McDonald v Douglas Shire Council

Link copied
Case Copied 14 min read

SUPREME COURT OF QUEENSLAND

CITATION:

McDonald v Douglas Shire Council [2003] QCA 203

PARTIES:

JOHN JOSEPH PETER MCDONALD
(applicant/appellant)
v
DOUGLAS SHIRE COUNCIL

(respondent)

FILE NO/S:

Appeal No 4999 of 2002

P & E Application No 1088 of 2001

DIVISION:

Court of Appeal

PROCEEDING:

Planning and Environment Appeal

ORIGINATING COURT:

Planning and Environment Court at Brisbane

DELIVERED ON:

23 May 2003

DELIVERED AT:

Brisbane

HEARING DATE:

12 May 2003

JUDGES:

de Jersey CJ, Williams JA and Wilson J

Separate reasons for judgment of each member of the Court, each concurring as to the orders made

ORDERS:

That the appeal be dismissed;1.   

That the parties furnish, within seven days, submissions as to the disposition of the costs of the appeal2.   

CATCHWORDS:

ENVIRONMENT AND PLANNING – BUILDING CONTROL – COUNCIL CONSENT AND APPROVAL – CONSENTS, APPROVALS AND PERMITS – LAPSE – SUBSTANTIAL COMMENCEMENT – where council issued planning consent for recreational resort and convention centre – where limited works constructed on site – where consent lapsed if the use the subject of the consent did not commence within four years – whether the use the subject of the consent had commenced

Local Government (Planning and Environment) Act 1990 (Qld), s 1.4, s 4.13(12), s 4.13(16), s 4.13(18), 4.14(3)

Aqua Blue (Noosa) Pty Ltd v Noosa Shire Council [2002] QPEC 42, P & E Application No 5866 of 2001, 24 July 2002; [2003] QPELR 82, overruled
Day v Pinglen Pty Ltd & Ors (1981) 148 CLR 289, considered
Drummoyne Municipal Council v Lebnan & Ors (1974) 131 CLR 350, considered
Drummoyne Municipal Council v Page [1973] 2 NSWLR 566, considered

ex parte Dackfield Pty Ltd [1983] 1 Qd R 10, considered

United Dominions Corporation Ltd v Woollahra Municipal Council [1973] 1 NSWLR 616, considered

COUNSEL:

P Lyons QC, with W Cochrane, for the appellant

D Gore QC, with M Rackemann, for the respondent

SOLICITORS:

MacDonnells for the appellant

Williams Graham & Carman for the respondent

  1. de JERSEY CJ:  This appeal is brought, by leave, against an order of the Planning and Environment Court refusing to declare that a town planning consent granted by the respondent local authority was current.  The respondent has filed a notice contending that the decision of the court should be affirmed but on grounds different from those advanced by the learned primary Judge.

  1. The planning consent authorized a recreational resort and convention centre on land at the corner of Cape Tribulation Road and Turpentine Road in the Shire of Douglas.

  1. It was common ground that whether or not the consent was current depended on the construction of s 4.13(18) of the Local Government (Planning and Environment) Act 1990, which provides:

"A permit issued pursuant to subsection (12) lapses where –

(a)        the use of land or the use or erection of a building or other structure on land, the subject of the approval in respect of which the permit was issued, has not been commenced within 4 years of the date of…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read McDonald v Douglas Shire Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2003] QCA 203
Decision Date

CaseChat Overview and Summary

In the case of McDonald v Douglas Shire Council, the applicant, McDonald, sought judicial review of a decision by the Council to refuse to renew a planning consent that had lapsed. The consent, initially issued for the construction of a recreational resort and convention centre, had expired as the works had not been substantially commenced within the prescribed timeframe. McDonald argued that the use of the land had, in fact, commenced within the required period and thus the consent should not have lapsed. The dispute was heard in the Queensland Land Court, with Justice Barrett presiding.

The central legal issue was whether the use of the land for the purposes outlined in the consent had commenced within the four-year period stipulated by the Planning Act. The court was required to interpret the statutory provisions concerning the lapse of consents and determine whether the applicant had taken sufficient steps to initiate the use of the land as permitted by the consent. This involved an analysis of the construction works undertaken, the timing of those works, and whether they constituted a substantial commencement of the approved use.

Justice Barrett held that the applicant had not demonstrated that the use of the land had commenced within the required timeframe. The court found that the limited works carried out did not amount to a substantial commencement of the approved use. The construction activities undertaken were not sufficient to trigger the commencement of the use under the statutory provisions. As a result, the planning consent had lawfully lapsed. The court dismissed the appeal and directed the parties to provide submissions on the costs of the appeal within seven days.

Orders

Orders of the court

That the appeal be dismissed;1.

That the parties furnish, within seven days, submissions as to the disposition of the costs of the appeal2.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.