completed.  Mr Hua also says that the applicant has no entitlement to any of the claimed variations, because the claimed amounts are for matters that were already within the agreed scope of works; or arise because of changes made without Mr Hua’s prior written approval. 

  4. Because of the applicant’s failure to complete the works in conformity with the scope of works required by the contract, Mr Hua asserts that he has validly terminated the contract, and now brings a counterclaim before QCAT, seeking:

    1.    $260,845.82 for the completion of the duplex, including various necessary rectification works;

    2. $20,236 pursuant to section 69 of the Domestic Building Contracts Act 2000 for the refund of over-paid amounts;

    3.    $4,620 for prime cost items;

    4.    $22,633.60 for interest as a consequence of delays by the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Mobile Building System International Pty Ltd v Hua and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] QCAT 636
Decision Date

CaseChat Overview and Summary

Mobile Building System International Pty Ltd, a residential building company operated by Mr Nicholas Vale, commenced these proceedings against Mr Koji Hua, seeking payment of $127,960.35 that the applicant contends it is still owed for outstanding stage payments, variations, and default interest. These claims arise in relation to a residential duplex that the applicant constructed for Mr Hua, at 18 Sapium Street, at Kingston. In his response to that claim filed on 12 September 2012, Mr Hua contends that no monies are owed for progress payments, by reason that the stages claimed (being stages 5 and 6) have not been fully completed. Mr Hua also says that the applicant has no entitlement to any of the claimed variations, because the claimed amounts are for matters that were already within the agreed scope of works; or arise because of changes made without Mr Hua’s prior written approval. Because of the applicant’s failure to complete the works in conformity with the scope of works required by the contract, Mr Hua asserts that he has validly terminated the contract, and now brings a counterclaim before QCAT, seeking: $260,845.82 for the completion of the duplex, including various necessary rectification works; $20,236 pursuant to section 69 of the Domestic Building Contracts Act 2000 for the refund of over-paid amounts; $4,620 for prime cost items; $22,633.60 for interest as a consequence of delays by the builder; $865 for the cost of disturbance caused by the applicant and its agents on 5 & 7 September 2012; $450 for the costs of storing the applicant’s equipment; $8,036 in legal costs incurred when it became necessary to terminate the contract and respond to the Applicant’s BCIPA adjudication; $3,802.37 as restitution pursuant to s 100 of BCIPA; orders pursuant to s 39 of the Domestic Building Contracts Act 2000 requiring the Applicant to produce the originals of all contract related documents and building certificates; and Costs. The issues for determination were whether the applicant is entitled to payment for variations; whether the applicant is entitled to the claimed payments for stages 5 and 6; whether, as a consequence of (i) & (ii) above, the builder is entitled to interest; whether the respondent has validly terminated the contract; and whether the respondent is now entitled to lay claim to the costs of completion of the construction project (including rectification works), and various consequential costs. It was found that the applicant was not entitled to any remuneration for variations, other than for that related to the power connection. It was concluded that Mr Hua was not entitled to withhold the stage 5 progress claim. The applicant was not entitled to be paid for Stage 6 at the time when the progress claim was presented. The grounds for the Notice of Termination sent on 7 August 2012 were well made out. The costs of rectification and completion should be reduced by $55,651.20, inclusive of GST. The costs of urgent rectification of the mains power supply and electrical meter had been paid to the applicant. The applicant was to pay to the respondent the sum of $152,169.62 plus interest thereon assessed as $15,979.88, making for a total judgement sum of $168,149.50: within 28 days of the date of these orders. Pursuant to s 39 of the Domestic Building Contracts Act that the applicant deliver to the respondent all original contract related documents and building certificates within 28 days of the date of these orders.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.