Metro Chatswood Pty Ltd v Transport Construction Authority

Case [2010] NSWLEC 148



Land and Environment Court


of New South Wales


CITATION: Metro Chatswood Pty Ltd v Transport Construction Authority [2010] NSWLEC 148
PARTIES:

APPLICANT:
Metro Chatswood Pty Ltd

RESPONDENT:
Transport Construction Authority
FILE NUMBER(S): 30983; 30984 of 2008
CORAM: Biscoe J
KEY ISSUES: PRACTICE AND PROCEDURE :- vacation of hearing dates because of in principle settlement agreement.
LEGISLATION CITED: Land Acquisition (Just Terms Compensation) Act 1991
DATES OF HEARING: 5 August 2010
EX TEMPORE JUDGMENT DATE: 5 August 2010
LEGAL REPRESENTATIVES:

APPLICANT:
Mr J Ayling SC
SOLICITORS
Piper Alderman

RESPONDENT:
Mr C Norton, barrister
SOLICITORS
Clayton Utz


JUDGMENT:

      THE LAND AND
      ENVIRONMENT COURT
      OF NEW SOUTH WALES

      BISCOE J

      5 August 2010

      30983-84 of 2008

      METRO CHATSWOOD PTY LTD v TRANSPORT CONSTRUCTION AUTHORITY

      EX TEMPORE JUDGMENT

1 HIS HONOUR: This is a motion by the applicant, supported by the respondent, to vacate the hearing dates of this matter next week.

2 The proceedings are for compensation for the compulsory acquisition of easements under the Land Acquisition (Just Terms Compensation) Act 1991. The main issue is the proper construction of the principal easement. The competing constructions have a very great effect on the amount of compensation that might be awarded. This became clear at a case management conference before me last week when the construction issue was extensively discussed.

3 Since then the parties have reached an in principle agreement to settle the proceedings including by variation of the principal easement to clarify its meaning and thereby to eliminate the construction issue to which I have referred. Thus, if the hearing were to proceed next week it would be on the basis of a false issue in the sense of one which will disappear under the settlement agreement.

4 The in principle settlement agreement is subject to certain conditions being satisfied which will or may involve obtaining the consent of third parties. The parties estimate that one month is necessary to attend to the third party issue and to formalise documentation including documentation that requires registration.

5 In the circumstances I am satisfied that it is appropriate to vacate the hearing dates and to stand over the proceedings for about a month.

6 The orders of the Court are as follows:


      1. The hearing dates of 9-13 August 2010 are vacated.
      2. The matter is listed for mention on 10 September 2010 before the List Judge.
Details
AGLC
Metro Chatswood Pty Ltd v Transport Construction Authority [2010] NSWLEC 148
Case
[2010] NSWLEC 148
Decision Date

CaseChat Overview and Summary

Metro Chatswood Pty Ltd applied to vacate the hearing dates for their case against the Transport Construction Authority in the Land and Environment Court of New South Wales. The matter involved the compulsory acquisition of easements under the Land Acquisition (Just Terms Compensation) Act 1991. The primary issue was the proper construction of the principal easement, which had significant implications for the compensation amount. This issue was thoroughly discussed at a case management conference. Subsequently, the parties reached an in principle agreement to settle the proceedings, including varying the principal easement to clarify its meaning and thereby eliminating the construction issue. The hearing was to proceed on a false issue if it were to continue as scheduled. The in principle settlement agreement was contingent on certain conditions being met, including obtaining consent from third parties and formalising documentation. The parties estimated that one month was necessary to address these conditions and finalise the documentation.

The court accepted the application to vacate the hearing dates, recognising the parties' in principle agreement and the need to attend to the third-party consent and documentation issues. The hearing dates of 9-13 August 2010 were vacated, and the matter was listed for mention on 10 September 2010 before the List Judge. The orders of the court included vacating the hearing dates and listing the matter for a future mention to allow time for the parties to finalise the settlement agreement. This decision ensured that the hearing would proceed on the basis of the true issues, rather than a moot point.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.