MENER GROUP PTY LTD and HIPPYDAYZE PTY LTD

Link copied
Case Copied 27 min read

JURISDICTION     :   STATE ADMINISTRATIVE TRIBUNAL

ACT:   BUILDING SERVICES (COMPLAINTS RESOLUTION AND ADMINISTRATION) ACT 2011 (WA)

CITATION:   MENER GROUP PTY LTD and HIPPYDAYZE PTY LTD [2019] WASAT 58

MEMBER:   MS C WALLACE, SENIOR MEMBER

HEARD:   DETERMINED ON THE DOCUMENTS

DELIVERED          :   31 JULY 2019

FILE NO/S:   CC 943 of 2019

BETWEEN:   MENER GROUP PTY LTD

Applicant

AND

HIPPYDAYZE PTY LTD

Respondent


Catchwords:

Building Services (Complaint Resolution and Administration) Act 2011 (WA) - Application for leave to apply for internal review under s 58(2) - Criteria on application for leave - Whether there was a breach of s 54(10) of the State Administrative Tribunal Act 2004 (WA) - Whether there was a breach of the principles of natural justice where mediator also presided on final hearing - Whether errors of law made in formulation of final order - Whether reasons of the Tribunal were inadequate - Whether in the circumstances a substantial injustice will be suffered

Legislation:

Building Services (Complaint Resolution and Administration) Act 2011 (WA), s 5(1), s 5(2), s 11(1)(d), s 38, s 41(2)(b), s 43, s 43(1)(a), s 49(1), s 58(2)
Home Building Contracts Act 1991 (WA), s 17
State Administrative Tribunal Act 2004 (WA), s 25(2), s 32(1) s 54, s 54(6), s 54(10), s 60(2), s 77

Result:

Leave to review granted

Summary of Tribunal's decision:

The applicant applied, under s 58(2) of the Building Services (Complaint Resolution and Administration) Act 2011 (WA), for leave to be granted to review the decision of Member de Villiers made on 28 May 2019. The decision of Member de Villiers was made in respect of applications made by the applicant seeking a Home Building Works Contract Remedy Order (HBWC Remedy Order) claiming amounts outstanding in respect of practical completion invoices issued to the respondent in respect of the construction of three units in the suburb of Gosnells. Although Member de Villiers found partially in favour of the applicant that money was owing under the relevant home building works contracts, a final order was issued ordering the applicant to pay the amount of $16,374.06 to the respondent.
The Tribunal granted leave to review the decision of Member de Villiers on the basis that if leave was not granted, a substantial injustice may be suffered by the applicant due to the following findings:
(a) Member de Villiers breached s 54(10) of the State Administrative Tribunal Act 2004 (WA) by both mediating the matter and then presiding at final hearing without the consent of the parties being sought or obtained. The Tribunal found that this also constituted a breach of the principles of natural justice.
(b)     Errors of law were made given that Member de Villiers made findings that outstanding amounts were owing to the applicant but no HBWC Remedy Order was made. In addition, in the absence of any legal       authority, Member de Villiers produced a final order which included the requirement to pay an amount by the applicant to the respondent which had been ordered in a previously concluded Tribunal proceeding,…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read MENER GROUP PTY LTD and HIPPYDAYZE PTY LTD and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] WASAT 58
Decision Date

CaseChat Overview and Summary

The matter between Mener Group Pty Ltd and Hippydayze Pty Ltd was heard before the State Administrative Tribunal of Western Australia. The dispute centred around the resolution of a complaint under the Building Services (Complaint Resolution and Administration) Act 2011 (WA). Mener Group sought leave to apply for an internal review of the Tribunal's decision, arguing that there were substantial errors in the Tribunal's final order. The legal issues the court needed to resolve included whether there was a breach of section 54(10) of the State Administrative Tribunal Act 2004 (WA), whether the principles of natural justice were breached when the mediator presided over the final hearing, and whether there were errors of law in the formulation of the final order. Additionally, Mener Group contended that the reasons provided by the Tribunal were inadequate and that, in the circumstances, a substantial injustice would be suffered if leave was not granted.

The court examined the reasons provided by the Tribunal and found them to be seriously inadequate. The reasons did not sufficiently explain the path of reasoning undertaken by the Tribunal, particularly in relation to the 'set-offs' applied in the final order. The court noted that the statutory requirement for reasons, as outlined in section 77 of the SAT Act, was not met. The Tribunal's reasons did not include findings on material questions of fact, nor did they provide adequate explanations for the decisions made. The court referenced the propositions established in Centex Australasia Pty Ltd v Commissioner for Consumer Protection, which emphasized the importance of reasons that allow an appeal court to determine whether the decision involved appellable error and to provide procedural fairness to the litigants. The court concluded that the inadequacy of the reasons resulted in a miscarriage of justice, as it was unable to discern the reasoning process of the Tribunal.

As a result of its findings, the court granted Mener Group's application for leave to apply for internal review. The decision acknowledged the substantial injustice that would be suffered if the inadequate reasons were not rectified. The court recognised the importance of adequate reasons in ensuring procedural fairness and the ability to properly review the Tribunal's decision. The final orders of the court allowed Mener Group to proceed with its application for internal review, providing an opportunity to address the issues of procedural fairness and the adequacy of reasons in the Tribunal's decision.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

The requirements to provide reasons for a final decision is set out in s 77 of the SAT Act:Reasons for final decision(1)The Tribunal is to give its reasons for a final decision.(2)Reasons that the Tribunal gives for a final decision have to include the Tribunal’s findings on material questions of fact, referring to the evidence or other material on which those findings are based. In the context of a consideration of s 77 of the SAT Act, the Court of Appeal in Centex Australasia Pty Ltd v Commissioner for Consumer Protection [2017] WASCA 79 set out the following propositions at [103]:The statutory terminology used to define the obligation to provide reasons can and should be construed in the context of a line of decisions which, notwithstanding their dependence upon particular statutory provisions, inform the approach taken to the construction of particular statutory provisions such as those applicable to this case. The propositions established in those cases include the following:(a)the primary function of reasons is to allow an appeal court to determine whether the decision involved appellable error and to provide procedural fairness to the litigants who are entitled to know why they have been successful or unsuccessful; (b)the statement of reasons must explain the actual path of reasoning in sufficient detail to enable a court to see whether the decision is vitiated by error; (c)reasons need not be lengthy and elaborate, nor do they require a reference to all of the evidence led or to every submission advanced by the parties; (d)there is no mechanical formula which can be applied to determine whether reasons are adequate in any particular case - much will depend upon the particular circumstances of any individual case; (e)usually it will be necessary to look at the reasons as a whole, viewed in the context of the evidence; (f)where one set of evidence is accepted over a conflicting set of significant evidence the trial judge must set out his or her findings as to how it is that one has been accepted over the other; (g)inadequacy of reasons does not necessarily amount to appellable error - rather, an appeal court will only intervene when the inadequacy is such as to give rise to a miscarriage of justice; (h)appellable error arising from inadequate reasons does not necessarily result in a new trial - in an appropriate course the appeal court may itself determine the matter. In this Tribunal's view, the reasons of Member de Villiers are seriously inadequate and do not reveal the process of reasoning undertaken particularly in relation to the various 'set­offs'. For example, the basis on which the provisional cost for water and gas was found to be 'incorrect' is not discernible at all; Mener Group at [19]. In addition, the basis on which Member de Villiers found that amounts ought to be deducted from the practical completion invoice for the installation of a hot water system and air conditioning is entirely unclear; Mener Group at [21]. In this Tribunal's view the inadequacy of Member de Villiers reasons has resulted in a miscarriage of justice. This Tribunal is unable to discern the path of reasoning undertaken by Member de Villiers and although there is no requirement to refer to all of the evidence, the reasons of Member de Villiers are devoid of any reference to evidence.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.