SUPREME COURT OF QUEENSLAND
CITATION:
Mirvac Queensland Pty Ltd & Anor v Shamrock Civil Engineering Pty Ltd & Ors [2015] QSC 271
PARTIES:
MIRVAC QUEENSLAND PTY LTD
(ACN 060 411 207)(first plaintiff)
and
MIRVAC CONSTRUCTIONS (QLD) PTY LTD
(ACN 088 536 476)
(second plaintiff)v
SHAMROCK CIVIL ENGINEERING PTY LTD
(ACN 066 655 856)(first defendant)
and
MPN CONSULTING PTY LTD
(ACN 062 191 799)
(second defendant/first third party)
and
ROCLA PTY LTD
(ACN 000 032 191)
(second third party)FILE NO:
BS No 5113 of 2013
DIVISION:
Trial Division
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
22 September 2015
DELIVERED AT:
Brisbane
HEARING DATE:
17 September 2015
JUDGE:
Douglas J
ORDER:
1. Strike out paras 26F, 33(i), 38(i) and 43(i) of the second further amended statement of claim
2. Leave is granted to the plaintiffs to re-plead
3. Direct that the plaintiffs deliver a draft third further amended statement of claim by 4:00PM on Friday 25 September 2015
4. The plaintiffs pay the first and second defendants’ and second third parties’ costs of the application
CATCHWORDS:
PROCEDURE – SUPREME COURT PROCEDURE – QUEENSLAND – PROCEDURE UNDER UNIFORM CIVIL PROCEDURE RULES AND PREDECESSORS – PLEADING – STATEMENT OF CLAIM – where the first plaintiff was required by the Brisbane City Council to provide a stormwater harvesting system in a park now owned by the Council in order to comply with development approval conditions – where the first defendant was engaged to construct and install the system – where the second defendant was engaged to aid in the design and documentation of the system – where the stormwater harvesting system installed subsequently failed and was abandoned – where the first plaintiff was relieved from complying with the development approval conditions by the Council insofar as they included a requirement to provide a stormwater harvesting system in the park now owned once again by the Council – where the first defendant was sued for breach of contract and for damages for negligence and the second defendant was sued in tort – whether the first plaintiff properly pleaded the claims for damages
Commonwealth v Amann Aviation Pty Ltd (1991) 174 CLR 64; [1991] HCA 54, cited
LBS Holdings Pty Ltd v The Body Corporate for Condor Community Title Scheme 13200 [2004] QSC 229, cited
McRae v Commonwealth Disposals Commission (1951) 84 CLR 377; [1951] HCA 79, cited
Southern Cross Mine Management Pty Ltd v Ensham Resources Pty Ltd [2004] QSC 457, cited
UI International Pty Ltd v Interworks Architects Pty Ltd [2008] 2 Qd R 158; [2007] QCA 402, citedCOUNSEL:
P A Hastie QC for the plaintiffs
D P O’Brien QC with P J McCafferty for the first defendant
J B Sweeney for the second defendant and first third party
D J Pyle for the second third partySOLICITORS:
Minter Ellison for the plaintiffs
TressCox Lawyers for the first defendant
Carter Newell Lawyers for the second defendant and first third party
Keep reading for free
Create a free CaseChat account to read Mirvac Queensland Pty Ltd v Shamrock Civil Engineering Pty L... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2015] QSC 271
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the plaintiffs had properly pleaded the claims for damages. The first defendant argued that the pleadings should be struck out, as the plaintiffs had not sufficiently demonstrated any loss or damage that would entitle them to compensation. The plaintiffs, on the other hand, argued that they had lost the benefit and use of the stormwater harvesting system, and that the cost of the installation should be considered as the best particulars of the benefit. The court found that the pleadings did not establish what different position the plaintiffs would have been in had the contract been fully performed, nor did they allege that the first defendant's breach made it impossible to ascertain whether or not the plaintiffs would have made a profit from the performance of the contract. The court concluded that it was appropriate to strike out certain paragraphs of the pleadings and grant leave to re-plead.
In light of the submissions made by the plaintiffs' counsel, the court granted leave to re-plead and directed the plaintiffs to deliver a draft third further amended statement of claim by a specified deadline. The plaintiffs were also ordered to pay the first and second defendants' and second third parties' costs of the application. The court's decision was based on the need for the plaintiffs to better particularise their claims and demonstrate the loss or damage they had suffered as a result of the defendants' actions.
Orders
Orders of the court
1. Strike out paras 26F, 33(i), 38(i) and 43(i) of the second further amended statement of claim
2. Leave is granted to the plaintiffs to re-plead
3. Direct that the plaintiffs deliver a draft third further amended statement of claim by 4:00PM on Friday 25 September 2015
4. The plaintiffs pay the first and second defendants’ and second third parties’ costs of the application
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
The challenge by the defendants relates only to the “capital cost” claim of $1,827,923, not to the claim for rectification costs.Submissions and consideration The first defendant’s argument that paras 26F, 33(i) and 38(i) should be struck out is based on several premises. The first argument is that the first plaintiff was never intended to benefit from or otherwise use the stormwater harvesting system. Rather that was intended to be for the benefit of the Council on land which reverted to it. As the pleading stands, having regard to the uncontroverted fact that the Council now owns the land, there is no factual basis in the pleading to conclude that the plaintiffs have lost the benefit and use of the stormwater harvesting system. Mr Hastie QC for the plaintiffs indicated that the plaintiffs perceived at least a marketing advantage in being able to promote the development as one which included environmentally sustainable design initiatives, as alleged in para 7A of the pleading, but there are no further facts pleaded or particularised to make that point or show how it would benefit the plaintiffs financially or otherwise. He conceded that para 26F could be better particularised to allege in what respects the plaintiffs had lost the benefit and use of the stormwater harvesting system. At present, however, the pleading does not disclose any particular benefit or use of the stormwater harvesting system available to the plaintiffs that has been lost. The second argument for the first defendant was that, where it is alleged that building or construction work is defective, the appropriate measure of damages will be either the rectification costs or, failing that, that measure which reflects the diminished value of an asset.[1] Mr O’Brien QC submitted that, where rectification cannot be carried out, as here, and where the value of the asset is not diminished, there is simply no loss for which the plaintiffs should be compensated. [1] UI International Pty Ltd v Interworks Architects Pty Ltd [2008] 2 Qd R 158, 172 at [20], 190-192 at [87] – [93]. The third argument for the first defendant was that the only benefit to the first plaintiff of its installation and payment for the stormwater harvesting system was its entitlement to pursue the development, on the basis that it was never intended to receive any particular benefit from the installation other than the development approval. Once the parkland had been transferred back to the Council, which agreed to the course that had been adopted of filling the tanks and abandoning the system, the first plaintiff had suffered no loss compensable on the normal principles for the award of damages for breach of contract or in tort. The first plaintiff was in precisely the same position as it would have been had the contract been performed or if any alleged negligence with respect to the design and installation of the system had not occurred. The fourth argument advanced for the first defendant was that, if the position advanced by the plaintiffs was correct, then the first plaintiff would, if successful, receive a windfall such that it would be put in a better position than it would have been in had the contract been performed. The rationale for that submission was that it was always the position that the first plaintiff was obliged to spend money on the system for the sole benefit of the Council and for which the first plaintiff was not to be reimbursed. It received the benefit of undertaking its proposed development under the development approval in attempting to install the system, but the fact that the system was not successfully completed was of no consequence to it. In other words, the funds applied towards the design and installation of the system needed to be spent in order to comply with the conditions and to permit the first plaintiff to recover the costs of the system would be to sanction double recovery.[2][2] See UI International Pty Ltd v Interworks Architects Pty Ltd [2008] 2 Qd R 158, 188 at [79].