McGrath and Anor v Fleming Group Developments Pty Ltd ACN 617 721 687 and Ors (Civil Dispute)

Link copied
Case Copied 17 min read

ACT CIVIL & ADMINISTRATIVE TRIBUNAL

MCGRATH & ANOR v FLEMING GROUP DEVELOPMENTS PTY LTD ACN 617 721 687 & ORS (Civil Dispute) [2020] ACAT 47

XD 189/2020

Catchwords: CIVIL DISPUTE –– fence dispute – private nuisance – relevant consideration for replacement of a fence; aesthetics, noise abatement, safety of children and pets, privacy, durability and maintenance issues – loud air conditioner – where elevated property ‘overlooks’ adjacent property

Legislation cited:     ACT Civil and Administrative Tribunal Act 2008 ss 15, 16

Common Boundaries Act 1981 ss 5, 10, 11

Cases cited:   Bishop & Anor v Sakkara & Anor [2020] ACAT 45

Cherian v Roy [2017] ACAT 106

McGrath and Anor v ACT Planning and Land Authority and Anor [2018] ACAT 100

Tribunal:       Senior Member A Anforth

Date of Orders:  30 June 2020

Date of Reasons for Decision:         30 June 2020AUSTRALIAN CAPITAL TERRITORY          

CIVIL & ADMINISTRATIVE TRIBUNAL  XD 189/2020

BETWEEN:

ANGELA MCGRATH

First Applicant

ANDREW CROSS

Second Applicant

AND:

FLEMING GROUP DEVELOPMENTS PTY LTD ACN 617 721 687

First Respondent

IAN FLEMING

Second Respondent

SCOTT FLEMING

Third Respondent

TRIBUNAL:  Senior Member A Anforth

DATE:                  30 June 2020

ORDER

The Tribunal orders that:

1.           The applicants and the second and third respondents are to replace their common boundary fence with a 1.8m Colorbond fence (or such other height as may be determined by further order of the Tribunal) located on top of a treated wooden base spanning the length of the fence.

2.           If any party seeks to argue for a higher fence, then the party should make application to the Registrar to be heard on that issue within 7 days of receipt of this decision.

3.           The applicants and the second and third respondents are to agree to the colour or in default may seek further orders of the Tribunal on that issue within 7 days of receipt of this decision.

4.           The applicants and the second and third respondents are to accept the quote from One Way Fencing of 30 October 2019. If One Way Fencing is not prepared to adhere to that quote, then the applicants and the second and third respondents may either agree a replacement contractor or seek further order from the Tribunal that issue within 7 days of receipt of this decision.

5.           The applicants are to act as the project manager for the replacement fence.

6.           The second and third respondents are to provide all reasonable and necessary access to the applicants and tradesmen for the purpose of replacing the fence.

7.           If any problems arise with Orders 5 and 6 any party may seek further directions from the Tribunal on that issue.

8.           The application against the first respondent is dismissed.

………………………………..

Senior Member A Anforth

REASONS FOR DECISION

1.           The respondents at different times owned the same house adjacent to that of the applicants in suburban Canberra. A dispute has arisen between them concerning their common boundary fence which is now before the Tribunal to resolve under the Common Boundaries Act 1981 (

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read McGrath and Anor v Fleming Group Developments Pty Ltd ACN 61... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2020] ACAT 47
Decision Date

CaseChat Overview and Summary

McGrath and Anor v Fleming Group Developments Pty Ltd ACN 617 721 687 and Ors was a civil dispute heard by the Tribunal. The applicants, McGrath, sought to replace a boundary fence with the respondents, Fleming Group Developments Pty Ltd ACN 617 721 687 and others, due to concerns about the existing fence's condition and its impact on their property. The applicants raised issues such as aesthetics, noise abatement, safety of children and pets, privacy, durability, and maintenance. The respondents opposed the replacement and argued for a higher fence. The Tribunal was required to decide whether the applicants could replace the existing fence and, if so, what the terms of the replacement should be.

The Tribunal considered the relevant factors in deciding whether the applicants could replace the fence. These included the aesthetic impact, noise abatement, safety concerns, privacy, durability, and maintenance issues. The Tribunal found that the existing fence was inadequate and that the applicants' proposed replacement was reasonable. The Tribunal also considered the respondents' arguments for a higher fence but found that there was insufficient evidence to support such a claim. The Tribunal emphasised the need for the parties to cooperate in replacing the fence and managing any issues that arose during the process.

The Tribunal ordered that the applicants and the respondents replace the common boundary fence with a 1.8m Colorbond fence on top of a treated wooden base. The Tribunal set out detailed terms for the replacement, including the project manager, access, and dispute resolution. The Tribunal also made orders to ensure that the parties cooperated in replacing the fence and managing any issues that arose during the process. The Tribunal dismissed the application against the first respondent as it was not necessary to make orders against that party.

The Tribunal's orders provided a clear framework for replacing the fence and managing any issues that arose during the process. The orders emphasised the need for the parties to cooperate and resolve any disputes through the Tribunal. The orders also provided for flexibility in case any issues arose during the replacement process. Overall, the Tribunal's decision provided a fair and reasonable outcome for both parties.

Orders

Orders of the court

The Tribunal orders that:

1. The applicants and the second and third respondents are to replace their common boundary fence with a 1.8m Colorbond fence (or such other height as may be determined by further order of the Tribunal) located on top of a treated wooden base spanning the length of the fence.

2. If any party seeks to argue for a higher fence, then the party should make application to the Registrar to be heard on that issue within 7 days of receipt of this decision.

3. The applicants and the second and third respondents are to agree to the colour or in default may seek further orders of the Tribunal on that issue within 7 days of receipt of this decision.

4. The applicants and the second and third respondents are to accept the quote from One Way Fencing of 30 October 2019. If One Way Fencing is not prepared to adhere to that quote, then the applicants and the second and third respondents may either agree a replacement contractor or seek further order from the Tribunal that issue within 7 days of receipt of this decision.

5. The applicants are to act as the project manager for the replacement fence.

6. The second and third respondents are to provide all reasonable and necessary access to the applicants and tradesmen for the purpose of replacing the fence.

7. If any problems arise with Orders 5 and 6 any party may seek further directions from the Tribunal on that issue.

8. The application against the first respondent is dismissed.

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established