| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL COURT
COMMERCIAL LIST
S ECI 2023 03762
BETWEEN:
| MERKON CONSTRUCTIONS PTY LTD (ACN 006 587 319) | Plaintiff |
| and | |
| RESIDENCE COMPANY PTY LTD (ACN 056 096 121) | Defendant |
---
JUDGE: | M Osborne J |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 20 March 2025 |
DATE OF JUDGMENT: | 28 March 2025 |
CASE MAY BE CITED AS: | Merkon Constructions Pty Ltd v Residence Company Pty Ltd |
MEDIUM NEUTRAL CITATION: | [2025] VSC 151 |
---
BUILDING CONTRACT – Construction contract entered into between developer and builder – Interpretation of terms – Deeds of variation – Variation of contract sum – Builder’s claimed debt – Secured monies – Whether second deed of variation constitutes illegal contract – Whether builder is estopped from asserting claim for outstanding debt due to signing building superintendent’s final certificate – Developer’s defences rejected by Court – Judgment for the amount owed to builder.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | M Galvin KC with O Wolahan | Walpole Johnson |
| For the Defendant | Ian Hone, solicitor | Ian G Hone, barrister and solicitor |
HIS HONOUR:
In this proceeding, the plaintiff, Merkon Constructions Pty Ltd (‘the builder’) seeks to recover the sum of $2,448,869.55, which is said to represent the balance of moneys due to it from the defendant, Residence Company Pty Ltd (‘the developer’), following the construction of a multi-level residential apartment building at 10-16 Lilydale Grove, Hawthorn East (‘the property’).
On 8 July 2019, the builder and the developer entered into a construction contract (‘the contract’), which, inter alia, provided for the builder to undertake construction works for a lump sum of $28,826,000 (exclusive of GST), to be paid in accordance with the contract. The contract followed standard terms and included provisions, inter alia, for the payment of sums due under the contract, including the pricing and payment for variations, as well as provisions for the payment by the builder of liquidated damages in the event of delay.
By a loan facility agreement dated 1 November 2019 (‘the facility agreement’), entered into between the developer and a lender, Monland Pty Ltd (‘the lender’), the developer obtained a construction finance facility with a $40 million facility limit to facilitate the payment of construction costs incurred during the course of construction, including the payment of sums owed to the builder.
Among other things, the facility agreement provided, in clause 5.3, for any proceeds of sale (from the apartments when constructed) to be paid to the lender and applied to reduce amounts owed by the developer under the facility agreement.
The facility agreement was entered into contemporaneously with and referred to a builder’s side deed (‘the builder’s side deed’), which was entered into between the lender, the developer and the builder on 31 October 2019. The recitals to the builder’s side deed recorded that the lender had agreed to provide certain financial accommodation to the developer to fund payments to the builder for the construction works in accordance with the facility agreement, and that the developer had…
Keep reading for free
Create a free CaseChat account to read Merkon Constructions Pty Ltd v Residence Company Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2025] VSC 151
- Decision Date
CaseChat Overview and Summary
The court held that the second deed of variation did not constitute an illegal contract, as it did not contravene any statutory provision or public policy. Furthermore, the court determined that the builder was not estopped from claiming the outstanding debt. The court found that the signing of the building superintendent’s final certificate did not constitute a representation that the builder had been fully paid for the works completed. The court held that the developer’s defences were without merit, and the builder was entitled to recover the outstanding debt for the balance of the contract price.
The court concluded that the builder was entitled to recover the outstanding debt, and ordered the developer to pay the sum of $566,108.23, plus interest at the rate of 7% per annum from 18 July 2018 until the date of judgment. The court also ordered the developer to pay the builder’s costs of the proceedings, to be assessed if not agreed.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi