| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMON LAW DIVISION
BUILDING CASES LIST
No. 7012 of 2006
| McCONNELL DOWELL CONSTRUCTORS (AUST) PTY LTD (ACN 008 444 880) | Plaintiff |
| v | |
| GAS TRANSMISSION SERVICES WA (OPERATIONS) PTY LTD (ACN 106 043 332) AND ORS | Defendants |
---
JUDGE: | HARGRAVE J | |
WHERE HELD: | Melbourne | |
DATE OF HEARING: | 18 October 2006 | |
DATE OF JUDGMENT: | 8 November 2006 | |
CASE MAY BE CITED AS: | McConnell Dowell Constructors v Gas Transmission Services | |
MEDIUM NEUTRAL CITATION: | [2006] VSC 411 | First Revision |
---
Stay of Proceeding – dispute resolution clause in agreement requiring expert determination – whether clause applicable to dispute – dispute resolution clause capable of applying to only some issues in the proceeding – exercise of discretion – stay application refused.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Dr C Pannam QC and Mr A Neal | Clayton Utz |
| For the First Defendant | Mr H Foxcroft SC and Dr M Collins | Mallesons Stephen Jaques |
| For the Third Defendant | Mr D Collins SC and K Lyons | MolinoCahill Lawyers |
HIS HONOUR:
Introduction
Newcrest Mining Ltd operates a gold and copper mine at Telfer in Western Australia. By a “Gas Transport Agreement” dated 13 October 2003 between Newcrest and Gas Transmission Services WA (Operations) Pty Ltd, Gas Transmission agreed to design, construct, own and operate a buried gas pipeline to supply gas to a gas fuelled power station which would supply electrical power to the Telfer Mine.
By an “EPC Contract” dated 10 October 2003, Gas Transmission engaged McConnell Dowell Constructors (Aust) Pty Ltd to engineer, procure, construct and commission the gas pipeline. The EPC Contract was, in effect, a subcontract in respect of the design and construct obligations of Gas Transmission under the Gas Transport Agreement - or “GTA” as that contract is called in the EPC Contract.
Although the two contracts were apparently negotiated in tandem, the nicknames of Gas Transmission and McConnell Dowell in the two contracts are, confusingly, different:
(1)Gas Transmission is called “the Supplier” in the Gas Transport Agreement, and “OpCo” in the EPC Contract.
(2)McConnell Dowell is called McConnell Dowell in the Gas Transport Agreement, and “the Contractor” in the EPC Contract.
As will appear, this is by no means the only source of confusion arising from differences between the two contracts.
During the construction of the gas pipeline, the works were substantially affected by two cyclones – “Cyclone Monty” and “Cyclone Fay”.
In this proceeding, McConnell Dowell raises a number of claims against Gas Transmission. Some of the claims are for extra costs arising out of the two cyclones. There are also claims for extensions of time and other relief. Some incidental claims are made against Newcrest directly.
Apart from the statement of claim, there are no pleadings. The full scope of the issues is yet to be defined.
Gas Transmission has applied to stay the whole of this proceeding until the completion of an expert determination procedure provided for under the contracts. In summary, it was submitted on behalf of Gas…
Keep reading for free
Create a free CaseChat account to read McConnell Dowell Constructors (Aust) Pty Ltd v Gas Transmiss... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2006] VSC 411
- Decision Date
CaseChat Overview and Summary
The court was tasked with determining whether the dispute resolution clause in the agreement was applicable to the present dispute and, if so, whether it could apply to only some of the issues raised by the plaintiff. The defendants argued that the clause was not applicable, while the plaintiffs contended that it was. The court's decision hinged on the interpretation of the clause and its scope, as well as the exercise of discretion in determining whether to grant a stay of the proceedings pending expert determination.
After considering the arguments and the nature of the clause, the court found that the dispute resolution clause was indeed applicable to the dispute at hand. However, the clause could only be applied to some of the issues raised by the plaintiff. The court exercised its discretion and refused the application for a stay of the proceeding, allowing the case to proceed in the Federal Court. The reasoning behind this decision was based on the court's assessment that the specific issues which the clause applied to were not suitable for expert determination at that stage of the proceedings. The court also considered the broader implications for the efficiency of the legal process and the rights of the parties involved.