| CITATION: | Mewett v Williams [2015] QCAT 50 |
| PARTIES: | Adam Mewett t/as Mewett Constructions (Applicant) |
| v | |
| Daniel Williams (Respondent) |
| APPLICATION NUMBER: | BDL092-14 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | 27 January 2015 |
| HEARD AT: | Brisbane |
| DECISION OF: | Dr Cullen, Member |
| DELIVERED ON: | 16 February 2015 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. The application is dismissed. |
| CATCHWORDS: | Domestic Building Dispute – Unlawful contract by builder, homeowner entitled to terminate contract, builder entitled to be paid for fair market value of work less cost to rectify defects Domestic Building Contracts Act 2000 (Qld) |
APPEARANCES:
| APPLICANT: | Adam Mewett |
| RESPONDENT: | Daniel Williams |
REASONS FOR DECISION
The respondent in this matter, a young man named Daniel Williams, entered into a contract for the renovation of a bathroom and laundry. Unfortunately, he believed that the contract was with a Mr Paul Donovan, the husband of one of his mother’s friends. This was not so, and the ensuing renovation project has been anything but straightforward.
Mr Williams discovered that his contract was not with Mr Donovan, but was actually with a company called Mewett Constructions, for whom Mr Donovan was acting as agent. Mr Williams disputes the existence of a contract, but there is evidence that before the Tribunal that Mr Donovan forwarded a quote via his own email, on Mewett Constructions letterhead. The quotation was then accepted by Mr Williams.
Sadly, for all parties concerned in this matter, the issues raised before the Tribunal here aptly demonstrate the reasons that domestic building contracts are regulated in Queensland.
Mr Adam Mewett, the Director of Mewett Constructions, accepts that he did not comply with the Domestic Building Contracts Act 2000 (Qld) in providing Mr Williams with a written contract, and admits that he required payment of a deposit sum in excess of that permitted by the Act.
Mr Mewett says that he has learnt a considerable amount about the paperwork end of building, as a result of the difficulties he has faced with this particular matter. Equally, it is entirely understandable that Mr Williams feels that he has been duped, as it was never made clear to him that his contract was not with Mr Donovan, but rather was with Mewett Constructions.
Application by builder seeking payment for work
The application now before the Tribunal has come about because Mr Mewett says that Mewett Constructions is entitled to be paid for the work it performed at Mr Williams’ home. Mewett Constructions seeks an order in its favour for what it says is an unpaid sum of $14,803.90.
In defence, Mr Williams submits that there are a number of aspects of the work that are either defective, or incomplete. Mr Williams has not filed a counter-claim in this matter, but has provided the Tribunal with quotations relating to the costs of rectification. Of these, the least expensive is $17,855.51.
Mr Mewett has raised considerable concern that Mr Williams has not allowed him the opportunity to rectify any defective work, or to complete work that had not been finalised. That complaint has…
Keep reading for free
Create a free CaseChat account to read Mewett v Williams and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] QCAT 50
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the contract between the parties was unlawful and, if so, whether Williams was entitled to terminate the contract. The court also needed to determine whether Mewett was entitled to any payment for the work completed. The court considered the terms of the contract, the relevant provisions of the Home Building Act, and the precedent set by previous cases.
The court found that the contract was indeed unlawful, as it did not comply with the requirements of the Home Building Act. However, the court held that Williams was not entitled to terminate the contract as the Act did not provide for termination in such circumstances. Instead, the court held that Mewett was entitled to be paid for the fair market value of the work completed, less the cost to rectify any defects. The court dismissed Williams' application.
The court ordered that the application was dismissed, and that Mewett was entitled to be paid for the fair market value of the work completed, less the cost to rectify any defects. The court did not award any costs to either party.
Orders
Orders of the court
1. The application is dismissed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.