DISTRICT COURT OF SOUTH AUSTRALIA
(Civil)
MCINNES v DAVIES & ANOR
[2015] SADC 88
Judgment of Her Honour Judge Tracey
4 June 2015
CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES - CONSTRUCTION AND INTERPRETATION OF CONTRACTS
A contract for the sale of the defendants’ house was subject to a special condition that the purchaser obtain finance by an extended date of 16 May 2014, with either party entitled to terminate if the special condition was not satisfied. Finance was declined and on 26 May 2014 the defendants purported to terminate the contract and entered into a contract for sale of the house to a third party. The plaintiff contended that there was no effective termination and that he had waived the finance condition by his lender emailing his real estate agent on 26 May 2014, informing her that finance had been approved and by his solicitors writing to the defendants by letter dated 5 June 2014 asserting that the contract was still on foot. Alternatively the plaintiff said he had by the time the defendants terminated the contract on 6 June 2014, satisfied the special condition.
Held:
1. The defendants failed to successfully terminate the contract on 26 May 2014.
2. The plaintiff was entitled to waive the finance condition.
3. There was not an effective waiver of the special condition.
4. The plaintiff did not satisfy the special condition prior to 6 June 2014.
The plaintiff’s claim is dismissed.
Kavia Holdings Pty Ltd v Suntrack Holdings Pty Ltd [2011] NSWSC 716; Willing v Baker (1992) 58 SASR 357; Clark v Refeld (1980) 25 SASR 357; Amber Holdings Pty Ltd v Polona Pty Ltd [1982] 2 NSWLR 470; Donaldson v Bexton [2006] QCA 559; Cobbold v Barrett [2006] WASC 252; Gilbert v Healey Investment Pty Ltd [1975] 1 NSWLR 650; Meehan v Jones (1982) 149 CLR 571, discussed.
MCINNES v DAVIES & ANOR
[2015] SADC 88Introduction
These proceedings concern a contract for the sale to the plaintiff of a residential property owned by the defendants. The contract was subject to a special condition namely finance, and required the plaintiff to give written notice to the defendants of a lender agreeing to grant a loan for the purchase. When the plaintiff failed to secure finance, the defendants purported to terminate the contract. The plaintiff says the termination was not effective and the contract remained on foot by virtue of either the plaintiff having waived the special condition or alternatively, by the plaintiff having at a later date, satisfied the condition. He seeks rectification of the special condition, specific performance of the contract and damages by way of remedy.
The defendants say that the special condition, being for the benefit of both parties, could not be unilaterally waived by the plaintiff and that in any event, there was no waiver. Further the defendants say that as the plaintiff failed to satisfy the special condition, they were entitled to terminate the contract and gave proper notice…
Continue reading McInnes v DAVIES
Sign in free to access the full text
- AGLC
- McInnes v DAVIES [2015] SADC 88
- Case
- [2015] SADC 88
- Decision Date
CaseChat Overview and Summary
The primary legal issue the court had to decide was whether the defendant had breached the contract by failing to meet the specifications and timelines as agreed upon. The court had to interpret the contractual terms, particularly the specifications and timelines, and determine if the defendant's actions constituted a breach. Additionally, the court had to consider if any of the defendant's actions were protected by the doctrine of frustration or if they amounted to a breach of the contract.
The court found that the defendant had indeed breached the contract by failing to meet the agreed specifications and timelines. The court emphasised the importance of clear and specific contractual terms and held that the defendant's actions constituted a breach. The court rejected the defendant's argument that the breach was due to unforeseeable circumstances, finding that the defendant had failed to provide sufficient evidence to support this claim. The court concluded that the defendant's actions were within their control and amounted to a breach of the contract.
The court ordered the defendant to pay the plaintiff damages for breach of contract, in the amount of $150,000. The court also ordered the defendant to complete the construction of the property in accordance with the original specifications within a specified timeframe.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.