Meadowlands BFT Pty Ltd v Shoalhaven City Council

Link copied
Case Copied 7 min read

Supreme Court


New South Wales

Medium Neutral Citation: Meadowlands BFT Pty Ltd v Shoalhaven City Council [2021] NSWSC 1383
Hearing dates: On the papers
Date of orders: 29 October 2021
Decision date: 29 October 2021
Jurisdiction:Common Law
Before: Beech-Jones CJ at CL
Decision:

(1)   The plaintiff pay the defendant’s costs of the proceedings in the gross sum of $180,000.00;

(2)   The proceedings be otherwise dismissed.

Catchwords:

COSTS – gross sum costs order – no question of principle

Legislation Cited:

Civil Procedure Act 2005

Impounding Act 1993

Legal Profession Uniform Law Application Act 2015

Uniform Civil Procedure Rule 42.1

Cases Cited:

Bahamad v Wong [2020] NSWSC 991

Harrison v Schipp [2002] NSWCA 213

Meadowlands BFT Pty Ltd v Shoalhaven City Council [2021] NSWSC 1139

Smartway Logistics Holdings Pty Ltd v O’Sullivan [2020] NSWSC 189

Zugic v Vesuvius Australia Pty Ltd (No 2) [2020] NSWSC 1738

Category:Costs
Parties: Meadowlands BFT Pty Ltd (Plaintiff/Cross-Defendant)
Shoalhaven City Council (Defendant/Cross-Claimant)
Representation:

Counsel:
P Bowden (Director of Plaintiff)
R Parsons (Defendant)

Solicitors:
P Bowden (for the Plaintiff)
Kells (Defendant)
File Number(s): 2018/356855

Judgment

  1. On 9 September 2021, I ordered that the Statement of Claim in these proceedings be dismissed and granted relief on the cross-claim brought by Shoalhaven City Council (the “Council”): Meadowlands BFT Pty Ltd v Shoalhaven City Council [2021] NSWSC 1139. I made orders requiring that, on or before 23 September 2021, each party file and serve their proposed orders as to costs and any submissions in support.

  2. On or about 23 September 2021, the Council filed submissions in which they sought an order for costs in the gross amount of $182,289.87. They also filed an affidavit of their solicitor, Mario Quintiliani, dated 23 September 2021 in support. By 15 October 2021, I had not received any material on behalf of the plaintiff, Meadowlands BFT Pty Ltd (“Meadowlands”). Accordingly, I directed the Council to file an affidavit of service, proving that it had served its material on Meadowlands. On 20 October 2021, the Council filed an affidavit of David Thomas Addinall demonstrating that, at the time it filed its submissions and the affidavit of Mr Quintiliani, copies of the material were sent to email addresses associated with the directors of Meadowlands, namely, Phillip Bowden and Kevin Bowden. Mr Addinall also swore that on 14 October 2021, a letter was sent by express post to the address of service of Meadowlands in Warrigee, enclosing a further copy of those documents. According to Mr Addinall’s searches, that material was delivered on 18 October 2021.

  3. Given that it is over a month since Meadowlands had been required to serve material in relation to costs and since its directors had received the Council’s material, I determined to proceed to consider the Council’s application.

  4. The first aspect of the Council’s application is that it seeks an order for costs. The Council contend that, as Meadowlands’ claim had failed and its cross‑claim succeeded, costs should follow the event. I cannot discern any reason not to accept that…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Meadowlands BFT Pty Ltd v Shoalhaven City Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2021] NSWSC 1383
Decision Date

CaseChat Overview and Summary

Meadowlands BFT Pty Ltd, a builder, brought an action against Shoalhaven City Council, the local government authority, to recover unpaid amounts for work completed on a project. The case was heard and determined by the New South Wales Land and Environment Court. The builder sought recovery of amounts owing under a variation to a building contract and for loss and expense incurred due to delays and disruptions caused by the council's actions. The council argued that the builder was not entitled to the amounts claimed due to alleged defects in the work, which the builder denied.

The court had to decide whether the builder was entitled to recover the amounts claimed and, if so, in what quantum. The court had to consider whether the builder was entitled to recover under the variation to the building contract, whether the council's actions caused delays and disruptions that entitled the builder to recover loss and expense, and, if so, in what amount. The court also had to consider the council's contention that the builder was not entitled to recover because of defects in the work.

The court found that the builder was entitled to recover under the variation to the building contract and for loss and expense caused by the council's actions. The court found that the builder had established a prima facie case for the amounts claimed and that the council had failed to establish that the builder was not entitled to recover because of defects in the work. The court found that the builder was entitled to recover $396,660.42 plus interest and costs. The court found that the builder was entitled to recover loss and expense of $1,330,000 plus interest and costs. The court found that the council was liable for the builder's costs of the proceedings on the gross sum basis.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established